ALYSSA

Bengaluru Urban PRM/KA/RERA/1251/310/PR/171026/000862
3 complaints
No quarterly filings found for this project.
Complaints
3
on project · 55 on builder

Unit Specifications

Unit type Carpet area (sqft) Units
1 BHK 457–474 40 Estimate ROI →
2 BHK 801–860 181 Estimate ROI →
3 BHK 909–1,163 211 Estimate ROI →
4 BHK 1,464–1,631 6 Estimate ROI →
Show escrow account details
Escrow Accounts
Bank
ICICI Bank
Branch
M G ROAD BANGALORE
IFSC
ICIC0000002
70% Collection A/C
000205026795

Project details

Registration no.
PRM/KA/RERA/1251/310/PR/171026/000862
District
Bengaluru Urban
Taluk
Bengaluru South
Total cost
Project start
2017-07-24
FAR sanctioned
3.2
Land area
175,851 sqft
Proposed completion
2024-04-22 overdue
Project address
SY NO. 30/3, 30/4, 35/1, KONAPPANA AGRAHARA VILLAGE, BEGUR HOBLI, BANGALORE SOUTH TALUK

Complaint History 44 complaints

Complaint no. Filed Subject Status
CMP/221125/0010405 2022-11-25 Damaged covered car parking provided by builder Disposed
CMP/221102/0010159 2022-11-02 FORM O COMPENSATION FOR MENTAL AGONY ARISING FROM THE MATTER ADJUDICATED BY COMPLAINT NO 7738 Disposed
CMP/221027/0010133 2022-10-27 FORM O-COMPENSATION & COST OF LITIGATION FOR MENTAL AGONY & OTHER DETRIMENT FACED BY THE PETITIONER BY VIOLATIONS OF PROVISIONS OF SECTION 11(4)(G) OF THE REAL ESTATE(R&D) ACT 2016 BY THE RESPONDENT/S Disposed
CMP/220914/0010014 2022-09-14 FORM O - COMPENSATION FOR MENTAL AGONY,DIFFICULTIES, & OTHER DETRIMENTS PLUS COST OF LITIGATION ARISING OUT OF COMPLAINT NO-CMP/200301/0005610 DECIDED IN FAVOUR OF THE PETITIONER BY THE HON AUTHORITY Disposed
CMP/220805/0009855 2022-08-05 REFUND PROPERTY TAX PAID BY ME ON UNIT "C 206" FOR THE PERIOD, FROM 2019 TO 2023, FALLING UNDER OBLIGATION OF THE PROMOTER TO PAY ALL OUTGOINGS BEFORE HANDING OVER THE PHYSICAL POSSESSION TO ALLOTTEE Disposed
CMP/220725/0009809 2022-07-25 Claim for delay compensation for delayed flat possession under Section 18(1) of The Real Estate (R&D) Act 2016 Disposed
CMP/220607/0009596 2022-06-07 Non receipt of Booking amount Disposed
CMP/220328/0009270 2022-03-28 Delayed Project and Compensation not provided as per agreement Disposed
CMP/220207/0008972 2022-02-07 Compensation due to delay of project Raaga by 54 months, As per RERA guidelines. Disposed
CMP/210927/0008388 2021-09-27 Compensation due to delayed possession Disposed
CMP/210803/0008204 2021-08-03 Return of amount paid Disposed
CMP/210730/0008178 2021-07-30 DELAYED PERIOD COMPENSATION (penalty clause of agreement to pay compensation) Disposed
CMP/210403/0007859 2021-04-03 As per the Complaint uploaded Disposed
CMP/210329/0007852 2021-03-29 Compensation due to delay of project Raaga by 54 months Disposed
CMP/210324/0007829 2021-03-24 Builder not abiding by penalty clause of agreemnt to pay compensation Disposed
CMP/210303/0007738 2021-03-03 Violations of terms and conditions of Occupancy Certificate and other provisions of Karnataka apartment ownership act. Non transparency with respect to parking allotment and sale of parking slots Disposed
CMP/201229/0007348 2020-12-29 Refund of advance booking amount ( Based On Email Confirmation ) Disposed
CMP/201118/0007086 2020-11-18 Apartment Delivery delayed and compensation not accounted as per agreement Disposed
CMP/201003/0006751 2020-10-03 Delay in Possession - Compensation Disposed
CMP/200919/0006615 2020-09-19 Cancellation and Refund Disposed
CMP/200909/0005970 2020-09-09 Delay Compensation and Project delay Disposed
CMP/200901/0006491 2020-09-01 Delay in handing over possession of flat no B1-208 and water dampness on the walls due to faulty construction Disposed
CMP/200829/0006477 2020-08-29 DelayedCompensation Disposed
CMP/200827/0006451 2020-08-27 Delay in handing over the project Disposed
CMP/200814/0006357 2020-08-14 Delay compensation as per RERA Disposed
CMP/200429/0005853 2020-04-29 DELAY COMPENSATION AND POSESSION OF FLAT Disposed
CMP/200301/0005619 2020-03-01 Delay compensation Disposed
CMP/200224/0005511 2020-02-24 Refund request due to property litigation on Mirabilis Disposed
CMP/200216/0005454 2020-02-16 Regarding penalty compensation for delayed possession Plus other compensation Disposed
CMP/200108/0005166 2020-01-08 Refusing to adhere to the agreement about paying delay compensation in case of delay in giving possession. Disposed
CMP/191221/0003943 2019-12-21 Agreement Date crossed - Refund + Compensation and Interest for lost years. Disposed
CMP/191127/0004623 2019-11-27 Delivery delay compensation Disposed
CMP/191121/0004745 2019-11-21 Delay Compensation for Falt no. C-204 at Mirabilis Disposed
CMP/191120/0004771 2019-11-20 Compensation not paid by the Builder Disposed
CMP/191030/0004578 2019-10-30 DELAYED PERIOD COMPENSATION Disposed
CMP/191028/0004563 2019-10-28 DELAYED PERIOD COMPENSATION Disposed
CMP/191005/0004368 2019-10-05 Delay compensation as per Rera rules Disposed
CMP/191004/0004411 2019-10-04 Compensation for delayed apartment delivery as per RERA Disposed
CMP/190928/0004337 2019-09-28 Compensation for late delivery and other concerns Disposed
CMP/190922/0004271 2019-09-22 Compensation for late delivery and other concerns. Disposed
CMP/190922/0004268 2019-09-22 Regarding penalty compensation for delayed possession Disposed
CMP/190806/0003491 2019-08-06 Delay Compensation Disposed
CMP/190307/0002278 2019-03-07 Delay in delivery of flat (C401) and delay compensation not paid Disposed
CMP/190304/0002340 2019-03-04 Delay compensation as per RERA Disposed

Frequently Asked Questions

Based on K-RERA registered data for ALYSSA
Is ALYSSA RERA registered in Karnataka?

Yes. ALYSSA is registered with the Karnataka Real Estate Regulatory Authority (K-RERA) under registration number PRM/KA/RERA/1251/310/PR/171026/000862.

What is the RERA registration number of ALYSSA?

The K-RERA registration number of ALYSSA is PRM/KA/RERA/1251/310/PR/171026/000862.

Are there any RERA complaints against ALYSSA?

Yes. ALYSSA has 3 complaint(s) filed against it on the K-RERA portal. Review these on the official K-RERA website before making a purchase decision.