Projects / YESH MEGA CITY PHASE-03
+ Compare with another project

YESH MEGA CITY PHASE-03

Mysore · YESH DEVELOPERS AND PROMOTERS PRM/KA/RERA/1268/378/PR/061225/008320
Delivered · 100% built
Filed — · Q3 2025-26
Construction
100%
complete
Sold
of ? total units
Available
0
units
Complaints
0
on project
Construction progress
% complete per quarter
Sales velocity
Units sold per quarter · cumulative booked (line)
Inventory drain
Available units over time
Show financial data (advance collected vs withdrawn)
Quarterly financials
₹ Crore — advance collected vs amount withdrawn this quarter

Quarter-wise Tower Data

Filed: 2026-01-14 · Project 100% complete

No tower breakdown recorded for this quarter.

Show escrow account details
Escrow Accounts
Bank
Karnataka Bank Ltd.
Branch
V V Mohalla - Mysuru
IFSC
KARB0000505
70% Collection A/C
0505202500001601
100% A/C
0505202500001501
30% A/C
0505202500001701

Project details

Registration no.
PRM/KA/RERA/1268/378/PR/061225/008320
District
Mysore
Taluk
MYSORE
Promoter
YESH DEVELOPERS AND PROMOTERS
Firm type
Proprietorship
PAN
AFVPM2997Q
GSTIN
29AFVPM2997Q1ZX
Total cost
₹3.70 Cr
Project start
2024-03-07
Land/property litigation
No
Proposed completion
2026-05-22
Project address
Survey Number 122/1 (Old Sy No 98-P), Ankanahalli Village , Bilikere Hobli, Hunsur Taluk
Show documents on file with K-RERA (108)
Documents on file
Government NOCs
BESCOM (electricity) not found
BWSSB (water & sewerage) not found
Fire NOC not found
KSPCB (pollution control) not found
SEIAA (environmental clearance) not found
Airport / Air Force NOC not found
Telecom (BSNL) NOC not found
Lift license not found
RERA statutory forms
Form-1 (project registration) on file
Form-2/3 (CA certificate) on file
Form-B / Sec 3(1) affidavit on file
Company KYC
Certificate of incorporation not found
GST certificate on file
PAN card on file
Partnership deed / firm registration not found
Promoter financials
8 on file
Legal / land documents
16 on file
Other documents
23 on file · 19 marked not available
Plan approvals
12 on file
Sale/allotment documents
5 on file
Site photographs
5 on file
Technical certificates
1 on file
Inventory of documents the promoter has uploaded to their K-RERA project page — not a review of their contents. "Not found" means no filed document matched that item by name; it doesn't necessarily apply to every project (e.g. an airport-proximity NOC).

Frequently Asked Questions

Based on K-RERA registered data for YESH MEGA CITY PHASE-03
Is YESH MEGA CITY PHASE-03 RERA registered in Karnataka?

Yes. YESH MEGA CITY PHASE-03 is registered with the Karnataka Real Estate Regulatory Authority (K-RERA) under registration number PRM/KA/RERA/1268/378/PR/061225/008320.

What is the RERA registration number of YESH MEGA CITY PHASE-03?

The K-RERA registration number of YESH MEGA CITY PHASE-03 is PRM/KA/RERA/1268/378/PR/061225/008320.

What is the current construction status of YESH MEGA CITY PHASE-03?

As of Q3 2025-26, YESH MEGA CITY PHASE-03 is 100% complete — construction has finished according to its latest K-RERA quarterly filing.

Are flats still available in YESH MEGA CITY PHASE-03?

As per the latest K-RERA filing (Q3 2025-26), YESH MEGA CITY PHASE-03 is sold out — no units are currently listed as available.

Are there any RERA complaints against YESH MEGA CITY PHASE-03?

As per K-RERA data tracked by rera.watch, there are no complaints currently recorded against YESH MEGA CITY PHASE-03.

How many RERA complaints does YESH DEVELOPERS AND PROMOTERS have?

YESH DEVELOPERS AND PROMOTERS, the builder/promoter of YESH MEGA CITY PHASE-03, has 0 complaint(s) filed against them across all their K-RERA registered projects in Karnataka.

Who is the builder or developer of YESH MEGA CITY PHASE-03?

YESH MEGA CITY PHASE-03 is developed by YESH DEVELOPERS AND PROMOTERS, a proprietorship registered with K-RERA in Mysore, Karnataka.

When did YESH MEGA CITY PHASE-03 last file a quarterly update with K-RERA?

YESH MEGA CITY PHASE-03 last filed a quarterly update for Q3 2025-26 on 2026-01-14. The project has submitted 1 quarterly report(s) on K-RERA to date.