Projects / Atmos Silverwoods
+ Compare with another project

Atmos Silverwoods

Bengaluru Urban · ATMOS CONSTRUCTIONS PRIVATE LIMITED PRM/KA/RERA/1251/472/PR/080823/006129
On track · 39% built
Filed — · Q1 2026-27
Fund safety: no flags
Construction
39%
complete
Sold
60
of 76 total units
Available
16
units
4 BHK: 16
Complaints
0
on project
Construction progress
% complete per quarter
Sales velocity
Units sold per quarter · cumulative booked (line)
Inventory drain
Available units over time
Show financial data (advance collected vs withdrawn)
Quarterly financials
₹ Crore — advance collected vs amount withdrawn this quarter

Quarter-wise Tower Data

Filed: 2026-07-15 · Project 39% complete
A 68% complete
Unit type Total Booked Available
4 BHK 10 10 0
Parking 20 20 —
Floor completion
Floor 0
100.0%
Floor 1
100.0%
Floor 2
100.0%
B 68% complete
Unit type Total Booked Available
4 BHK 30 25 5
Parking 60 50 10
Floor completion
Floor 0
100.0%
Floor 1
100.0%
Floor 2
100.0%
C 65% complete
Unit type Total Booked Available
4 BHK 27 18 9
Parking 54 36 18
Floor completion
Floor 0
100.0%
Floor 1
100.0%
Floor 2
100.0%
D 70% complete
Unit type Total Booked Available
4 BHK 2 — 2
Parking 4 — 4
Floor completion
Floor 0
100.0%
Floor 1
100.0%
Floor 2
100.0%
E 66% complete
Unit type Total Booked Available
4 BHK 7 7 0
Parking 14 14 —
Floor completion
Floor 0
100.0%
Floor 1
100.0%
Floor 2
100.0%

Unit Specifications

Unit type Carpet area (sqft) Units
4 BHK 2,237–2,945 152 Estimate ROI →
Show escrow account details
Escrow Accounts
Bank
HDFC
Branch
Malleshwaram
IFSC
HDFC0000041
70% Collection A/C
50200079006510

Registration Extension Extension granted

Promoters can apply for a Section 6 extensionA formal application under RERA Section 6 for more time to complete the project, requiring a stated reason — distinct from the automatic, government-wide Covid extension every project received. when they can't meet the originally registered completion date.

Promoter's stated reason for delay: others, Shortage of Building Materials, Concrete, Jalli etc, Shortage of Labour, Transport strike - Delay in Delivery of Material, Force Majeure

Event Start date Proposed completion
At the time of Registration 2023-06-01 2026-05-31 Certificate →
Section 6 Extension 2026-05-31 2027-05-31 Certificate →
Extension applied on
2026-03-30
Extension approved on
2026-04-18
Extension registration no.
EX/PRM/KA/RERA/1251/472/PR/260418/006129

Project details

Registration no.
PRM/KA/RERA/1251/472/PR/080823/006129
District
Bengaluru Urban
Taluk
Yelahanka
Promoter
ATMOS CONSTRUCTIONS PRIVATE LIMITED
Firm type
Company
PAN
AAXCA9384P
GSTIN
29AAXCA9384P1Z7
Total units
76
Project start
2023-06-01
FAR sanctioned
1.04
Land/property litigation
No
Proposed completion
2027-05-31
Project address
Survey No.126/5, 126/10, 126/6, 126/7, 126/12, 125/2A, 125/3 of Arekere Village Hesargatta Hobli , Yelahanka Taluk, Bengaluru Urban District , Yelahanka , Bengaluru Urban, Karnataka - 562157

Buyer Risk Report

1 risk signal detected from this project's K-RERA quarterly filings.

Sign in free — no password — to see exactly which quarters and complaints triggered these flags.

Sign in to see full details →
Show documents on file with K-RERA (157)
Documents on file
Government NOCs
BESCOM (electricity) on file
BWSSB (water & sewerage) not found
Fire NOC not found
KSPCB (pollution control) on file
SEIAA (environmental clearance) not found
Airport / Air Force NOC not found
Telecom (BSNL) NOC not found
Lift license not found
RERA statutory forms
Form-1 (project registration) not found
Form-2/3 (CA certificate) on file
Form-B / Sec 3(1) affidavit on file
Company KYC
Certificate of incorporation not found
GST certificate not found
PAN card on file
Partnership deed / firm registration not found
Promoter financials
8 on file
Legal / land documents
37 on file
Other documents
49 on file · 26 marked not available
Plan approvals
9 on file
Sale/allotment documents
3 on file · 1 marked not available
Site photographs
1 on file
Technical certificates
6 on file
Inventory of documents the promoter has uploaded to their K-RERA project page — not a review of their contents. "Not found" means no filed document matched that item by name; it doesn't necessarily apply to every project (e.g. an airport-proximity NOC).

Frequently Asked Questions

Based on K-RERA registered data for Atmos Silverwoods
Is Atmos Silverwoods RERA registered in Karnataka?

Yes. Atmos Silverwoods is registered with the Karnataka Real Estate Regulatory Authority (K-RERA) under registration number PRM/KA/RERA/1251/472/PR/080823/006129.

What is the RERA registration number of Atmos Silverwoods?

The K-RERA registration number of Atmos Silverwoods is PRM/KA/RERA/1251/472/PR/080823/006129.

What is the current construction status of Atmos Silverwoods?

As of Q1 2026-27, Atmos Silverwoods is 39% complete according to its latest K-RERA quarterly filing.

Are flats still available in Atmos Silverwoods?

Yes. As per the latest K-RERA quarterly filing (Q1 2026-27), Atmos Silverwoods has 16 unit(s) available for purchase.

How many flats have been sold in Atmos Silverwoods?

As per the latest K-RERA filing (Q1 2026-27), 60 out of 76 units in Atmos Silverwoods have been sold or booked.

Are 4 BHK flats available in Atmos Silverwoods?

Yes. According to the latest K-RERA quarterly filing, there are 16 4 BHK unit(s) available in Atmos Silverwoods, Bengaluru Urban.

Are there any RERA complaints against Atmos Silverwoods?

As per K-RERA data tracked by rera.watch, there are no complaints currently recorded against Atmos Silverwoods.

How many RERA complaints does ATMOS CONSTRUCTIONS PRIVATE LIMITED have?

ATMOS CONSTRUCTIONS PRIVATE LIMITED, the builder/promoter of Atmos Silverwoods, has 0 complaint(s) filed against them across all their K-RERA registered projects in Karnataka.

Who is the builder or developer of Atmos Silverwoods?

Atmos Silverwoods is developed by ATMOS CONSTRUCTIONS PRIVATE LIMITED, a company registered with K-RERA in Bengaluru Urban, Karnataka.

When did Atmos Silverwoods last file a quarterly update with K-RERA?

Atmos Silverwoods last filed a quarterly update for Q1 2026-27 on 2026-07-15. The project has submitted 3 quarterly report(s) on K-RERA to date.