Projects / INSPIRA TREES OF LIFE
+ Compare with another project

INSPIRA TREES OF LIFE

2 complaints · 15% built
Filed — · Q1 2026-27
Construction
15%
complete
Sold
of ? total units
Available
0
units
Complaints
2
on project · 2 on builder
Construction progress
% complete per quarter
Sales velocity
Units sold per quarter · cumulative booked (line)
Inventory drain
Available units over time
Show financial data (advance collected vs withdrawn)
Quarterly financials
₹ Crore — advance collected vs amount withdrawn this quarter

Quarter-wise Tower Data

Filed: 2026-07-15 · Project 15% complete

No tower breakdown recorded for this quarter.

Show escrow account details
Escrow Accounts
Bank
HDFC
Branch
BANGALORE - KASTURBA GANDHI MARG
IFSC
HDFC0000009
70% Collection A/C
57500001853228
100% A/C
57500001853024
30% A/C
57500001853382

Project details

District
Bengaluru Urban
Taluk
Anekal
Total cost
Project start
2013-03-02
Land area
597,327 sqft
Proposed completion
2019-12-31 overdue
Project address
Sy No. 7/1,8,102/1,107,106,12/1,5,6, Ittangur Road,, Sarjapur Village, Sarjapur Hobli, Anekal Taluk.

Frequently Asked Questions

Based on K-RERA registered data for INSPIRA TREES OF LIFE
Is INSPIRA TREES OF LIFE RERA registered in Karnataka?

Yes. INSPIRA TREES OF LIFE is registered with the Karnataka Real Estate Regulatory Authority (K-RERA) under registration number .

What is the RERA registration number of INSPIRA TREES OF LIFE?

The K-RERA registration number of INSPIRA TREES OF LIFE is .

What is the current construction status of INSPIRA TREES OF LIFE?

As of Q1 2026-27, INSPIRA TREES OF LIFE is 15% complete according to its latest K-RERA quarterly filing.

Are flats still available in INSPIRA TREES OF LIFE?

As per the latest K-RERA filing (Q1 2026-27), INSPIRA TREES OF LIFE is sold out — no units are currently listed as available.

Are there any RERA complaints against INSPIRA TREES OF LIFE?

Yes. INSPIRA TREES OF LIFE has 2 complaint(s) filed against it on the K-RERA portal. Review these on the official K-RERA website before making a purchase decision.

When did INSPIRA TREES OF LIFE last file a quarterly update with K-RERA?

INSPIRA TREES OF LIFE last filed a quarterly update for Q1 2026-27 on 2026-07-15. The project has submitted 3 quarterly report(s) on K-RERA to date.