Indian Springs
Show financial data (advance collected vs withdrawn)
Quarter-wise Tower Data
No tower breakdown recorded for this quarter.
Show escrow account details
Project details
Show documents on file with K-RERA (121)
| BESCOM (electricity) | on file |
| BWSSB (water & sewerage) | not found |
| Fire NOC | not found |
| KSPCB (pollution control) | not found |
| SEIAA (environmental clearance) | not found |
| Airport / Air Force NOC | not found |
| Telecom (BSNL) NOC | not found |
| Lift license | not found |
| Form-1 (project registration) | not found |
| Form-2/3 (CA certificate) | on file |
| Form-B / Sec 3(1) affidavit | on file |
| Certificate of incorporation | not found |
| GST certificate | on file |
| PAN card | not found |
| Partnership deed / firm registration | on file |
Frequently Asked Questions
Is Indian Springs RERA registered in Karnataka?
Yes. Indian Springs is registered with the Karnataka Real Estate Regulatory Authority (K-RERA) under registration number PRM/KA/RERA/1251/308/PR/100125/007380.
What is the RERA registration number of Indian Springs?
The K-RERA registration number of Indian Springs is PRM/KA/RERA/1251/308/PR/100125/007380.
What is the current construction status of Indian Springs?
As of Q4 2025-26, Indian Springs is 87% complete according to its latest K-RERA quarterly filing.
Are flats still available in Indian Springs?
As per the latest K-RERA filing (Q4 2025-26), Indian Springs is sold out — no units are currently listed as available.
Are there any RERA complaints against Indian Springs?
As per K-RERA data tracked by rera.watch, there are no complaints currently recorded against Indian Springs.
How many RERA complaints does Indian Springs have?
Indian Springs, the builder/promoter of Indian Springs, has 0 complaint(s) filed against them across all their K-RERA registered projects in Karnataka.
Who is the builder or developer of Indian Springs?
Indian Springs is developed by Indian Springs, a partnership firm registered with K-RERA in Bengaluru Urban, Karnataka.
When did Indian Springs last file a quarterly update with K-RERA?
Indian Springs last filed a quarterly update for Q4 2025-26 on 2026-04-15. The project has submitted 2 quarterly report(s) on K-RERA to date.