Projects / Rohan Upavan Phase 1, Phase 2, Phase 3A, Phase 3, Phase 4, Phase 5
+ Compare with another project

Rohan Upavan Phase 1, Phase 2, Phase 3A, Phase 3, Phase 4, Phase 5

Bengaluru Urban · Rohan Builders PRM/KA/RERA/1251/446/PR/200423/005890
On track · 86% built
Filed — · Q4 2025-26
Construction
86%
complete
Sold
276
of 283 total units
Available
7
units
1.5 BHK: 0
2 BHK: 30
2.5 BHK: 6
3 BHK: 6
Complaints
0
on project · 1 on builder
Construction progress
% complete per quarter
Sales velocity
Units sold per quarter · cumulative booked (line)
Inventory drain
Available units over time
Show financial data (advance collected vs withdrawn)
Quarterly financials
₹ Crore — advance collected vs amount withdrawn this quarter

Quarter-wise Tower Data

Filed: 2026-04-15 · Project 86% complete
Wing A 95% complete
Unit type Total Booked Available
2 BHK 61 57 4
2 BHK 61 57 4
2 BHK 61 57 4
2 BHK 61 57 4
2 BHK 61 57 4
2 BHK 61 57 4
2.5 BHK 21 20 1
2.5 BHK 21 20 1
2.5 BHK 21 20 1
2.5 BHK 21 20 1
2.5 BHK 21 20 1
2.5 BHK 21 20 1
Parking 82 77 5
Floor completion
Floor 0
100.0%
Floor 0
100.0%
Floor 0
100.0%
Floor 0
100.0%
Floor 0
100.0%
Floor 1
100.0%
Floor 1
100.0%
Floor 1
100.0%
Floor 1
100.0%
Floor 1
100.0%
Floor 2
100.0%
Floor 2
100.0%
Floor 2
100.0%
Floor 2
100.0%
Floor 2
100.0%
Floor 3
100.0%
Floor 3
100.0%
Floor 3
100.0%
Floor 3
100.0%
Floor 3
100.0%
Floor 4
100.0%
Floor 4
100.0%
Floor 4
100.0%
Floor 4
100.0%
Floor 4
100.0%
Floor 5
100.0%
Floor 5
100.0%
Floor 5
100.0%
Floor 5
100.0%
Floor 5
100.0%
Floor 6
100.0%
Floor 6
100.0%
Floor 6
100.0%
Floor 6
100.0%
Floor 6
100.0%
Floor 7
100.0%
Floor 7
100.0%
Floor 7
100.0%
Floor 7
100.0%
Floor 7
100.0%
Floor 8
100.0%
Floor 8
100.0%
Floor 8
100.0%
Floor 8
100.0%
Floor 8
100.0%
Floor 9
100.0%
Floor 9
100.0%
Floor 9
100.0%
Floor 9
100.0%
Floor 9
100.0%
Floor 10
100.0%
Floor 10
100.0%
Floor 10
100.0%
Floor 10
100.0%
Floor 10
100.0%
Floor 11
100.0%
Floor 11
100.0%
Floor 11
100.0%
Floor 11
100.0%
Floor 11
100.0%
Floor 12
100.0%
Floor 12
100.0%
Floor 12
100.0%
Floor 12
100.0%
Floor 12
100.0%
Floor 13
100.0%
Floor 13
100.0%
Floor 13
100.0%
Floor 13
100.0%
Floor 13
100.0%
Floor 14
100.0%
Floor 14
100.0%
Floor 14
100.0%
Floor 14
100.0%
Floor 14
100.0%
Floor 15
100.0%
Floor 15
100.0%
Floor 15
100.0%
Floor 15
100.0%
Floor 15
100.0%
Floor 16
100.0%
Floor 16
100.0%
Floor 16
100.0%
Floor 16
100.0%
Floor 16
100.0%
Floor 17
100.0%
Floor 17
100.0%
Floor 17
100.0%
Floor 17
100.0%
Floor 17
100.0%
Floor 18
100.0%
Floor 18
100.0%
Floor 18
100.0%
Floor 18
100.0%
Floor 18
100.0%
Floor 19
100.0%
Floor 19
100.0%
Floor 19
100.0%
Floor 19
100.0%
Floor 19
100.0%
Floor 20
100.0%
Floor 20
100.0%
Floor 20
100.0%
Floor 20
100.0%
Floor 20
100.0%
Floor 21
100.0%
Floor 21
100.0%
Floor 21
100.0%
Floor 21
100.0%
Floor 21
100.0%
Wing B 95% complete
Unit type Total Booked Available
1.5 BHK 79 79 0
1.5 BHK 79 79 0
1.5 BHK 79 79 0
1.5 BHK 79 79 0
1.5 BHK 79 79 0
1.5 BHK 79 79 0
2 BHK 40 39 1
2 BHK 40 39 1
2 BHK 40 39 1
2 BHK 40 39 1
2 BHK 40 39 1
2 BHK 40 39 1
Parking 119 118 1
Floor completion
Floor 0
100.0%
Floor 0
100.0%
Floor 0
100.0%
Floor 0
100.0%
Floor 0
100.0%
Floor 1
100.0%
Floor 1
100.0%
Floor 1
100.0%
Floor 1
100.0%
Floor 1
100.0%
Floor 2
100.0%
Floor 2
100.0%
Floor 2
100.0%
Floor 2
100.0%
Floor 2
100.0%
Floor 3
100.0%
Floor 3
100.0%
Floor 3
100.0%
Floor 3
100.0%
Floor 3
100.0%
Floor 4
100.0%
Floor 4
100.0%
Floor 4
100.0%
Floor 4
100.0%
Floor 4
100.0%
Floor 5
100.0%
Floor 5
100.0%
