SAIRAJ EXOTICA
Show financial data (advance collected vs withdrawn)
Quarter-wise Tower Data
SAIRAJ EXOTICA 100% complete
| Unit type | Total | Booked | Available |
|---|---|---|---|
| 2 BHK | 13 | 9 | 4 |
| 2 BHK | 13 | 9 | 4 |
| 2 BHK | 13 | 9 | 4 |
| 2 BHK | 13 | 9 | 4 |
| 2 BHK | 13 | 9 | 4 |
| 2 BHK | 13 | 9 | 4 |
| 2 BHK | 13 | 9 | 4 |
| 3 BHK | 5 | 5 | 0 |
| 3 BHK | 5 | 5 | 0 |
| 3 BHK | 5 | 5 | 0 |
| 3 BHK | 5 | 5 | 0 |
| 3 BHK | 5 | 5 | 0 |
| 3 BHK | 5 | 5 | 0 |
| 3 BHK | 5 | 5 | 0 |
| Other | 1 | 1 | 0 |
| Other | 1 | 1 | 0 |
| Other | 1 | 1 | 0 |
| Other | 1 | 1 | 0 |
| Other | 1 | 1 | 0 |
| Other | 1 | 1 | 0 |
| Other | 1 | 1 | 0 |
| Parking | 10 | 5 | 5 |
Unit Specifications
| Unit type | Carpet area (sqft) | Units | |
|---|---|---|---|
| 2 BHK | 470–655 | 26 | Estimate ROI → |
| 3 BHK | 706–739 | 10 | Estimate ROI → |
| Other | 1,425 | 2 | Estimate ROI → |
Show escrow account details
Registration Extension Extension granted
Promoters can apply for a Section 6 extensionA formal application under RERA Section 6 for more time to complete the project, requiring a stated reason — distinct from the automatic, government-wide Covid extension every project received. when they can't meet the originally registered completion date.
Promoter's stated reason for delay: others
| Event | Start date | Proposed completion | |
|---|---|---|---|
| At the time of Registration | 2024-02-05 | 2025-06-30 | Certificate → |
| Section 6 Extension | 2025-06-30 | 2026-06-30 | Certificate → |
Registry Details
Want the latest sale-deed / registration status for this project? Our team will look it up for you.
A few details and our team will look this up for you.
✓ We're on it — our team will reach out to you shortly.
Project details
Show documents on file with K-RERA (164)
| BESCOM (electricity) | not found |
| BWSSB (water & sewerage) | not found |
| Fire NOC | not found |
| KSPCB (pollution control) | on file |
| SEIAA (environmental clearance) | not found |
| Airport / Air Force NOC | not found |
| Telecom (BSNL) NOC | not found |
| Lift license | not found |
| Form-1 (project registration) | on file |
| Form-2/3 (CA certificate) | on file |
| Form-B / Sec 3(1) affidavit | on file |
| Certificate of incorporation | not found |
| GST certificate | on file |
| PAN card | on file |
| Partnership deed / firm registration | on file |
Frequently Asked Questions
Is SAIRAJ EXOTICA RERA registered in Karnataka?
Yes. SAIRAJ EXOTICA is registered with the Karnataka Real Estate Regulatory Authority (K-RERA) under registration number PRM/KA/RERA/1249/447/PR/230924/007060.
What is the RERA registration number of SAIRAJ EXOTICA?
The K-RERA registration number of SAIRAJ EXOTICA is PRM/KA/RERA/1249/447/PR/230924/007060.
What is the current construction status of SAIRAJ EXOTICA?
As of Q4 2025-26, SAIRAJ EXOTICA is 100% complete — construction has finished according to its latest K-RERA quarterly filing.
Are flats still available in SAIRAJ EXOTICA?
Yes. As per the latest K-RERA quarterly filing (Q4 2025-26), SAIRAJ EXOTICA has 4 unit(s) available for purchase.
How many flats have been sold in SAIRAJ EXOTICA?
As per the latest K-RERA filing (Q4 2025-26), 15 out of 19 units in SAIRAJ EXOTICA have been sold or booked.
Are 2 BHK flats available in SAIRAJ EXOTICA?
Yes. According to the latest K-RERA quarterly filing, there are 28 2 BHK unit(s) available in SAIRAJ EXOTICA, Belagavi.
Are there any RERA complaints against SAIRAJ EXOTICA?
As per K-RERA data tracked by rera.watch, there are no complaints currently recorded against SAIRAJ EXOTICA.
How many RERA complaints does SAIRAJ BUILDERS have?
SAIRAJ BUILDERS, the builder/promoter of SAIRAJ EXOTICA, has 0 complaint(s) filed against them across all their K-RERA registered projects in Karnataka.
Who is the builder or developer of SAIRAJ EXOTICA?
SAIRAJ EXOTICA is developed by SAIRAJ BUILDERS, a partnership firm registered with K-RERA in Belagavi, Karnataka.
When did SAIRAJ EXOTICA last file a quarterly update with K-RERA?
SAIRAJ EXOTICA last filed a quarterly update for Q4 2025-26 on 2026-04-13. The project has submitted 2 quarterly report(s) on K-RERA to date.