PRUTHVI FAIRFIELDS

Kolar · M/S. PRUTHVI PROJECTS PRM/KA/RERA/1265/347/PR/060825/007972
On track · 0% built
Filed — · Q1 2026-27
Fund safety: no flags
Construction
0%
complete
Sold
—
of ? total units
Available
0
units
Complaints
0
on project
Construction progress
% complete per quarter
Sales velocity
Units sold per quarter · cumulative booked (line)
Inventory drain
Available units over time
Show financial data (advance collected vs withdrawn)
Quarterly financials
₹ Crore — advance collected vs amount withdrawn this quarter

Quarter-wise Tower Data

Filed: 2026-07-15 · Project 0% complete

No tower breakdown recorded for this quarter.

Show escrow account details
Escrow Accounts
Bank
Industrial Development Bank of India
Branch
HSR LAYOUT
IFSC
IBKL0000896
70% Collection A/C
0896102000015969
100% A/C
0896102000015978
30% A/C
0896102000015950

Project details

Registration no.
PRM/KA/RERA/1265/347/PR/060825/007972
District
Kolar
Taluk
Bengaluru South
Promoter
M/S. PRUTHVI PROJECTS
Firm type
Proprietorship
PAN
AICPR9631G
GSTIN
29AICPR631G2ZV
Project start
2025-05-21
Total cost
₹15.12 Cr
Land/property litigation
No
Proposed completion
2028-05-31
Project address
SY NO. 172, 173 & 174 AT MADANAHATTI VILLAGE, , KASABA HOBLI, MALUR TALUK, KOLAR DISTRICT , Maluru , Kolar, Karnataka - 563130

Buyer Risk Report

1 risk signal detected from this project's K-RERA quarterly filings.

Sign in free — no password — to see exactly which quarters and complaints triggered these flags.

Sign in to see full details →
Show documents on file with K-RERA (52)
Documents on file
Government NOCs
BESCOM (electricity) on file
BWSSB (water & sewerage) not found
Fire NOC not found
KSPCB (pollution control) not found
SEIAA (environmental clearance) not found
Airport / Air Force NOC not found
Telecom (BSNL) NOC not found
Lift license not found
RERA statutory forms
Form-1 (project registration) on file
Form-2/3 (CA certificate) not found
Form-B / Sec 3(1) affidavit on file
Company KYC
Certificate of incorporation not found
GST certificate on file
PAN card not found
Partnership deed / firm registration not found
Promoter financials
9 on file
Legal / land documents
6 on file
Other documents
12 on file · 7 marked not available
Plan approvals
3 on file
Sale/allotment documents
3 on file
Technical certificates
2 on file
Inventory of documents the promoter has uploaded to their K-RERA project page — not a review of their contents. "Not found" means no filed document matched that item by name; it doesn't necessarily apply to every project (e.g. an airport-proximity NOC).

Frequently Asked Questions

Based on K-RERA registered data for PRUTHVI FAIRFIELDS
Is PRUTHVI FAIRFIELDS RERA registered in Karnataka?

Yes. PRUTHVI FAIRFIELDS is registered with the Karnataka Real Estate Regulatory Authority (K-RERA) under registration number PRM/KA/RERA/1265/347/PR/060825/007972.

What is the RERA registration number of PRUTHVI FAIRFIELDS?

The K-RERA registration number of PRUTHVI FAIRFIELDS is PRM/KA/RERA/1265/347/PR/060825/007972.

What is the current construction status of PRUTHVI FAIRFIELDS?

As of Q1 2026-27, PRUTHVI FAIRFIELDS is 0% complete according to its latest K-RERA quarterly filing.

Are flats still available in PRUTHVI FAIRFIELDS?

As per the latest K-RERA filing (Q1 2026-27), PRUTHVI FAIRFIELDS is sold out — no units are currently listed as available.

Are there any RERA complaints against PRUTHVI FAIRFIELDS?

As per K-RERA data tracked by rera.watch, there are no complaints currently recorded against PRUTHVI FAIRFIELDS.

How many RERA complaints does M/S. PRUTHVI PROJECTS have?

M/S. PRUTHVI PROJECTS, the builder/promoter of PRUTHVI FAIRFIELDS, has 0 complaint(s) filed against them across all their K-RERA registered projects in Karnataka.

Who is the builder or developer of PRUTHVI FAIRFIELDS?

PRUTHVI FAIRFIELDS is developed by M/S. PRUTHVI PROJECTS, a proprietorship registered with K-RERA in Kolar, Karnataka.

When did PRUTHVI FAIRFIELDS last file a quarterly update with K-RERA?

PRUTHVI FAIRFIELDS last filed a quarterly update for Q1 2026-27 on 2026-07-15. The project has submitted 3 quarterly report(s) on K-RERA to date.