Floor 5
100.0%
Floor 5
100.0%
Floor 5
100.0%
Floor 6
100.0%
Floor 6
100.0%
Floor 6
100.0%
Floor 6
100.0%
Floor 6
100.0%
Floor 7
100.0%
Floor 7
100.0%
Floor 7
100.0%
Floor 7
100.0%
Floor 7
100.0%
Floor 8
100.0%
Floor 8
100.0%
Floor 8
100.0%
Floor 8
100.0%
Floor 8
100.0%
Floor 9
100.0%
Floor 9
100.0%
Floor 9
100.0%
Floor 9
100.0%
Floor 9
100.0%
Floor 10
100.0%
Floor 10
100.0%
Floor 10
100.0%
Floor 10
100.0%
Floor 10
100.0%
Floor 11
100.0%
Floor 11
100.0%
Floor 11
100.0%
Floor 11
100.0%
Floor 11
100.0%
Floor 12
100.0%
Floor 12
100.0%
Floor 12
100.0%
Floor 12
100.0%
Floor 12
100.0%
Floor 13
100.0%
Floor 13
100.0%
Floor 13
100.0%
Floor 13
100.0%
Floor 13
100.0%
Floor 14
100.0%
Floor 14
100.0%
Floor 14
100.0%
Floor 14
100.0%
Floor 14
100.0%
Floor 15
100.0%
Floor 15
100.0%
Floor 15
100.0%
Floor 15
100.0%
Floor 15
100.0%
Floor 16
100.0%
Floor 16
100.0%
Floor 16
100.0%
Floor 16
100.0%
Floor 16
100.0%
Floor 17
100.0%
Floor 17
100.0%
Floor 17
100.0%
Floor 17
100.0%
Floor 17
100.0%
Floor 18
100.0%
Floor 18
100.0%
Floor 18
100.0%
Floor 18
100.0%
Floor 18
100.0%
Floor 19
100.0%
Floor 19
100.0%
Floor 19
100.0%
Floor 19
100.0%
Floor 19
100.0%
Floor 20
100.0%
Floor 20
100.0%
Floor 20
100.0%
Floor 20
100.0%
Floor 20
100.0%
Floor 21
100.0%
Floor 21
100.0%
Floor 21
100.0%
Floor 21
100.0%
Floor 21
100.0%
Wing C 95% complete
Unit type Total Booked Available
2 BHK 23 23 0
2 BHK 23 23 0
2 BHK 23 23 0
2 BHK 23 23 0
2 BHK 23 23 0
2 BHK 23 23 0
2.5 BHK 19 19 0
2.5 BHK 19 19 0
2.5 BHK 19 19 0
2.5 BHK 19 19 0
2.5 BHK 19 19 0
2.5 BHK 19 19 0
3 BHK 40 39 1
3 BHK 40 39 1
3 BHK 40 39 1
3 BHK 40 39 1
3 BHK 40 39 1
3 BHK 40 39 1
Parking 82 81 1
Floor completion
Floor 0
100.0%
Floor 0
100.0%
Floor 0
100.0%
Floor 0
100.0%
Floor 0
100.0%
Floor 1
100.0%
Floor 1
100.0%
Floor 1
100.0%
Floor 1
100.0%
Floor 1
100.0%
Floor 2
100.0%
Floor 2
100.0%
Floor 2
100.0%
Floor 2
100.0%
Floor 2
100.0%
Floor 3
100.0%
Floor 3
100.0%
Floor 3
100.0%
Floor 3
100.0%
Floor 3
100.0%
Floor 4
100.0%
Floor 4
100.0%
Floor 4
100.0%
Floor 4
100.0%
Floor 4
100.0%
Floor 5
100.0%
Floor 5
100.0%
Floor 5
100.0%
Floor 5
100.0%
Floor 5
100.0%
Floor 6
100.0%
Floor 6
100.0%
Floor 6
100.0%
Floor 6
100.0%
Floor 6
100.0%
Floor 7
100.0%
Floor 7
100.0%
Floor 7
100.0%
Floor 7
100.0%
Floor 7
100.0%
Floor 8
100.0%
Floor 8
100.0%
Floor 8
100.0%
Floor 8
100.0%
Floor 8
100.0%
Floor 9
100.0%
Floor 9
100.0%
Floor 9
100.0%
Floor 9
100.0%
Floor 9
100.0%
Floor 10
100.0%
Floor 10
100.0%
Floor 10
100.0%
Floor 10
100.0%
Floor 10
100.0%
Floor 11
100.0%
Floor 11
100.0%
Floor 11
100.0%
Floor 11
100.0%
Floor 11
100.0%
Floor 12
100.0%
Floor 12
100.0%
Floor 12
100.0%
Floor 12
100.0%
Floor 12
100.0%
Floor 13
100.0%
Floor 13
100.0%
Floor 13
100.0%
Floor 13
100.0%
Floor 13
100.0%
Floor 14
100.0%
Floor 14
100.0%
Floor 14
100.0%
Floor 14
100.0%
Floor 14
100.0%
Floor 15
100.0%
Floor 15
100.0%
Floor 15
100.0%
Floor 15
100.0%
Floor 15
100.0%
Floor 16
100.0%
Floor 16
100.0%
Floor 16
100.0%
Floor 16
100.0%
Floor 16
100.0%
Floor 17
100.0%
Floor 17
100.0%
Floor 17
100.0%
Floor 17
100.0%
Floor 17
100.0%
Floor 18
100.0%
Floor 18
100.0%
Floor 18
100.0%
Floor 18
100.0%
Floor 18
100.0%
Floor 19
100.0%
Floor 19
100.0%
Floor 19
100.0%
Floor 19
100.0%
Floor 19
100.0%
Floor 20
100.0%
Floor 20
100.0%
Floor 20
100.0%
Floor 20
100.0%
Floor 20
100.0%
Floor 21
100.0%
Floor 21
100.0%
Floor 21
100.0%
Floor 21
100.0%
Floor 21
100.0%
Floor 22
100.0%
Floor 22
100.0%
Floor 22
100.0%
Floor 22
100.0%
Floor 22
100.0%

