Projects / Sattva Kaveri Siri Phase 2
+ Compare with another project

Sattva Kaveri Siri Phase 2

Mandya · CHINNAMASTA PROPERTIES PRIVATE LIMITED PRM/KA/RERA/1267/484/PR/250225/007523
On track · 65% built
Filed — · Q1 2026-27
Construction
65%
complete
Sold
of ? total units
Available
0
units
Complaints
0
on project
Construction progress
% complete per quarter
Sales velocity
Units sold per quarter · cumulative booked (line)
Inventory drain
Available units over time
Show financial data (advance collected vs withdrawn)
Quarterly financials
₹ Crore — advance collected vs amount withdrawn this quarter

Quarter-wise Tower Data

Filed: 2026-07-15 · Project 65% complete

No tower breakdown recorded for this quarter.

Show escrow account details
Escrow Accounts
Bank
ICICI Bank
Branch
MG Road
IFSC
ICIC0000002
70% Collection A/C
777705211324
100% A/C
777705201224
30% A/C
390405000591

Project details

Registration no.
PRM/KA/RERA/1267/484/PR/250225/007523
District
Mandya
Taluk
Bengaluru East
Promoter
CHINNAMASTA PROPERTIES PRIVATE LIMITED
Firm type
Company
PAN
AACCC6847Q
GSTIN
29AACCC6847QIZU
Total cost
₹88.21 Cr
Project start
2025-01-01
Land/property litigation
No
Proposed completion
2026-12-31
Project address
Sy.No. 273, 275, 276, 277, 278 and 279 of Sathanur village; S.No.197/2, 198/1A, 198/1B, 198/2A, 198/2B, , 199/1, 199/2, 199/3, 254, 255, 256/1, 256/2, 257 of Ummadahalli Village , Mandya , Mandya, Karnataka - 571402

Buyer Risk Report

1 risk signal detected from this project's K-RERA quarterly filings.

Sign in free — no password — to see exactly which quarters and complaints triggered these flags.

Sign in to see full details →
Show documents on file with K-RERA (66)
Documents on file
Government NOCs
BESCOM (electricity) on file
BWSSB (water & sewerage) not found
Fire NOC not found
KSPCB (pollution control) on file
SEIAA (environmental clearance) not found
Airport / Air Force NOC not found
Telecom (BSNL) NOC not found
Lift license not found
RERA statutory forms
Form-1 (project registration) on file
Form-2/3 (CA certificate) on file
Form-B / Sec 3(1) affidavit on file
Company KYC
Certificate of incorporation not found
GST certificate not found
PAN card not found
Partnership deed / firm registration not found
Promoter financials
12 on file
Legal / land documents
5 on file
Other documents
27 on file · 2 marked not available
Plan approvals
2 on file
Technical certificates
2 on file
Inventory of documents the promoter has uploaded to their K-RERA project page — not a review of their contents. "Not found" means no filed document matched that item by name; it doesn't necessarily apply to every project (e.g. an airport-proximity NOC).

Frequently Asked Questions

Based on K-RERA registered data for Sattva Kaveri Siri Phase 2
Is Sattva Kaveri Siri Phase 2 RERA registered in Karnataka?

Yes. Sattva Kaveri Siri Phase 2 is registered with the Karnataka Real Estate Regulatory Authority (K-RERA) under registration number PRM/KA/RERA/1267/484/PR/250225/007523.

What is the RERA registration number of Sattva Kaveri Siri Phase 2?

The K-RERA registration number of Sattva Kaveri Siri Phase 2 is PRM/KA/RERA/1267/484/PR/250225/007523.

What is the current construction status of Sattva Kaveri Siri Phase 2?

As of Q1 2026-27, Sattva Kaveri Siri Phase 2 is 65% complete according to its latest K-RERA quarterly filing.

Are flats still available in Sattva Kaveri Siri Phase 2?

As per the latest K-RERA filing (Q1 2026-27), Sattva Kaveri Siri Phase 2 is sold out — no units are currently listed as available.

Are there any RERA complaints against Sattva Kaveri Siri Phase 2?

As per K-RERA data tracked by rera.watch, there are no complaints currently recorded against Sattva Kaveri Siri Phase 2.

How many RERA complaints does CHINNAMASTA PROPERTIES PRIVATE LIMITED have?

CHINNAMASTA PROPERTIES PRIVATE LIMITED, the builder/promoter of Sattva Kaveri Siri Phase 2, has 0 complaint(s) filed against them across all their K-RERA registered projects in Karnataka.

Who is the builder or developer of Sattva Kaveri Siri Phase 2?

Sattva Kaveri Siri Phase 2 is developed by CHINNAMASTA PROPERTIES PRIVATE LIMITED, a company registered with K-RERA in Mandya, Karnataka.

When did Sattva Kaveri Siri Phase 2 last file a quarterly update with K-RERA?

Sattva Kaveri Siri Phase 2 last filed a quarterly update for Q1 2026-27 on 2026-07-15. The project has submitted 3 quarterly report(s) on K-RERA to date.