Projects / MANDAVI ROYAL GARDEN
+ Compare with another project

MANDAVI ROYAL GARDEN

Udupi · MANDAVI INFRASTRUCTURES PRM/KA/RERA/1273/318/PR/180424/006793
On track · 55% built
Filed — · Q1 2026-27
Construction
55%
complete
Sold
148
of 280 total units
Available
132
units
2 BHK: 43
3 BHK: 75
4 BHK: 14
Complaints
0
on project
Construction progress
% complete per quarter
Sales velocity
Units sold per quarter · cumulative booked (line)
Inventory drain
Available units over time
Show financial data (advance collected vs withdrawn)
Quarterly financials
₹ Crore — advance collected vs amount withdrawn this quarter

Quarter-wise Tower Data

Filed: 2026-07-13 · Project 55% complete
IRIS 40% complete
Unit type Total Booked Available
2 BHK 52 16 36
3 BHK 68 21 47
4 BHK 20 9 11
Parking 223 46 177
Floor completion
Floor 0
30.0%
Floor 1
30.0%
Floor 2
30.0%
Floor 3
30.0%
Floor 4
25.0%
Floor 5
25.0%
Floor 6
25.0%
Floor 7
25.0%
Floor 8
25.0%
Floor 9
25.0%
Floor 10
25.0%
Floor 11
10.0%
Floor 12
10.0%
Floor 13
10.0%
Floor 14
10.0%
Floor 15
10.0%
Floor 16
10.0%
Floor 17
10.0%
Floor 18
10.0%
Floor 19
10.0%
Floor 20
10.0%
Floor 21
10.0%
Floor 22
10.0%
Floor 23
10.0%
Floor 24
10.0%
Floor 25
10.0%
Floor 26
10.0%
Floor 27
10.0%
Floor 28
10.0%
Floor 29
0.0%
Floor 30
0.0%
Floor 31
0.0%
Floor 32
0.0%
Floor 33
0.0%
Floor 34
0.0%
Floor 35
0.0%
Floor 36
0.0%
Floor 37
0.0%
Floor 38
0.0%
Floor 39
0.0%
ORCHID 61% complete
Unit type Total Booked Available
2 BHK 52 45 7
3 BHK 68 40 28
4 BHK 20 17 3
Parking 200 102 98
Floor completion
Floor 0
55.0%
Floor 1
55.0%
Floor 2
50.0%
Floor 3
50.0%
Floor 4
40.0%
Floor 5
40.0%
Floor 6
30.0%
Floor 7
30.0%
Floor 8
25.0%
Floor 9
25.0%
Floor 10
25.0%
Floor 11
25.0%
Floor 12
25.0%
Floor 13
25.0%
Floor 14
25.0%
Floor 15
10.0%
Floor 16
10.0%
Floor 17
10.0%
Floor 18
10.0%
Floor 19
10.0%
Floor 20
10.0%
Floor 21
10.0%
Floor 22
10.0%
Floor 23
10.0%
Floor 24
10.0%
Floor 25
10.0%
Floor 26
10.0%
Floor 27
10.0%
Floor 28
10.0%
Floor 29
10.0%
Floor 30
10.0%
Floor 31
10.0%
Floor 32
10.0%
Floor 33
0.0%
Floor 34
0.0%
Floor 35
0.0%
Floor 36
0.0%
Floor 37
0.0%
Floor 38
0.0%
Floor 39
0.0%

Unit Specifications

Unit type Carpet area (sqft) Units
2 BHK 1,011–5,213 208 Estimate ROI →
3 BHK 1,279–5,583 272 Estimate ROI →
4 BHK 1,729–6,630 80 Estimate ROI →
Show escrow account details
Escrow Accounts
Bank
Karnataka Bank Ltd.
Branch
KUNJIBETTU
IFSC
KARB0000803
70% Collection A/C
8032000100062501
100% A/C
8032000100062401
30% A/C
8032000100062601

