G9 VINYAS 2
Show financial data (advance collected vs withdrawn)
Quarter-wise Tower Data
No tower breakdown recorded for this quarter.
Show escrow account details
Registration Extension Extension granted
Promoters can apply for a Section 6 extensionA formal application under RERA Section 6 for more time to complete the project, requiring a stated reason — distinct from the automatic, government-wide Covid extension every project received. when they can't meet the originally registered completion date.
Promoter's stated reason for delay: others
| Event | Start date | Proposed completion | |
|---|---|---|---|
| At the time of Registration | 2024-05-01 | 2024-12-31 | Certificate → |
| Section 6 Extension | 2024-12-31 | 2025-12-31 | Certificate → |
Registry Details
Want the latest sale-deed / registration status for this project? Our team will look it up for you.
A few details and our team will look this up for you.
✓ We're on it — our team will reach out to you shortly.
Project details
Show documents on file with K-RERA (182)
| BESCOM (electricity) | not found |
| BWSSB (water & sewerage) | not found |
| Fire NOC | not found |
| KSPCB (pollution control) | not found |
| SEIAA (environmental clearance) | not found |
| Airport / Air Force NOC | not found |
| Telecom (BSNL) NOC | not found |
| Lift license | not found |
| Form-1 (project registration) | not found |
| Form-2/3 (CA certificate) | not found |
| Form-B / Sec 3(1) affidavit | not found |
| Certificate of incorporation | not found |
| GST certificate | not found |
| PAN card | not found |
| Partnership deed / firm registration | not found |
Frequently Asked Questions
Is G9 VINYAS 2 RERA registered in Karnataka?
Yes. G9 VINYAS 2 is registered with the Karnataka Real Estate Regulatory Authority (K-RERA) under registration number PRM/KA/RERA/1268/378/PR/111124/007214.
What is the RERA registration number of G9 VINYAS 2?
The K-RERA registration number of G9 VINYAS 2 is PRM/KA/RERA/1268/378/PR/111124/007214.
What is the current construction status of G9 VINYAS 2?
As of Q3 2025-26, G9 VINYAS 2 is 100% complete — construction has finished according to its latest K-RERA quarterly filing.
Are flats still available in G9 VINYAS 2?
As per the latest K-RERA filing (Q3 2025-26), G9 VINYAS 2 is sold out — no units are currently listed as available.
Are there any RERA complaints against G9 VINYAS 2?
As per K-RERA data tracked by rera.watch, there are no complaints currently recorded against G9 VINYAS 2.
How many RERA complaints does S M DEVELOPERS have?
S M DEVELOPERS, the builder/promoter of G9 VINYAS 2, has 0 complaint(s) filed against them across all their K-RERA registered projects in Karnataka.
Who is the builder or developer of G9 VINYAS 2?
G9 VINYAS 2 is developed by S M DEVELOPERS, a partnership firm registered with K-RERA in Mysore, Karnataka.
When did G9 VINYAS 2 last file a quarterly update with K-RERA?
G9 VINYAS 2 last filed a quarterly update for Q3 2025-26 on 2026-02-05. The project has submitted 1 quarterly report(s) on K-RERA to date.