Projects / ESTELLA CMG TOWNSHIP PHASE 1
+ Compare with another project

ESTELLA CMG TOWNSHIP PHASE 1

Kolar · ESTELLA BUILDERS AND DEVELOPERS PRTVATE LIMITED PRM/KA/RERA/1265/343/PR/140126/008400
On track · 10% built
Filed — · Q1 2026-27
Fund safety: no flags
Construction
10%
complete
Sold
—
of ? total units
Available
0
units
Complaints
0
on project
Construction progress
% complete per quarter
Sales velocity
Units sold per quarter · cumulative booked (line)
Inventory drain
Available units over time
Show financial data (advance collected vs withdrawn)
Quarterly financials
₹ Crore — advance collected vs amount withdrawn this quarter

Quarter-wise Tower Data

Filed: 2026-07-14 · Project 10% complete

No tower breakdown recorded for this quarter.

Show escrow account details
Escrow Accounts
Bank
UNITED BANK OF INDIA
Branch
HSR LAYOUT 7TH SECTOR
IFSC
UBIN0554626
70% Collection A/C
546201010050964
100% A/C
546201010050963
30% A/C
546201010050965

Project details

Registration no.
PRM/KA/RERA/1265/343/PR/140126/008400
District
Kolar
Taluk
Anekal
Promoter
ESTELLA BUILDERS AND DEVELOPERS PRTVATE LIMITED
Firm type
Company
PAN
AAECE0970G
GSTIN
29AAECE0970GIZN
Project start
2025-06-02
Total cost
₹52.19 Cr
Land/property litigation
No
Proposed completion
2029-12-30
Project address
Survey No 70, 71/2, 71/5, Chudsandra Village, Sarjapura Hobli, Anekal Taluk, Bangalore
Show documents on file with K-RERA (181)
Documents on file
Government NOCs
BESCOM (electricity) on file
BWSSB (water & sewerage) not found
Fire NOC not found
KSPCB (pollution control) on file
SEIAA (environmental clearance) not found
Airport / Air Force NOC not found
Telecom (BSNL) NOC not found
Lift license not found
RERA statutory forms
Form-1 (project registration) on file
Form-2/3 (CA certificate) not found
Form-B / Sec 3(1) affidavit on file
Company KYC
Certificate of incorporation not found
GST certificate not found
PAN card not found
Partnership deed / firm registration not found
Promoter financials
20 on file
Legal / land documents
38 on file
Other documents
82 on file
Plan approvals
1 on file
Sale/allotment documents
3 on file
Site photographs
22 on file
Technical certificates
1 on file
Inventory of documents the promoter has uploaded to their K-RERA project page — not a review of their contents. "Not found" means no filed document matched that item by name; it doesn't necessarily apply to every project (e.g. an airport-proximity NOC).

Frequently Asked Questions

Based on K-RERA registered data for ESTELLA CMG TOWNSHIP PHASE 1
Is ESTELLA CMG TOWNSHIP PHASE 1 RERA registered in Karnataka?

Yes. ESTELLA CMG TOWNSHIP PHASE 1 is registered with the Karnataka Real Estate Regulatory Authority (K-RERA) under registration number PRM/KA/RERA/1265/343/PR/140126/008400.

What is the RERA registration number of ESTELLA CMG TOWNSHIP PHASE 1?

The K-RERA registration number of ESTELLA CMG TOWNSHIP PHASE 1 is PRM/KA/RERA/1265/343/PR/140126/008400.

What is the current construction status of ESTELLA CMG TOWNSHIP PHASE 1?

As of Q1 2026-27, ESTELLA CMG TOWNSHIP PHASE 1 is 10% complete according to its latest K-RERA quarterly filing.

Are flats still available in ESTELLA CMG TOWNSHIP PHASE 1?

As per the latest K-RERA filing (Q1 2026-27), ESTELLA CMG TOWNSHIP PHASE 1 is sold out — no units are currently listed as available.

Are there any RERA complaints against ESTELLA CMG TOWNSHIP PHASE 1?

As per K-RERA data tracked by rera.watch, there are no complaints currently recorded against ESTELLA CMG TOWNSHIP PHASE 1.

How many RERA complaints does ESTELLA BUILDERS AND DEVELOPERS PRTVATE LIMITED have?

ESTELLA BUILDERS AND DEVELOPERS PRTVATE LIMITED, the builder/promoter of ESTELLA CMG TOWNSHIP PHASE 1, has 0 complaint(s) filed against them across all their K-RERA registered projects in Karnataka.

Who is the builder or developer of ESTELLA CMG TOWNSHIP PHASE 1?

ESTELLA CMG TOWNSHIP PHASE 1 is developed by ESTELLA BUILDERS AND DEVELOPERS PRTVATE LIMITED, a company registered with K-RERA in Kolar, Karnataka.

When did ESTELLA CMG TOWNSHIP PHASE 1 last file a quarterly update with K-RERA?

ESTELLA CMG TOWNSHIP PHASE 1 last filed a quarterly update for Q1 2026-27 on 2026-07-14. The project has submitted 2 quarterly report(s) on K-RERA to date.