Projects / THE ADWAITH BY SANJEEVINI
+ Compare with another project

THE ADWAITH BY SANJEEVINI

Bengaluru Urban · SANJEEVINI PROPERTIES PRIVATE LIMITED PRM/KA/RERA/1251/446/PR/140825/007996
On track · 36% built
Filed — · Q2 2026-27
Fund safety: no flags
Construction
36%
complete
Sold
260
of 704 total units
Available
444
units
1 BHK: 58
3 BHK: 360
4 BHK: 26
Complaints
0
on project
Construction progress
% complete per quarter
Sales velocity
Units sold per quarter · cumulative booked (line)
Inventory drain
Available units over time
Show financial data (advance collected vs withdrawn)
Quarterly financials
₹ Crore — advance collected vs amount withdrawn this quarter

Quarter-wise Tower Data

Filed: 2026-10-14 · Project 36% complete
AARKA 36% complete
Unit type Total Booked Available
3 BHK 124 45 79
Parking 248 45 203
Floor completion
Floor 0
100.0%
Floor 1
90.0%
Floor 2
90.0%
Floor 3
50.0%
Floor 4
50.0%
Floor 5
0.0%
Floor 6
0.0%
Floor 7
0.0%
Floor 8
0.0%
Floor 9
0.0%
Floor 10
0.0%
Floor 11
0.0%
Floor 12
0.0%
Floor 13
0.0%
Floor 14
0.0%
Floor 15
0.0%
Floor 16
0.0%
Floor 17
0.0%
Floor 18
0.0%
Floor 19
0.0%
Floor 20
0.0%
Floor 21
0.0%
ANILA 36% complete
Unit type Total Booked Available
1 BHK 18 4 14
3 BHK 104 41 63
4 BHK 23 8 15
Parking 227 53 174
Floor completion
Floor 0
100.0%
Floor 1
85.0%
Floor 2
85.0%
Floor 3
45.0%
Floor 4
45.0%
Floor 5
45.0%
Floor 6
0.0%
Floor 7
0.0%
Floor 8
0.0%
Floor 9
0.0%
Floor 10
0.0%
Floor 11
0.0%
Floor 12
0.0%
Floor 13
0.0%
Floor 14
0.0%
Floor 15
0.0%
Floor 16
0.0%
Floor 17
0.0%
Floor 18
0.0%
Floor 19
0.0%
Floor 20
0.0%
Floor 21
0.0%
Floor 22
0.0%
Floor 23
0.0%
AQUA 36% complete
Unit type Total Booked Available
1 BHK 18 5 13
3 BHK 104 50 54
4 BHK 23 12 11
Parking 227 67 160
Floor completion
Floor 0
100.0%
Floor 1
60.0%
Floor 2
60.0%
Floor 3
45.0%
Floor 4
45.0%
Floor 5
45.0%
Floor 6
0.0%
Floor 7
0.0%
Floor 8
0.0%
Floor 9
0.0%
Floor 10
0.0%
Floor 11
0.0%
Floor 12
0.0%
Floor 13
0.0%
Floor 14
0.0%
Floor 15
0.0%
Floor 16
0.0%
Floor 17
0.0%
Floor 18
0.0%
Floor 19
0.0%
Floor 20
0.0%
Floor 21
0.0%
Floor 22
0.0%
Floor 23
0.0%
ARANYA 36% complete
Unit type Total Booked Available
1 BHK 18 5 13
3 BHK 127 49 78
Parking 227 54 173
Floor completion
Floor 0
100.0%
Floor 1
75.0%
Floor 2
50.0%
Floor 3
50.0%
Floor 4
50.0%
Floor 5
0.0%
Floor 6
0.0%
Floor 7
0.0%
Floor 8
0.0%
Floor 9
0.0%
Floor 10
0.0%
Floor 11
0.0%
Floor 12
0.0%
Floor 13
0.0%
Floor 14
0.0%
Floor 15
0.0%
Floor 16
0.0%
Floor 17
0.0%
Floor 18
0.0%
Floor 19
0.0%
Floor 20
0.0%
Floor 21
0.0%
Floor 22
0.0%
Floor 23
0.0%
AVANI 36% complete
Unit type Total Booked Available
1 BHK 18 — 18
3 BHK 127 41 86
Parking 227 41 186
Floor completion
Floor 0
100.0%
Floor 1
85.0%
Floor 2
85.0%
Floor 3
45.0%
Floor 4
45.0%
Floor 5
45.0%
Floor 6
45.0%
Floor 7
0.0%
Floor 8
0.0%
Floor 9
0.0%
Floor 10
0.0%
Floor 11
0.0%
Floor 12
0.0%
Floor 13
0.0%
Floor 14
0.0%
Floor 15
0.0%
Floor 16
0.0%
Floor 17
0.0%
Floor 18
0.0%
Floor 19
0.0%
Floor 20
0.0%
Floor 21
0.0%
Floor 22
0.0%
Floor 23
0.0%

