GRC Subhiksha

Bengaluru Urban · GRC Infra Pvt. Ltd. PRM/KA/RERA/1251/310/PR/030225/007478
On track · 18% built
Filed — · Q3 2025-26
Construction
18%
complete
Sold
123
of 308 total units
Available
185
units
Other: 1110
Complaints
0
on project · 1 on builder
Construction progress
% complete per quarter
Sales velocity
Units sold per quarter · cumulative booked (line)
Inventory drain
Available units over time
Show financial data (advance collected vs withdrawn)
Quarterly financials
₹ Crore — advance collected vs amount withdrawn this quarter

Quarter-wise Tower Data

Filed: 2026-03-21 · Project 18% complete
Tower-A 21% complete
Unit type Total Booked Available
Other 28 4 24
Other 28 6 22
Other 28 4 24
Other 28 6 22
Other 28 4 24
Other 28 6 22
Other 28 4 24
Other 28 6 22
Other 28 4 24
Other 28 6 22
Other 28 4 24
Other 28 6 22
Parking 60 10 50
Floor completion
Floor 0
100.0%
Floor 0
100.0%
Floor 0
100.0%
Floor 0
100.0%
Floor 0
100.0%
Floor 1
25.0%
Floor 1
25.0%
Floor 1
25.0%
Floor 1
25.0%
Floor 1
25.0%
Floor 2
25.0%
Floor 2
25.0%
Floor 2
25.0%
Floor 2
25.0%
Floor 2
25.0%
Floor 3
20.0%
Floor 3
20.0%
Floor 3
20.0%
Floor 3
20.0%
Floor 3
20.0%
Floor 4
20.0%
Floor 4
20.0%
Floor 4
20.0%
Floor 4
20.0%
Floor 4
20.0%
Floor 5
20.0%
Floor 5
20.0%
Floor 5
20.0%
Floor 5
20.0%
Floor 5
20.0%
Floor 6
10.0%
Floor 6
10.0%
Floor 6
10.0%
Floor 6
10.0%
Floor 6
10.0%
Floor 7
10.0%
Floor 7
10.0%
Floor 7
10.0%
Floor 7
10.0%
Floor 7
10.0%
Floor 8
10.0%
Floor 8
10.0%
Floor 8
10.0%
Floor 8
10.0%
Floor 8
10.0%
Floor 9
10.0%
Floor 9
10.0%
Floor 9
10.0%
Floor 9
10.0%
Floor 9
10.0%
Floor 10
10.0%
Floor 10
10.0%
Floor 10
10.0%
Floor 10
10.0%
Floor 10
10.0%
Floor 11
10.0%
Floor 11
10.0%
Floor 11
10.0%
Floor 11
10.0%
Floor 11
10.0%
Floor 12
10.0%
Floor 12
10.0%
Floor 12
10.0%
Floor 12
10.0%
Floor 12
10.0%
Floor 13
10.0%
Floor 13
10.0%
Floor 13
10.0%
Floor 13
10.0%
Floor 13
10.0%
Tower-B 21% complete
Unit type Total Booked Available
Other 4 4 0
Other 24 14 10
Other 14 9 5
Other 28 14 14
Other 14 7 7
Other 4 4 0
Other 24 14 10
Other 14 9 5
Other 28 14 14
Other 14 7 7
Other 4 4 0
Other 24 14 10
Other 14 9 5
Other 28 14 14
Other 14 7 7
Other 4 4 0
Other 24 14 10
Other 14 9 5
Other 28 14 14
Other 14 7 7
Other 4 4 0
Other 24 14 10
Other 14 9 5
Other 28 14 14
Other 14 7 7
Other 4 4 0
Other 24 14 10
Other 14 9 5
Other 28 14 14
Other 14 7 7
Parking 93 48 45
Floor completion
Floor 0
70.0%
Floor 0
70.0%
Floor 0
70.0%
Floor 0
70.0%
Floor 0
70.0%
Floor 1
20.0%
Floor 1
20.0%
Floor 1
20.0%
Floor 1
20.0%
Floor 1
20.0%
Floor 2
20.0%
Floor 2
20.0%
Floor 2
20.0%
Floor 2
20.0%
Floor 2
20.0%
Floor 3
20.0%
Floor 3
20.0%
Floor 3
20.0%
Floor 3
20.0%
Floor 3
20.0%
Floor 4
15.0%
Floor 4
15.0%
Floor 4
15.0%
Floor 4
15.0%
Floor 4
15.0%
Floor 5
15.0%
Floor 5
15.0%
Floor 5
15.0%
Floor 5
15.0%
Floor 5
15.0%
Floor 6
15.0%
Floor 6
15.0%
Floor 6
15.0%
Floor 6
15.0%
Floor 6
15.0%
Floor 7
15.0%
Floor 7
15.0%
Floor 7
15.0%
Floor 7
15.0%
Floor 7
15.0%
Floor 8
15.0%
Floor 8
15.0%
Floor 8
15.0%
Floor 8
15.0%
Floor 8
15.0%
Floor 9
15.0%
Floor 9
15.0%
Floor 9
15.0%
Floor 9
15.0%
Floor 9
15.0%
Floor 10
15.0%
Floor 10
15.0%
Floor 10
15.0%
Floor 10
15.0%
Floor 10
15.0%
Floor 11
15.0%
Floor 11
15.0%
Floor 11
