Projects / Sobha Madison Heights-Townpark Phase 1 W5 to 7
+ Compare with another project

Sobha Madison Heights-Townpark Phase 1 W5 to 7

Bengaluru Urban · SOBHA LIMITED PRM/KA/RERA/1251/308/PR/230125/007420
On track · 26% built
Filed — · Q1 2026-27
Fund safety: no flags
Construction
26%
complete
Sold
340
of 480 total units
Available
140
units
1 BHK: 0
2 BHK: 80
3 BHK: 60
Complaints
0
on project
Construction progress
% complete per quarter
Sales velocity
Units sold per quarter · cumulative booked (line)
Inventory drain
Available units over time
Show financial data (advance collected vs withdrawn)
Quarterly financials
₹ Crore — advance collected vs amount withdrawn this quarter

Quarter-wise Tower Data

Filed: 2026-07-13 · Project 26% complete
WING -5 6% complete
Unit type Total Booked Available
1 BHK 38 38 0
2 BHK 122 78 44
Parking 160 116 44
Floor completion
Floor 0
45.0%
Floor 1
0.0%
Floor 2
0.0%
Floor 3
0.0%
Floor 4
0.0%
Floor 5
0.0%
Floor 6
0.0%
Floor 7
0.0%
Floor 8
0.0%
Floor 9
0.0%
Floor 10
0.0%
Floor 11
0.0%
Floor 12
0.0%
Floor 13
0.0%
Floor 14
0.0%
Floor 15
0.0%
Floor 16
0.0%
Floor 17
0.0%
Floor 18
0.0%
Floor 19
0.0%
Floor 20
0.0%
Floor 21
0.0%
Floor 22
0.0%
Floor 23
0.0%
Floor 24
0.0%
Floor 25
0.0%
Floor 26
0.0%
Floor 27
0.0%
Floor 28
0.0%
Floor 29
0.0%
Floor 30
0.0%
Floor 31
0.0%
Floor 32
0.0%
Floor 33
0.0%
Floor 34
0.0%
Floor 35
0.0%
Floor 36
0.0%
Floor 37
0.0%
Floor 38
0.0%
Floor 39
0.0%
Floor 40
0.0%
Floor 41
0.0%
WING -6 5% complete
Unit type Total Booked Available
1 BHK 38 38 0
2 BHK 122 92 30
Parking 160 130 30
Floor completion
Floor 0
35.0%
Floor 1
0.0%
Floor 2
0.0%
Floor 3
0.0%
Floor 4
0.0%
Floor 5
0.0%
Floor 6
0.0%
Floor 7
0.0%
Floor 8
0.0%
Floor 9
0.0%
Floor 10
0.0%
Floor 11
0.0%
Floor 12
0.0%
Floor 13
0.0%
Floor 14
0.0%
Floor 15
0.0%
Floor 16
0.0%
Floor 17
0.0%
Floor 18
0.0%
Floor 19
0.0%
Floor 20
0.0%
Floor 21
0.0%
Floor 22
0.0%
Floor 23
0.0%
Floor 24
0.0%
Floor 25
0.0%
Floor 26
0.0%
Floor 27
0.0%
Floor 28
0.0%
Floor 29
0.0%
Floor 30
0.0%
Floor 31
0.0%
Floor 32
0.0%
Floor 33
0.0%
Floor 34
0.0%
Floor 35
0.0%
Floor 36
0.0%
Floor 37
0.0%
Floor 38
0.0%
Floor 39
0.0%
Floor 40
0.0%
Floor 41
0.0%
WING -7 10% complete
Unit type Total Booked Available
2 BHK 38 32 6
3 BHK 122 62 60
Parking 160 94 66
Floor completion
Floor 0
100.0%
Floor 1
100.0%
Floor 2
100.0%
Floor 3
100.0%
Floor 4
0.0%
Floor 5
0.0%
Floor 6
0.0%
Floor 7
0.0%
Floor 8
0.0%
Floor 9
0.0%
Floor 10
0.0%
Floor 11
0.0%
Floor 12
0.0%
Floor 13
0.0%
Floor 14
0.0%
Floor 15
0.0%
Floor 16
0.0%
Floor 17
0.0%
Floor 18
0.0%
Floor 19
0.0%
Floor 20
0.0%
Floor 21
0.0%
Floor 22
0.0%
Floor 23
0.0%
Floor 24
0.0%
Floor 25
0.0%
Floor 26
0.0%
Floor 27
0.0%
Floor 28
0.0%
Floor 29
0.0%
Floor 30
0.0%
Floor 31
0.0%
Floor 32
0.0%
Floor 33
0.0%
Floor 34
0.0%
Floor 35
0.0%
Floor 36
0.0%
Floor 37
0.0%
Floor 38
0.0%
Floor 39
0.0%
Floor 40
0.0%
Floor 41
0.0%

Unit Specifications

Unit type Carpet area (sqft) Units
1 BHK 480 152 Estimate ROI →
2 BHK 815–886 564 Estimate ROI →
3 BHK 1,007–1,191 244 Estimate ROI →
Show escrow account details
Escrow Accounts
Bank
KOTAK MAHINDRA BANK
Branch
MG Road, Bangalore
IFSC
KKBK0008066
70% Collection A/C
0249886311
100% A/C
0249886335
30% A/C
0249886359