Unit Specifications

Unit type Carpet area (sqft) Units
1 BHK 471–481 144 Estimate ROI →
3 BHK 963–1,239 1172 Estimate ROI →
4 BHK 1,633 92 Estimate ROI →
Show escrow account details
Escrow Accounts
Bank
HDFC
Branch
Whitefield Main Road
IFSC
HDFC0004182
70% Collection A/C
57500001779987
100% A/C
57500001780222
30% A/C
57500001779807

Project details

Registration no.
PRM/KA/RERA/1251/446/PR/140825/007996
District
Bengaluru Urban
Taluk
Bengaluru East
Promoter
SANJEEVINI PROPERTIES PRIVATE LIMITED
Firm type
Company
PAN
AAXCS8174K
GSTIN
29AAXCS8174K1Z5
Total units
704
Project start
2025-07-01
FAR sanctioned
2.99
Total cost
₹699.53 Cr
Land/property litigation
No
Proposed completion
2028-12-31
Project address
Site No. 167, Pattandur Agrahara Village, K R Puram Hobli, Whitefield, Bangalore -560066
Show documents on file with K-RERA (141)
Documents on file
Government NOCs
BESCOM (electricity) on file
BWSSB (water & sewerage) on file
Fire NOC on file
KSPCB (pollution control) on file
SEIAA (environmental clearance) not found
Airport / Air Force NOC not found
Telecom (BSNL) NOC on file
Lift license not found
RERA statutory forms
Form-1 (project registration) on file
Form-2/3 (CA certificate) on file
Form-B / Sec 3(1) affidavit on file
Company KYC
Certificate of incorporation not found
GST certificate on file
PAN card on file
Partnership deed / firm registration not found
Promoter financials
27 on file
Legal / land documents
9 on file
Other documents
43 on file · 7 marked not available
Plan approvals
22 on file
Sale/allotment documents
4 on file
Technical certificates
5 on file
Inventory of documents the promoter has uploaded to their K-RERA project page — not a review of their contents. "Not found" means no filed document matched that item by name; it doesn't necessarily apply to every project (e.g. an airport-proximity NOC).

Frequently Asked Questions

Based on K-RERA registered data for THE ADWAITH BY SANJEEVINI
Is THE ADWAITH BY SANJEEVINI RERA registered in Karnataka?

Yes. THE ADWAITH BY SANJEEVINI is registered with the Karnataka Real Estate Regulatory Authority (K-RERA) under registration number PRM/KA/RERA/1251/446/PR/140825/007996.

What is the RERA registration number of THE ADWAITH BY SANJEEVINI?

The K-RERA registration number of THE ADWAITH BY SANJEEVINI is PRM/KA/RERA/1251/446/PR/140825/007996.

What is the current construction status of THE ADWAITH BY SANJEEVINI?

As of Q2 2026-27, THE ADWAITH BY SANJEEVINI is 36% complete according to its latest K-RERA quarterly filing.

Are flats still available in THE ADWAITH BY SANJEEVINI?

Yes. As per the latest K-RERA quarterly filing (Q2 2026-27), THE ADWAITH BY SANJEEVINI has 444 unit(s) available for purchase.

How many flats have been sold in THE ADWAITH BY SANJEEVINI?

As per the latest K-RERA filing (Q2 2026-27), 260 out of 704 units in THE ADWAITH BY SANJEEVINI have been sold or booked.

Are 1 BHK flats available in THE ADWAITH BY SANJEEVINI?

Yes. According to the latest K-RERA quarterly filing, there are 58 1 BHK unit(s) available in THE ADWAITH BY SANJEEVINI, Bengaluru Urban.

Are 3 BHK flats available in THE ADWAITH BY SANJEEVINI?

Yes. According to the latest K-RERA quarterly filing, there are 360 3 BHK unit(s) available in THE ADWAITH BY SANJEEVINI, Bengaluru Urban.

Are 4 BHK flats available in THE ADWAITH BY SANJEEVINI?

Yes. According to the latest K-RERA quarterly filing, there are 26 4 BHK unit(s) available in THE ADWAITH BY SANJEEVINI, Bengaluru Urban.

Are there any RERA complaints against THE ADWAITH BY SANJEEVINI?

As per K-RERA data tracked by rera.watch, there are no complaints currently recorded against THE ADWAITH BY SANJEEVINI.

How many RERA complaints does SANJEEVINI PROPERTIES PRIVATE LIMITED have?

SANJEEVINI PROPERTIES PRIVATE LIMITED, the builder/promoter of THE ADWAITH BY SANJEEVINI, has 0 complaint(s) filed against them across all their K-RERA registered projects in Karnataka.

Who is the builder or developer of THE ADWAITH BY SANJEEVINI?

THE ADWAITH BY SANJEEVINI is developed by SANJEEVINI PROPERTIES PRIVATE LIMITED, a company registered with K-RERA in Bengaluru Urban, Karnataka.

When did THE ADWAITH BY SANJEEVINI last file a quarterly update with K-RERA?

THE ADWAITH BY SANJEEVINI last filed a quarterly update for Q2 2026-27 on 2026-10-14. The project has submitted 4 quarterly report(s) on K-RERA to date.