15.0%
Floor 11
15.0%
Floor 11
15.0%
Floor 12
15.0%
Floor 12
15.0%
Floor 12
15.0%
Floor 12
15.0%
Floor 12
15.0%
Floor 13
15.0%
Floor 13
15.0%
Floor 13
15.0%
Floor 13
15.0%
Floor 13
15.0%
Floor 14
15.0%
Floor 14
15.0%
Floor 14
15.0%
Floor 14
15.0%
Floor 14
15.0%
Tower-C 18% complete
Unit type Total Booked Available
Other 28 1 27
Other 14 4 10
Other 42 24 18
Other 28 1 27
Other 14 4 10
Other 42 24 18
Other 28 1 27
Other 14 4 10
Other 42 24 18
Other 28 1 27
Other 14 4 10
Other 42 24 18
Other 28 1 27
Other 14 4 10
Other 42 24 18
Other 28 1 27
Other 14 4 10
Other 42 24 18
Parking 93 29 64
Floor completion
Floor 0
65.0%
Floor 0
65.0%
Floor 0
65.0%
Floor 0
65.0%
Floor 0
65.0%
Floor 1
25.0%
Floor 1
25.0%
Floor 1
25.0%
Floor 1
25.0%
Floor 1
25.0%
Floor 2
20.0%
Floor 2
20.0%
Floor 2
20.0%
Floor 2
20.0%
Floor 2
20.0%
Floor 3
15.0%
Floor 3
15.0%
Floor 3
15.0%
Floor 3
15.0%
Floor 3
15.0%
Floor 4
15.0%
Floor 4
15.0%
Floor 4
15.0%
Floor 4
15.0%
Floor 4
15.0%
Floor 5
15.0%
Floor 5
15.0%
Floor 5
15.0%
Floor 5
15.0%
Floor 5
15.0%
Floor 6
15.0%
Floor 6
15.0%
Floor 6
15.0%
Floor 6
15.0%
Floor 6
15.0%
Floor 7
15.0%
Floor 7
15.0%
Floor 7
15.0%
Floor 7
15.0%
Floor 7
15.0%
Floor 8
10.0%
Floor 8
10.0%
Floor 8
10.0%
Floor 8
10.0%
Floor 8
10.0%
Floor 9
10.0%
Floor 9
10.0%
Floor 9
10.0%
Floor 9
10.0%
Floor 9
10.0%
Floor 10
10.0%
Floor 10
10.0%
Floor 10
10.0%
Floor 10
10.0%
Floor 10
10.0%
Floor 11
10.0%
Floor 11
10.0%
Floor 11
10.0%
Floor 11
10.0%
Floor 11
10.0%
Floor 12
10.0%
Floor 12
10.0%
Floor 12
10.0%
Floor 12
10.0%
Floor 12
10.0%
Floor 13
10.0%
Floor 13
10.0%
Floor 13
10.0%
Floor 13
10.0%
Floor 13
10.0%
Floor 14
10.0%
Floor 14
10.0%
Floor 14
10.0%
Floor 14
10.0%
Floor 14
10.0%
Tower-D 15% complete
Unit type Total Booked Available
Other 42 12 30
Other 1 1 0
Other 13 12 1
Other 28 11 17
Other 42 12 30
Other 1 1 0
Other 13 12 1
Other 28 11 17
Other 42 12 30
Other 1 1 0
Other 13 12 1
Other 28 11 17
Other 42 12 30
Other 1 1 0
Other 13 12 1
Other 28 11 17
Other 42 12 30
Other 1 1 0
Other 13 12 1
Other 28 11 17
Other 42 12 30
Other 1 1 0
Other 13 12 1
Other 28 11 17
Parking 93 36 57
Floor completion
Floor 0
30.0%
Floor 0
30.0%
Floor 0
30.0%
Floor 0
30.0%
Floor 0
30.0%
Floor 1
20.0%
Floor 1
20.0%
Floor 1
20.0%
Floor 1
20.0%
Floor 1
20.0%
Floor 2
20.0%
Floor 2
20.0%
Floor 2
20.0%
Floor 2
20.0%
Floor 2
20.0%
Floor 3
15.0%
Floor 3
15.0%
Floor 3
15.0%
Floor 3
15.0%
Floor 3
15.0%
Floor 4
15.0%
Floor 4
15.0%
Floor 4
15.0%
Floor 4
15.0%
Floor 4
15.0%
Floor 5
15.0%
Floor 5
15.0%
Floor 5
15.0%
Floor 5
15.0%
Floor 5
15.0%
Floor 6
15.0%
Floor 6
15.0%
Floor 6
15.0%
Floor 6
15.0%
Floor 6
15.0%
Floor 7
15.0%
Floor 7
15.0%
Floor 7
15.0%
Floor 7
15.0%
Floor 7
15.0%
Floor 8
10.0%
Floor 8
10.0%
Floor 8
10.0%
Floor 8
10.0%
Floor 8
10.0%
Floor 9
10.0%
Floor 9
10.0%
Floor 9
10.0%
Floor 9
10.0%
Floor 9
10.0%
Floor 10
10.0%
Floor 10
10.0%
Floor 10
10.0%
Floor 10
10.0%
Floor 10
10.0%
Floor 11
10.0%
Floor 11
10.0%
Floor 11
10.0%
Floor 11
10.0%
Floor 11
10.0%
Floor 12
10.0%
Floor 12
10.0%
Floor 12
10.0%
Floor 12
10.0%
Floor 12
10.0%
Floor 13
10.0%
Floor 13
10.0%
Floor 13
10.0%
Floor 13
10.0%
Floor 13
10.0%
Floor 14
10.0%
Floor 14
10.0%
Floor 14
10.0%
Floor 14
10.0%
Floor 14
10.0%