Unit Specifications

Unit type Carpet area (sqft) Units
1.5 BHK 445–462 158 Estimate ROI →
2 BHK 699–803 248 Estimate ROI →
2.5 BHK 858–949 80 Estimate ROI →
3 BHK 956–1,074 80 Estimate ROI →
Show escrow account details
Escrow Accounts
Bank
State Bank of Mauritius Ltd.
Branch
ULSOOR ROAD
IFSC
STCB0000065
70% Collection A/C
20062400604282
100% A/C
20062400604305
30% A/C
20062300593525

Project details

Registration no.
PRM/KA/RERA/1251/446/PR/200423/005890
District
Bengaluru Urban
Taluk
Bengaluru East
Promoter
Rohan Builders
Firm type
Partnership Firm
PAN
AABFR4467K
GSTIN
29AABFR4467K1ZQ
Total units
283
Total cost
₹156.61 Cr
Project start
2023-03-15
FAR sanctioned
2.99
Proposed completion
2027-03-31
Project address
KHATA NO. 43, SY NO. 49/2, 48/4A, 48/4B, 48/3, 48/6, 48/1 & 48/5 WARD NO. 25, KYALASANAHALLI VILLAGE, HORAMAVU SUB DIVISION, MAHADEVAPURA ZONE, KR PURAM HOBLI.

