Delivered · 100% built
Filed — · Q3 2025-26
Fund safety: no flags
Construction
100%
complete
Sold
19
of 19 total units
Available
5
units
2 BHK: 5
Other: 0
Complaints
0
on project
Construction progress
% complete per quarter
Sales velocity
Units sold per quarter · cumulative booked (line)
Inventory drain
Available units over time
Show financial data (advance collected vs withdrawn)
Quarterly financials
₹ Crore — advance collected vs amount withdrawn this quarter

Quarter-wise Tower Data

Filed: 2026-07-02 · Project 100% complete
ARINJAY EMPIRE 100% complete
Unit type Total Booked Available
2 BHK 19 14 5
Other 5 5 0
Parking 13 13 —
Floor completion
Floor 0
100.0%
Floor 1
100.0%
Floor 2
100.0%
Floor 3
100.0%
Floor 4
100.0%
Floor 5
100.0%

Unit Specifications

Unit type Carpet area (sqft) Units
2 BHK 512–1,081 38 Estimate ROI →
Other — 10
Show escrow account details
Escrow Accounts
Bank
CENTRAL BANK OF INDIA
Branch
BELAGAVI
IFSC
CBIN0280871
70% Collection A/C
5404573466
100% A/C
5404573466
30% A/C
5404573466

Registry Details

Want the latest sale-deed / registration status for this project? Our team will look it up for you.

Project details

Registration no.
PRM/KA/RERA/1249/447/PR/161123/006412
District
Belagavi
Taluk
Belagavi
Promoter
ARINJAY CONSTRUCTIONS
Firm type
Partnership Firm
PAN
ACAFA9817D
GSTIN
29ACAFA9817D1ZF
Total units
19
Project start
2023-05-01
FAR sanctioned
1.89
Total cost
₹5.28 Cr
Land/property litigation
No
Proposed completion
2026-08-15
Project address
CTS NO: 1920/A, 1920/B, 1921, 1922, BHOJ GALLI, SHAHAPUR , BELAGAVI , Belagavi , Belagavi, Karnataka - 590003
Show documents on file with K-RERA (135)
Documents on file
Government NOCs
BESCOM (electricity) not found
BWSSB (water & sewerage) not found
Fire NOC not found
KSPCB (pollution control) not found
SEIAA (environmental clearance) not found
Airport / Air Force NOC not found
Telecom (BSNL) NOC not found
Lift license not found
RERA statutory forms
Form-1 (project registration) on file
Form-2/3 (CA certificate) on file
Form-B / Sec 3(1) affidavit on file
Company KYC
Certificate of incorporation not found
GST certificate on file
PAN card not found
Partnership deed / firm registration not found
Promoter financials
10 on file
Legal / land documents
3 on file
Other documents
61 on file · 30 marked not available
Plan approvals
10 on file
Sale/allotment documents
3 on file
Site photographs
1 on file
Technical certificates
3 on file
Inventory of documents the promoter has uploaded to their K-RERA project page — not a review of their contents. "Not found" means no filed document matched that item by name; it doesn't necessarily apply to every project (e.g. an airport-proximity NOC).

Frequently Asked Questions

Based on K-RERA registered data for ARINJAY EMPIRE
Is ARINJAY EMPIRE RERA registered in Karnataka?

Yes. ARINJAY EMPIRE is registered with the Karnataka Real Estate Regulatory Authority (K-RERA) under registration number PRM/KA/RERA/1249/447/PR/161123/006412.

What is the RERA registration number of ARINJAY EMPIRE?

The K-RERA registration number of ARINJAY EMPIRE is PRM/KA/RERA/1249/447/PR/161123/006412.

What is the current construction status of ARINJAY EMPIRE?

As of Q3 2025-26, ARINJAY EMPIRE is 100% complete — construction has finished according to its latest K-RERA quarterly filing.

Are flats still available in ARINJAY EMPIRE?

Yes. As per the latest K-RERA quarterly filing (Q3 2025-26), ARINJAY EMPIRE has 5 unit(s) available for purchase.

How many flats have been sold in ARINJAY EMPIRE?

As per the latest K-RERA filing (Q3 2025-26), 19 out of 19 units in ARINJAY EMPIRE have been sold or booked.

Are 2 BHK flats available in ARINJAY EMPIRE?

Yes. According to the latest K-RERA quarterly filing, there are 5 2 BHK unit(s) available in ARINJAY EMPIRE, Belagavi.

Are there any RERA complaints against ARINJAY EMPIRE?

As per K-RERA data tracked by rera.watch, there are no complaints currently recorded against ARINJAY EMPIRE.

How many RERA complaints does ARINJAY CONSTRUCTIONS have?

ARINJAY CONSTRUCTIONS, the builder/promoter of ARINJAY EMPIRE, has 0 complaint(s) filed against them across all their K-RERA registered projects in Karnataka.

Who is the builder or developer of ARINJAY EMPIRE?

ARINJAY EMPIRE is developed by ARINJAY CONSTRUCTIONS, a partnership firm registered with K-RERA in Belagavi, Karnataka.

When did ARINJAY EMPIRE last file a quarterly update with K-RERA?

ARINJAY EMPIRE last filed a quarterly update for Q3 2025-26 on 2026-07-02. The project has submitted 1 quarterly report(s) on K-RERA to date.