MORYA ENCLAVE

Belagavi · PARTH BUILDERS AND DEVELOPERS PRM/KA/RERA/1249/447/PR/220424/006828
Delivered · 100% built
Filed — · Q1 2026-27
Construction
100%
complete
Sold
14
of 19 total units
Available
5
units
2 BHK: 1
3 BHK: 4
Commercial: 0
Complaints
0
on project · 2 on builder
Construction progress
% complete per quarter
Sales velocity
Units sold per quarter · cumulative booked (line)
Inventory drain
Available units over time
Show financial data (advance collected vs withdrawn)
Quarterly financials
₹ Crore — advance collected vs amount withdrawn this quarter

Quarter-wise Tower Data

Filed: 2026-07-15 · Project 100% complete
MORYA ELITE 100% complete
Unit type Total Booked Available
2 BHK 10 9 1
3 BHK 8 4 4
Commercial 1 1 0
Parking 10 8 2
Floor completion
Floor 0
99.0%
Floor 1
99.0%
Floor 2
99.0%
Floor 3
99.0%
Floor 4
99.0%

Unit Specifications

Unit type Carpet area (sqft) Units
2 BHK 457–609 20 Estimate ROI →
3 BHK 619–763 16 Estimate ROI →
Commercial 1,252 2 Estimate ROI →
Show escrow account details
Escrow Accounts
Bank
Canara Bank
Branch
Khanapur Road, Tilakwadi
IFSC
CNRB0000558
70% Collection A/C
120026217860
100% A/C
120026217886
30% A/C
120026433344

Project details

Registration no.
PRM/KA/RERA/1249/447/PR/220424/006828
District
Belagavi
Taluk
Belagavi
Promoter
PARTH BUILDERS AND DEVELOPERS
Firm type
Partnership Firm
PAN
AATFP6729J
GSTIN
29AATFP6729J1ZB
Total units
19
Total cost
₹7.02 Cr
Project start
2024-01-01
FAR sanctioned
2.24
Proposed completion
2027-12-31
Project address
PLOT NO. 3, FORMING PART OF R S NO. 53/1, PID NO. 139404 , CORRESPONDING TO CTS NO. 2332/2 , SHAHU NAGAR, KANGRALI BK

Frequently Asked Questions

Based on K-RERA registered data for MORYA ENCLAVE
Is MORYA ENCLAVE RERA registered in Karnataka?

Yes. MORYA ENCLAVE is registered with the Karnataka Real Estate Regulatory Authority (K-RERA) under registration number PRM/KA/RERA/1249/447/PR/220424/006828.

What is the RERA registration number of MORYA ENCLAVE?

The K-RERA registration number of MORYA ENCLAVE is PRM/KA/RERA/1249/447/PR/220424/006828.

What is the current construction status of MORYA ENCLAVE?

As of Q1 2026-27, MORYA ENCLAVE is 100% complete — construction has finished according to its latest K-RERA quarterly filing.

Are flats still available in MORYA ENCLAVE?

Yes. As per the latest K-RERA quarterly filing (Q1 2026-27), MORYA ENCLAVE has 5 unit(s) available for purchase.

How many flats have been sold in MORYA ENCLAVE?

As per the latest K-RERA filing (Q1 2026-27), 14 out of 19 units in MORYA ENCLAVE have been sold or booked.

Are 2 BHK flats available in MORYA ENCLAVE?

Yes. According to the latest K-RERA quarterly filing, there are 1 2 BHK unit(s) available in MORYA ENCLAVE, Belagavi.

Are 3 BHK flats available in MORYA ENCLAVE?

Yes. According to the latest K-RERA quarterly filing, there are 4 3 BHK unit(s) available in MORYA ENCLAVE, Belagavi.

Are there any RERA complaints against MORYA ENCLAVE?

As per K-RERA data tracked by rera.watch, there are no complaints currently recorded against MORYA ENCLAVE.

How many RERA complaints does PARTH BUILDERS AND DEVELOPERS have?

PARTH BUILDERS AND DEVELOPERS, the builder/promoter of MORYA ENCLAVE, has 2 complaint(s) filed against them across all their K-RERA registered projects in Karnataka.

Who is the builder or developer of MORYA ENCLAVE?

MORYA ENCLAVE is developed by PARTH BUILDERS AND DEVELOPERS, a partnership firm registered with K-RERA in Belagavi, Karnataka.

When did MORYA ENCLAVE last file a quarterly update with K-RERA?

MORYA ENCLAVE last filed a quarterly update for Q1 2026-27 on 2026-07-15. The project has submitted 3 quarterly report(s) on K-RERA to date.