Projects / NSR GREEN WOODS PHASE-3
+ Compare with another project

NSR GREEN WOODS PHASE-3

Kolar · NSR VENTURES PRM/KA/RERA/1265/347/PR/170125/007389
Delivered · 100% built
Filed — · Q4 2025-26
Construction
100%
complete
Sold
of ? total units
Available
0
units
Complaints
0
on project
Construction progress
% complete per quarter
Sales velocity
Units sold per quarter · cumulative booked (line)
Inventory drain
Available units over time
Show financial data (advance collected vs withdrawn)
Quarterly financials
₹ Crore — advance collected vs amount withdrawn this quarter

Quarter-wise Tower Data

Filed: 2026-04-14 · Project 100% complete

No tower breakdown recorded for this quarter.

Show escrow account details
Escrow Accounts
Bank
STATE BANK OF INDIA
Branch
Malur
IFSC
SBIN0011294
70% Collection A/C
43548505873
100% A/C
43548516896
30% A/C
43548516513

Project details

Registration no.
PRM/KA/RERA/1265/347/PR/170125/007389
District
Kolar
Taluk
Bengaluru South
Promoter
NSR VENTURES
Firm type
Partnership Firm
PAN
AAJFN7940F
GSTIN
29AAJFN7940F1ZX
Total cost
₹12.59 Cr
Project start
2024-12-01
Land/property litigation
No
Proposed completion
2030-12-31
Project address
Sy No 5/1, 6, 7 at Bellavi Village , Kasaba Hobli, Malur Taluk, Kolar District , Maluru , Kolar, Karnataka - 563130
Show documents on file with K-RERA (132)
Documents on file
Government NOCs
BESCOM (electricity) on file
BWSSB (water & sewerage) not found
Fire NOC not found
KSPCB (pollution control) on file
SEIAA (environmental clearance) not found
Airport / Air Force NOC not found
Telecom (BSNL) NOC not found
Lift license not found
RERA statutory forms
Form-1 (project registration) on file
Form-2/3 (CA certificate) on file
Form-B / Sec 3(1) affidavit on file
Company KYC
Certificate of incorporation not found
GST certificate on file
PAN card not found
Partnership deed / firm registration not found
Promoter financials
8 on file
Legal / land documents
21 on file
Other documents
49 on file · 5 marked not available
Plan approvals
5 on file
Sale/allotment documents
1 on file
Site photographs
8 on file · 1 marked not available
Technical certificates
2 on file
Inventory of documents the promoter has uploaded to their K-RERA project page — not a review of their contents. "Not found" means no filed document matched that item by name; it doesn't necessarily apply to every project (e.g. an airport-proximity NOC).

Frequently Asked Questions

Based on K-RERA registered data for NSR GREEN WOODS PHASE-3
Is NSR GREEN WOODS PHASE-3 RERA registered in Karnataka?

Yes. NSR GREEN WOODS PHASE-3 is registered with the Karnataka Real Estate Regulatory Authority (K-RERA) under registration number PRM/KA/RERA/1265/347/PR/170125/007389.

What is the RERA registration number of NSR GREEN WOODS PHASE-3?

The K-RERA registration number of NSR GREEN WOODS PHASE-3 is PRM/KA/RERA/1265/347/PR/170125/007389.

What is the current construction status of NSR GREEN WOODS PHASE-3?

As of Q4 2025-26, NSR GREEN WOODS PHASE-3 is 100% complete — construction has finished according to its latest K-RERA quarterly filing.

Are flats still available in NSR GREEN WOODS PHASE-3?

As per the latest K-RERA filing (Q4 2025-26), NSR GREEN WOODS PHASE-3 is sold out — no units are currently listed as available.

Are there any RERA complaints against NSR GREEN WOODS PHASE-3?

As per K-RERA data tracked by rera.watch, there are no complaints currently recorded against NSR GREEN WOODS PHASE-3.

How many RERA complaints does NSR VENTURES have?

NSR VENTURES, the builder/promoter of NSR GREEN WOODS PHASE-3, has 0 complaint(s) filed against them across all their K-RERA registered projects in Karnataka.

Who is the builder or developer of NSR GREEN WOODS PHASE-3?

NSR GREEN WOODS PHASE-3 is developed by NSR VENTURES, a partnership firm registered with K-RERA in Kolar, Karnataka.

When did NSR GREEN WOODS PHASE-3 last file a quarterly update with K-RERA?

NSR GREEN WOODS PHASE-3 last filed a quarterly update for Q4 2025-26 on 2026-04-14. The project has submitted 2 quarterly report(s) on K-RERA to date.