Frequently Asked Questions

Based on K-RERA registered data for Rohan Upavan Phase 1, Phase 2, Phase 3A, Phase 3, Phase 4, Phase 5
Is Rohan Upavan Phase 1, Phase 2, Phase 3A, Phase 3, Phase 4, Phase 5 RERA registered in Karnataka?

Yes. Rohan Upavan Phase 1, Phase 2, Phase 3A, Phase 3, Phase 4, Phase 5 is registered with the Karnataka Real Estate Regulatory Authority (K-RERA) under registration number PRM/KA/RERA/1251/446/PR/200423/005890.

What is the RERA registration number of Rohan Upavan Phase 1, Phase 2, Phase 3A, Phase 3, Phase 4, Phase 5?

The K-RERA registration number of Rohan Upavan Phase 1, Phase 2, Phase 3A, Phase 3, Phase 4, Phase 5 is PRM/KA/RERA/1251/446/PR/200423/005890.

What is the current construction status of Rohan Upavan Phase 1, Phase 2, Phase 3A, Phase 3, Phase 4, Phase 5?

As of Q4 2025-26, Rohan Upavan Phase 1, Phase 2, Phase 3A, Phase 3, Phase 4, Phase 5 is 86% complete according to its latest K-RERA quarterly filing.

Are flats still available in Rohan Upavan Phase 1, Phase 2, Phase 3A, Phase 3, Phase 4, Phase 5?

Yes. As per the latest K-RERA quarterly filing (Q4 2025-26), Rohan Upavan Phase 1, Phase 2, Phase 3A, Phase 3, Phase 4, Phase 5 has 7 unit(s) available for purchase.

How many flats have been sold in Rohan Upavan Phase 1, Phase 2, Phase 3A, Phase 3, Phase 4, Phase 5?

As per the latest K-RERA filing (Q4 2025-26), 276 out of 283 units in Rohan Upavan Phase 1, Phase 2, Phase 3A, Phase 3, Phase 4, Phase 5 have been sold or booked.

Are 2 BHK flats available in Rohan Upavan Phase 1, Phase 2, Phase 3A, Phase 3, Phase 4, Phase 5?

Yes. According to the latest K-RERA quarterly filing, there are 30 2 BHK unit(s) available in Rohan Upavan Phase 1, Phase 2, Phase 3A, Phase 3, Phase 4, Phase 5, Bengaluru Urban.

Are 2.5 BHK flats available in Rohan Upavan Phase 1, Phase 2, Phase 3A, Phase 3, Phase 4, Phase 5?

Yes. According to the latest K-RERA quarterly filing, there are 6 2.5 BHK unit(s) available in Rohan Upavan Phase 1, Phase 2, Phase 3A, Phase 3, Phase 4, Phase 5, Bengaluru Urban.

Are 3 BHK flats available in Rohan Upavan Phase 1, Phase 2, Phase 3A, Phase 3, Phase 4, Phase 5?

Yes. According to the latest K-RERA quarterly filing, there are 6 3 BHK unit(s) available in Rohan Upavan Phase 1, Phase 2, Phase 3A, Phase 3, Phase 4, Phase 5, Bengaluru Urban.

Are there any RERA complaints against Rohan Upavan Phase 1, Phase 2, Phase 3A, Phase 3, Phase 4, Phase 5?

As per K-RERA data tracked by rera.watch, there are no complaints currently recorded against Rohan Upavan Phase 1, Phase 2, Phase 3A, Phase 3, Phase 4, Phase 5.

How many RERA complaints does Rohan Builders have?

Rohan Builders, the builder/promoter of Rohan Upavan Phase 1, Phase 2, Phase 3A, Phase 3, Phase 4, Phase 5, has 1 complaint(s) filed against them across all their K-RERA registered projects in Karnataka.

Who is the builder or developer of Rohan Upavan Phase 1, Phase 2, Phase 3A, Phase 3, Phase 4, Phase 5?

Rohan Upavan Phase 1, Phase 2, Phase 3A, Phase 3, Phase 4, Phase 5 is developed by Rohan Builders, a partnership firm registered with K-RERA in Bengaluru Urban, Karnataka.

When did Rohan Upavan Phase 1, Phase 2, Phase 3A, Phase 3, Phase 4, Phase 5 last file a quarterly update with K-RERA?

Rohan Upavan Phase 1, Phase 2, Phase 3A, Phase 3, Phase 4, Phase 5 last filed a quarterly update for Q4 2025-26 on 2026-04-15. The project has submitted 2 quarterly report(s) on K-RERA to date.