Project details

Registration no.
PRM/KA/RERA/1251/308/PR/230125/007420
District
Bengaluru Urban
Taluk
Anekal
Promoter
SOBHA LIMITED
Firm type
Company
PAN
AABCS7723E
GSTIN
29AABCS7723E1ZB
Total units
480
Project start
2025-08-01
FAR sanctioned
2.7404
Land/property litigation
No
Proposed completion
2030-12-31
Project address
"PROPOSED RESIDENTIAL DEVELOPMENT PROJECT AT SY.NO.47/1B,47/2B, KYALASANAHALLI VILLAGE , WARD NO.25, MAHADEVAPURA ZONE, K.R. PURAM HOBLI, BANGALORE "

Buyer Risk Report 3 complaints

1 risk signal detected · 3 complaints on file from this project's K-RERA quarterly filings.

Sign in free — no password — to see exactly which quarters and complaints triggered these flags.

Sign in to see full details →
Show documents on file with K-RERA (174)
Documents on file
Government NOCs
BESCOM (electricity) on file
BWSSB (water & sewerage) not found
Fire NOC not found
KSPCB (pollution control) on file
SEIAA (environmental clearance) on file
Airport / Air Force NOC not found
Telecom (BSNL) NOC on file
Lift license not found
RERA statutory forms
Form-1 (project registration) on file
Form-2/3 (CA certificate) on file
Form-B / Sec 3(1) affidavit on file
Company KYC
Certificate of incorporation not found
GST certificate on file
PAN card on file
Partnership deed / firm registration not found
Promoter financials
17 on file
Legal / land documents
46 on file
Other documents
56 on file · 2 marked not available
Plan approvals
26 on file
Sale/allotment documents
2 on file
Site photographs
2 on file
Technical certificates
2 on file
Inventory of documents the promoter has uploaded to their K-RERA project page — not a review of their contents. "Not found" means no filed document matched that item by name; it doesn't necessarily apply to every project (e.g. an airport-proximity NOC).

Frequently Asked Questions

Based on K-RERA registered data for Sobha Madison Heights-Townpark Phase 1 W5 to 7
Is Sobha Madison Heights-Townpark Phase 1 W5 to 7 RERA registered in Karnataka?

Yes. Sobha Madison Heights-Townpark Phase 1 W5 to 7 is registered with the Karnataka Real Estate Regulatory Authority (K-RERA) under registration number PRM/KA/RERA/1251/308/PR/230125/007420.

What is the RERA registration number of Sobha Madison Heights-Townpark Phase 1 W5 to 7?

The K-RERA registration number of Sobha Madison Heights-Townpark Phase 1 W5 to 7 is PRM/KA/RERA/1251/308/PR/230125/007420.

What is the current construction status of Sobha Madison Heights-Townpark Phase 1 W5 to 7?

As of Q1 2026-27, Sobha Madison Heights-Townpark Phase 1 W5 to 7 is 26% complete according to its latest K-RERA quarterly filing.

Are flats still available in Sobha Madison Heights-Townpark Phase 1 W5 to 7?

Yes. As per the latest K-RERA quarterly filing (Q1 2026-27), Sobha Madison Heights-Townpark Phase 1 W5 to 7 has 140 unit(s) available for purchase.

How many flats have been sold in Sobha Madison Heights-Townpark Phase 1 W5 to 7?

As per the latest K-RERA filing (Q1 2026-27), 340 out of 480 units in Sobha Madison Heights-Townpark Phase 1 W5 to 7 have been sold or booked.

Are 2 BHK flats available in Sobha Madison Heights-Townpark Phase 1 W5 to 7?

Yes. According to the latest K-RERA quarterly filing, there are 80 2 BHK unit(s) available in Sobha Madison Heights-Townpark Phase 1 W5 to 7, Bengaluru Urban.

Are 3 BHK flats available in Sobha Madison Heights-Townpark Phase 1 W5 to 7?

Yes. According to the latest K-RERA quarterly filing, there are 60 3 BHK unit(s) available in Sobha Madison Heights-Townpark Phase 1 W5 to 7, Bengaluru Urban.

Are there any RERA complaints against Sobha Madison Heights-Townpark Phase 1 W5 to 7?

As per K-RERA data tracked by rera.watch, there are no complaints currently recorded against Sobha Madison Heights-Townpark Phase 1 W5 to 7.

How many RERA complaints does SOBHA LIMITED have?

SOBHA LIMITED, the builder/promoter of Sobha Madison Heights-Townpark Phase 1 W5 to 7, has 0 complaint(s) filed against them across all their K-RERA registered projects in Karnataka.

Who is the builder or developer of Sobha Madison Heights-Townpark Phase 1 W5 to 7?

Sobha Madison Heights-Townpark Phase 1 W5 to 7 is developed by SOBHA LIMITED, a company registered with K-RERA in Bengaluru Urban, Karnataka.

When did Sobha Madison Heights-Townpark Phase 1 W5 to 7 last file a quarterly update with K-RERA?

Sobha Madison Heights-Townpark Phase 1 W5 to 7 last filed a quarterly update for Q1 2026-27 on 2026-07-13. The project has submitted 3 quarterly report(s) on K-RERA to date.