Ashish ANR Row house
Show financial data (advance collected vs withdrawn)
Quarter-wise Tower Data
ANR Rowhouses 80% complete
| Unit type | Total | Booked | Available |
|---|---|---|---|
| Villa/Plot | 21 | 7 | 14 |
| Villa/Plot | 21 | 7 | 14 |
| Parking | 2 | — | 2 |
Unit Specifications
| Unit type | Carpet area (sqft) | Units | |
|---|---|---|---|
| Villa/Plot | 1,851–7,989 | 42 | Estimate ROI → |
Show escrow account details
Registration Extension Extension granted
Promoters can apply for a Section 6 extensionA formal application under RERA Section 6 for more time to complete the project, requiring a stated reason — distinct from the automatic, government-wide Covid extension every project received. when they can't meet the originally registered completion date.
Promoter's stated reason for delay: others
| Event | Start date | Proposed completion | |
|---|---|---|---|
| At the time of Registration | 2023-05-15 | 2025-12-31 | Certificate → |
| Section 6 Extension | 2025-12-31 | 2026-12-31 | Certificate → |
Project details
Buyer Risk Report
1 risk signal detected from this project's K-RERA quarterly filings.
Sign in free — no password — to see exactly which quarters and complaints triggered these flags.
Sign in to see full details →A few details and our team will reach out — no referral fee, just a connection.
✓ We're on it — our team will reach out to you shortly.
Show documents on file with K-RERA (122)
| BESCOM (electricity) | on file |
| BWSSB (water & sewerage) | on file |
| Fire NOC | not found |
| KSPCB (pollution control) | on file |
| SEIAA (environmental clearance) | not found |
| Airport / Air Force NOC | not found |
| Telecom (BSNL) NOC | not found |
| Lift license | not found |
| Form-1 (project registration) | not found |
| Form-2/3 (CA certificate) | on file |
| Form-B / Sec 3(1) affidavit | on file |
| Certificate of incorporation | not found |
| GST certificate | on file |
| PAN card | on file |
| Partnership deed / firm registration | on file |
Frequently Asked Questions
Is Ashish ANR Row house RERA registered in Karnataka?
Yes. Ashish ANR Row house is registered with the Karnataka Real Estate Regulatory Authority (K-RERA) under registration number PRM/KA/RERA/1251/446/PR/300623/006026.
What is the RERA registration number of Ashish ANR Row house?
The K-RERA registration number of Ashish ANR Row house is PRM/KA/RERA/1251/446/PR/300623/006026.
What is the current construction status of Ashish ANR Row house?
As of Q1 2026-27, Ashish ANR Row house is 80% complete according to its latest K-RERA quarterly filing.
Are flats still available in Ashish ANR Row house?
Yes. As per the latest K-RERA quarterly filing (Q1 2026-27), Ashish ANR Row house has 14 unit(s) available for purchase.
How many flats have been sold in Ashish ANR Row house?
As per the latest K-RERA filing (Q1 2026-27), 7 out of 21 units in Ashish ANR Row house have been sold or booked.
Are there any RERA complaints against Ashish ANR Row house?
As per K-RERA data tracked by rera.watch, there are no complaints currently recorded against Ashish ANR Row house.
How many RERA complaints does Aashish Developer and Builders have?
Aashish Developer and Builders, the builder/promoter of Ashish ANR Row house, has 1 complaint(s) filed against them across all their K-RERA registered projects in Karnataka.
Who is the builder or developer of Ashish ANR Row house?
Ashish ANR Row house is developed by Aashish Developer and Builders, a partnership firm registered with K-RERA in Bengaluru Urban, Karnataka.
When did Ashish ANR Row house last file a quarterly update with K-RERA?
Ashish ANR Row house last filed a quarterly update for Q1 2026-27 on 2026-07-14. The project has submitted 3 quarterly report(s) on K-RERA to date.