Project details

Registration no.
PRM/KA/RERA/1273/318/PR/180424/006793
District
Udupi
Taluk
Udupi
Promoter
MANDAVI INFRASTRUCTURES
Firm type
Partnership Firm
PAN
ABXFM5907A
GSTIN
29ABXFM5907A1ZX
Total units
280
Total cost
₹158.05 Cr
Project start
2024-03-01
FAR sanctioned
1.71
Land/property litigation
No
Proposed completion
2030-03-25
Project address
130/2, 130/16, 130/14B2, 130/14A1, 130/14A2, 130/3, 130/14B1, 126/2A, 126/3, 126/4, 126/5, 126/6, 126/7, 127/1, 130/118, 130/117 , SHIVALI VILLAGE UDUPI , Udupi , Udupi, Karnataka - 576102
Show documents on file with K-RERA (152)
Documents on file
Government NOCs
BESCOM (electricity) not found
BWSSB (water & sewerage) not found
Fire NOC on file
KSPCB (pollution control) on file
SEIAA (environmental clearance) not found
Airport / Air Force NOC not found
Telecom (BSNL) NOC not found
Lift license not found
RERA statutory forms
Form-1 (project registration) on file
Form-2/3 (CA certificate) on file
Form-B / Sec 3(1) affidavit on file
Company KYC
Certificate of incorporation not found
GST certificate on file
PAN card on file
Partnership deed / firm registration on file
Promoter financials
22 on file
Legal / land documents
17 on file
Other documents
52 on file · 8 marked not available
Plan approvals
20 on file
Sale/allotment documents
1 on file
Site photographs
5 on file
Technical certificates
5 on file
Inventory of documents the promoter has uploaded to their K-RERA project page — not a review of their contents. "Not found" means no filed document matched that item by name; it doesn't necessarily apply to every project (e.g. an airport-proximity NOC).

Frequently Asked Questions

Based on K-RERA registered data for MANDAVI ROYAL GARDEN
Is MANDAVI ROYAL GARDEN RERA registered in Karnataka?

Yes. MANDAVI ROYAL GARDEN is registered with the Karnataka Real Estate Regulatory Authority (K-RERA) under registration number PRM/KA/RERA/1273/318/PR/180424/006793.

What is the RERA registration number of MANDAVI ROYAL GARDEN?

The K-RERA registration number of MANDAVI ROYAL GARDEN is PRM/KA/RERA/1273/318/PR/180424/006793.

What is the current construction status of MANDAVI ROYAL GARDEN?

As of Q1 2026-27, MANDAVI ROYAL GARDEN is 55% complete according to its latest K-RERA quarterly filing.

Are flats still available in MANDAVI ROYAL GARDEN?

Yes. As per the latest K-RERA quarterly filing (Q1 2026-27), MANDAVI ROYAL GARDEN has 132 unit(s) available for purchase.

How many flats have been sold in MANDAVI ROYAL GARDEN?

As per the latest K-RERA filing (Q1 2026-27), 148 out of 280 units in MANDAVI ROYAL GARDEN have been sold or booked.

Are 2 BHK flats available in MANDAVI ROYAL GARDEN?

Yes. According to the latest K-RERA quarterly filing, there are 43 2 BHK unit(s) available in MANDAVI ROYAL GARDEN, Udupi.

Are 3 BHK flats available in MANDAVI ROYAL GARDEN?

Yes. According to the latest K-RERA quarterly filing, there are 75 3 BHK unit(s) available in MANDAVI ROYAL GARDEN, Udupi.

Are 4 BHK flats available in MANDAVI ROYAL GARDEN?

Yes. According to the latest K-RERA quarterly filing, there are 14 4 BHK unit(s) available in MANDAVI ROYAL GARDEN, Udupi.

Are there any RERA complaints against MANDAVI ROYAL GARDEN?

As per K-RERA data tracked by rera.watch, there are no complaints currently recorded against MANDAVI ROYAL GARDEN.

How many RERA complaints does MANDAVI INFRASTRUCTURES have?

MANDAVI INFRASTRUCTURES, the builder/promoter of MANDAVI ROYAL GARDEN, has 0 complaint(s) filed against them across all their K-RERA registered projects in Karnataka.

Who is the builder or developer of MANDAVI ROYAL GARDEN?

MANDAVI ROYAL GARDEN is developed by MANDAVI INFRASTRUCTURES, a partnership firm registered with K-RERA in Udupi, Karnataka.

When did MANDAVI ROYAL GARDEN last file a quarterly update with K-RERA?

MANDAVI ROYAL GARDEN last filed a quarterly update for Q1 2026-27 on 2026-07-13. The project has submitted 3 quarterly report(s) on K-RERA to date.