Projects / Sowparnika Life On The Green
+ Compare with another project

Sowparnika Life On The Green

Bengaluru Urban · SOWPARNIKA SUPERTECH PRIVATE LIMITED PRM/KA/RERA/1251/308/PR/090523/005925
Delivered · 100% built
Filed — · Q4 2025-26
Construction
100%
complete
Sold
of ? total units
Available
0
units
Complaints
0
on project
Construction progress
% complete per quarter
Sales velocity
Units sold per quarter · cumulative booked (line)
Inventory drain
Available units over time
Show financial data (advance collected vs withdrawn)
Quarterly financials
₹ Crore — advance collected vs amount withdrawn this quarter

Quarter-wise Tower Data

Filed: 2026-04-15 · Project 100% complete

No tower breakdown recorded for this quarter.

Show escrow account details
Escrow Accounts
Bank
HDFC
Branch
OLD AIRPORT ROAD
IFSC
HDFC0000075
70% Collection A/C
57500001179522

Project details

Registration no.
PRM/KA/RERA/1251/308/PR/090523/005925
District
Bengaluru Urban
Taluk
Anekal
Promoter
SOWPARNIKA SUPERTECH PRIVATE LIMITED
Firm type
Company
PAN
ABGCS8220G
GSTIN
9ABGCS8220G1Z6
Total cost
₹59.83 Cr
Project start
2023-04-10
Land/property litigation
No
Proposed completion
2026-04-09
Project address
Sy. No. 72/1, 72/2, 80/4, 80/7, 81 and 88 , Bidaraguppe Village , Anekal , Bengaluru Urban, Karnataka - 562107
Show documents on file with K-RERA (107)
Documents on file
Government NOCs
BESCOM (electricity) on file
BWSSB (water & sewerage) not found
Fire NOC not found
KSPCB (pollution control) not found
SEIAA (environmental clearance) not found
Airport / Air Force NOC not found
Telecom (BSNL) NOC not found
Lift license not found
RERA statutory forms
Form-1 (project registration) on file
Form-2/3 (CA certificate) on file
Form-B / Sec 3(1) affidavit on file
Company KYC
Certificate of incorporation not found
GST certificate on file
PAN card not found
Partnership deed / firm registration not found
Promoter financials
5 on file
Legal / land documents
14 on file
Other documents
19 on file · 36 marked not available
Plan approvals
7 on file
Sale/allotment documents
2 on file
Site photographs
1 on file
Technical certificates
1 on file
Inventory of documents the promoter has uploaded to their K-RERA project page — not a review of their contents. "Not found" means no filed document matched that item by name; it doesn't necessarily apply to every project (e.g. an airport-proximity NOC).

Frequently Asked Questions

Based on K-RERA registered data for Sowparnika Life On The Green
Is Sowparnika Life On The Green RERA registered in Karnataka?

Yes. Sowparnika Life On The Green is registered with the Karnataka Real Estate Regulatory Authority (K-RERA) under registration number PRM/KA/RERA/1251/308/PR/090523/005925.

What is the RERA registration number of Sowparnika Life On The Green?

The K-RERA registration number of Sowparnika Life On The Green is PRM/KA/RERA/1251/308/PR/090523/005925.

What is the current construction status of Sowparnika Life On The Green?

As of Q4 2025-26, Sowparnika Life On The Green is 100% complete — construction has finished according to its latest K-RERA quarterly filing.

Are flats still available in Sowparnika Life On The Green?

As per the latest K-RERA filing (Q4 2025-26), Sowparnika Life On The Green is sold out — no units are currently listed as available.

Are there any RERA complaints against Sowparnika Life On The Green?

As per K-RERA data tracked by rera.watch, there are no complaints currently recorded against Sowparnika Life On The Green.

How many RERA complaints does SOWPARNIKA SUPERTECH PRIVATE LIMITED have?

SOWPARNIKA SUPERTECH PRIVATE LIMITED, the builder/promoter of Sowparnika Life On The Green, has 0 complaint(s) filed against them across all their K-RERA registered projects in Karnataka.

Who is the builder or developer of Sowparnika Life On The Green?

Sowparnika Life On The Green is developed by SOWPARNIKA SUPERTECH PRIVATE LIMITED, a company registered with K-RERA in Bengaluru Urban, Karnataka.

When did Sowparnika Life On The Green last file a quarterly update with K-RERA?

Sowparnika Life On The Green last filed a quarterly update for Q4 2025-26 on 2026-04-15. The project has submitted 2 quarterly report(s) on K-RERA to date.