Unit Specifications

Unit type Carpet area (sqft) Units
Other 977 8 Estimate ROI →
Other 931–977 48 Estimate ROI →
Other 960–977 56 Estimate ROI →
Other 775–857 168 Estimate ROI →
Other 990 2 Estimate ROI →
Other 978–990 110 Estimate ROI →
Other 996–1,084 168 Estimate ROI →
Other 981–1,010 56 Estimate ROI →
Show escrow account details
Escrow Accounts
Bank
STATE BANK OF INDIA
Branch
SBI, SME Jayanagar
IFSC
SBIN0006959
70% Collection A/C
43523523777
100% A/C
43523544460
30% A/C
43523457066

Project details

Registration no.
PRM/KA/RERA/1251/310/PR/030225/007478
District
Bengaluru Urban
Taluk
Anekal
Promoter
GRC Infra Pvt. Ltd.
Firm type
Company
PAN
AADCG6210G
GSTIN
29AADCG6210G1ZT
Total units
308
Total cost
₹273.06 Cr
Project start
2024-12-06
FAR sanctioned
1.5
Proposed completion
2030-12-31
Project address
Sy no 38/1 & 38/2 situated atchoodasandra village, sarjapura hobli, anekal taluk, bangalore\, Sy no 38/1 & 38/2 situated atchoodasandra village, sarjapura hobli, anekal taluk, bangalore

Frequently Asked Questions

Based on K-RERA registered data for GRC Subhiksha
Is GRC Subhiksha RERA registered in Karnataka?

Yes. GRC Subhiksha is registered with the Karnataka Real Estate Regulatory Authority (K-RERA) under registration number PRM/KA/RERA/1251/310/PR/030225/007478.

What is the RERA registration number of GRC Subhiksha?

The K-RERA registration number of GRC Subhiksha is PRM/KA/RERA/1251/310/PR/030225/007478.

What is the current construction status of GRC Subhiksha?

As of Q3 2025-26, GRC Subhiksha is 18% complete according to its latest K-RERA quarterly filing.

Are flats still available in GRC Subhiksha?

Yes. As per the latest K-RERA quarterly filing (Q3 2025-26), GRC Subhiksha has 185 unit(s) available for purchase.

How many flats have been sold in GRC Subhiksha?

As per the latest K-RERA filing (Q3 2025-26), 123 out of 308 units in GRC Subhiksha have been sold or booked.

Are there any RERA complaints against GRC Subhiksha?

As per K-RERA data tracked by rera.watch, there are no complaints currently recorded against GRC Subhiksha.

How many RERA complaints does GRC Infra Pvt. Ltd. have?

GRC Infra Pvt. Ltd., the builder/promoter of GRC Subhiksha, has 1 complaint(s) filed against them across all their K-RERA registered projects in Karnataka.

Who is the builder or developer of GRC Subhiksha?

GRC Subhiksha is developed by GRC Infra Pvt. Ltd., a company registered with K-RERA in Bengaluru Urban, Karnataka.

When did GRC Subhiksha last file a quarterly update with K-RERA?

GRC Subhiksha last filed a quarterly update for Q3 2025-26 on 2026-03-21. The project has submitted 1 quarterly report(s) on K-RERA to date.