Show documents on file with K-RERA (94)
Documents on file
Government NOCs
BESCOM (electricity)
on file
BWSSB (water & sewerage)
not found
Fire NOC
not found
KSPCB (pollution control)
on file
SEIAA (environmental clearance)
on file
Airport / Air Force NOC
not found
Telecom (BSNL) NOC
not found
Lift license
not found
RERA statutory forms
Form-1 (project registration)
not found
Form-2/3 (CA certificate)
on file
Form-B / Sec 3(1) affidavit
on file
Company KYC
Certificate of incorporation
not found
GST certificate
not found
PAN card
not found
Partnership deed / firm registration
not found
Promoter financials
3 on file
Legal / land documents
13 on file
Other documents
41 on file
· 9 marked not available
Plan approvals
4 on file
Sale/allotment documents
3 on file
Site photographs
4 on file
Technical certificates
2 on file
Inventory of documents the promoter has uploaded to their K-RERA project page — not a review of their contents.
"Not found" means no filed document matched that item by name; it doesn't necessarily apply to every project (e.g. an airport-proximity NOC).
Frequently Asked Questions
Based on K-RERA registered data for Nambiar District 25 Phase 1
Is Nambiar District 25 Phase 1 RERA registered in Karnataka?
Yes. Nambiar District 25 Phase 1 is registered with the Karnataka Real Estate Regulatory Authority (K-RERA) under registration number PRM/KA/RERA/1251/308/PR/100125/007377.
What is the RERA registration number of Nambiar District 25 Phase 1?
The K-RERA registration number of Nambiar District 25 Phase 1 is PRM/KA/RERA/1251/308/PR/100125/007377.
What is the current construction status of Nambiar District 25 Phase 1?
As of Q2 2026-27, Nambiar District 25 Phase 1 is 30% complete according to its latest K-RERA quarterly filing.
Are flats still available in Nambiar District 25 Phase 1?
Yes. As per the latest K-RERA quarterly filing (Q2 2026-27), Nambiar District 25 Phase 1 has 32 unit(s) available for purchase.
How many flats have been sold in Nambiar District 25 Phase 1?
As per the latest K-RERA filing (Q2 2026-27), 764 out of 796 units in Nambiar District 25 Phase 1 have been sold or booked.
Are 3 BHK flats available in Nambiar District 25 Phase 1?
Yes. According to the latest K-RERA quarterly filing, there are 16 3 BHK unit(s) available in Nambiar District 25 Phase 1, Bengaluru Urban.
Are 3.5 BHK flats available in Nambiar District 25 Phase 1?
Yes. According to the latest K-RERA quarterly filing, there are 7 3.5 BHK unit(s) available in Nambiar District 25 Phase 1, Bengaluru Urban.
Are 4 BHK flats available in Nambiar District 25 Phase 1?
Yes. According to the latest K-RERA quarterly filing, there are 9 4 BHK unit(s) available in Nambiar District 25 Phase 1, Bengaluru Urban.
Are there any RERA complaints against Nambiar District 25 Phase 1?
As per K-RERA data tracked by rera.watch, there are no complaints currently recorded against Nambiar District 25 Phase 1.
How many RERA complaints does Nambiar EnsembleResidential Projects LLP have?
Nambiar EnsembleResidential Projects LLP, the builder/promoter of Nambiar District 25 Phase 1, has 2 complaint(s) filed against them across all their K-RERA registered projects in Karnataka.
Who is the builder or developer of Nambiar District 25 Phase 1?
Nambiar District 25 Phase 1 is developed by Nambiar EnsembleResidential Projects LLP, a partnership firm registered with K-RERA in Bengaluru Urban, Karnataka.
When did Nambiar District 25 Phase 1 last file a quarterly update with K-RERA?
Nambiar District 25 Phase 1 last filed a quarterly update for Q2 2026-27 on 2026-10-12. The project has submitted 4 quarterly report(s) on K-RERA to date.