Projects / Preeti Green Springs
+ Compare with another project

Preeti Green Springs

Mysore · Preeti Developers Private Limited PRM/KA/RERA/1268/378/PR/121125/008245
On track · 96% built
Filed — · Q1 2026-27
Fund safety: no flags
Construction
96%
complete
Sold
—
of ? total units
Available
0
units
Complaints
0
on project
Construction progress
% complete per quarter
Sales velocity
Units sold per quarter · cumulative booked (line)
Inventory drain
Available units over time
Show financial data (advance collected vs withdrawn)
Quarterly financials
₹ Crore — advance collected vs amount withdrawn this quarter

Quarter-wise Tower Data

Filed: 2026-07-11 · Project 96% complete

No tower breakdown recorded for this quarter.

Show escrow account details
Escrow Accounts
Bank
ICICI Bank
Branch
Bagalur
IFSC
ICIC0002318
70% Collection A/C
231805001364
100% A/C
231805001363
30% A/C
231805001365

Project details

Registration no.
PRM/KA/RERA/1268/378/PR/121125/008245
District
Mysore
Taluk
Yelahanka
Promoter
Preeti Developers Private Limited
Firm type
Company
PAN
AAECP0099H
GSTIN
29AAECP0099H2Z5
Project start
2024-01-01
Total cost
₹22.47 Cr
Land/property litigation
No
Proposed completion
2027-12-31
Project address
1ST MAIN ROAD AGRAHARA BADAVANE BANGALORE, YELAHANKA NORTH

Buyer Risk Report

1 risk signal detected from this project's K-RERA quarterly filings.

Sign in free — no password — to see exactly which quarters and complaints triggered these flags.

Sign in to see full details →
Show documents on file with K-RERA (74)
Documents on file
Government NOCs
BESCOM (electricity) on file
BWSSB (water & sewerage) not found
Fire NOC not found
KSPCB (pollution control) not found
SEIAA (environmental clearance) not found
Airport / Air Force NOC not found
Telecom (BSNL) NOC not found
Lift license not found
RERA statutory forms
Form-1 (project registration) on file
Form-2/3 (CA certificate) on file
Form-B / Sec 3(1) affidavit on file
Company KYC
Certificate of incorporation not found
GST certificate on file
PAN card not found
Partnership deed / firm registration not found
Promoter financials
17 on file
Legal / land documents
8 on file
Other documents
24 on file · 3 marked not available
Plan approvals
4 on file
Sale/allotment documents
2 on file
Technical certificates
1 on file
Inventory of documents the promoter has uploaded to their K-RERA project page — not a review of their contents. "Not found" means no filed document matched that item by name; it doesn't necessarily apply to every project (e.g. an airport-proximity NOC).

Frequently Asked Questions

Based on K-RERA registered data for Preeti Green Springs
Is Preeti Green Springs RERA registered in Karnataka?

Yes. Preeti Green Springs is registered with the Karnataka Real Estate Regulatory Authority (K-RERA) under registration number PRM/KA/RERA/1268/378/PR/121125/008245.

What is the RERA registration number of Preeti Green Springs?

The K-RERA registration number of Preeti Green Springs is PRM/KA/RERA/1268/378/PR/121125/008245.

What is the current construction status of Preeti Green Springs?

As of Q1 2026-27, Preeti Green Springs is 96% complete according to its latest K-RERA quarterly filing.

Are flats still available in Preeti Green Springs?

As per the latest K-RERA filing (Q1 2026-27), Preeti Green Springs is sold out — no units are currently listed as available.

Are there any RERA complaints against Preeti Green Springs?

As per K-RERA data tracked by rera.watch, there are no complaints currently recorded against Preeti Green Springs.

How many RERA complaints does Preeti Developers Private Limited have?

Preeti Developers Private Limited, the builder/promoter of Preeti Green Springs, has 0 complaint(s) filed against them across all their K-RERA registered projects in Karnataka.

Who is the builder or developer of Preeti Green Springs?

Preeti Green Springs is developed by Preeti Developers Private Limited, a company registered with K-RERA in Mysore, Karnataka.

When did Preeti Green Springs last file a quarterly update with K-RERA?

Preeti Green Springs last filed a quarterly update for Q1 2026-27 on 2026-07-11. The project has submitted 3 quarterly report(s) on K-RERA to date.