| CMP/221122/0010374 |
2022-11-22 |
Request for Delay Compensation Claim for Late Handover of Purchased Property |
Disposed
|
| CMP/221116/0010342 |
2022-11-16 |
Delay in possession |
Disposed
|
| CMP/221108/0010228 |
2022-11-08 |
Compensation on the late handing of the Apartment |
Disposed
|
| CMP/220803/0009847 |
2022-08-03 |
Requisition for Delay Compensation for late project delivery of Shriram Summitt SMT 201401 by the builder Shriram Properties Pvt Ltd |
Disposed
|
| CMP/220801/0009835 |
2022-08-01 |
Delayed delivery of flat and unreasonable payment-delay fee charged by builder |
Disposed
|
| CMP/220728/0009826 |
2022-07-28 |
Request for Delay compensation on account of delayed possession by builder for Property: Flat no. 21:11:02, Shriram Summit, Electronic City, Bangalore. |
Disposed
|
| CMP/220625/0009691 |
2022-06-25 |
Builder denied any delay compensation as project is delayed more the 2 year and 6 monts |
Disposed
|
| CMP/220617/0009647 |
2022-06-17 |
Delay in Project and compensation for the delay from RERA |
Disposed
|
| CMP/220518/0009480 |
2022-05-18 |
Request for Compensation for too much delay in handover of Property SHRIRAM SUMMITT WING 19.09.903 |
Disposed
|
| CMP/220516/0009468 |
2022-05-16 |
Excessive Delay in Handover & Not providing Delay Compensation |
Disposed
|
| CMP/220504/0009416 |
2022-05-04 |
Delay in project compensation and flat delivery |
Disposed
|
| CMP/220426/0009388 |
2022-04-26 |
Project Shriram Summit is being delayed and no compnesation from builder. |
Disposed
|
| CMP/220401/0009304 |
2022-04-01 |
Request for compensation for delayed project Flat no 19.08.03. Shriram Summit, electronic city, Bengaluru |
Disposed
|
| CMP/220330/0009289 |
2022-03-30 |
Request for compensation on account of delayed possession by builder. Property: Flat no. 21:03:02, Shriram Summit, Electronic City, Bangalore. |
Disposed
|
| CMP/220329/0009283 |
2022-03-29 |
Delay compensation and Handover of our flat |
Disposed
|
| CMP/220329/0009281 |
2022-03-29 |
Immediate intervention on Compensation and aparment handover date |
Disposed
|
| CMP/220328/0009267 |
2022-03-28 |
Delay in Handover of Flat 211204 ( Compensation Requested ) by SHRIRAM PROPERTIES PRIVATE LIMITED Registration Number : PRM/KA/RERA/1251/308/PR/171015/001121 |
Disposed
|
| CMP/220328/0009264 |
2022-03-28 |
Delay in Project Completion, Failed to adhere to RERA guidelines, No update on compensation |
Disposed
|
| CMP/211222/0008744 |
2021-12-22 |
Delay in possession and requesting compensation from the builder for the delay |
Disposed
|
| CMP/211222/0008741 |
2021-12-22 |
Exorbitant Delay in Possession (3yrs of Delay) |
Disposed
|
| CMP/211108/0008525 |
2021-11-08 |
Delay in possession(31st December 2019) and no compensation payed by Builder |
Disposed
|
| CMP/210926/0008385 |
2021-09-26 |
Refund or Proper Compensation for Delayed Project |
Disposed
|
| CMP/210901/0008291 |
2021-09-01 |
Delivery Date Delayed by almost 2 years & False promises given |
Disposed
|
| CMP/210830/0008283 |
2021-08-30 |
Delay compensation and completion of project |
Disposed
|
| CMP/210825/0008270 |
2021-08-25 |
Delay in Possession, Pre-EMI Interest and compensation is not provided by builder |
Disposed
|
| CMP/210819/0008258 |
2021-08-19 |
Multiple extension in Delivery date of Project Completion and compensation for delay |
Disposed
|
| CMP/210809/0008230 |
2021-08-09 |
Delay in Possession and compensation is not provided by builder |
Disposed
|
| CMP/210718/0008141 |
2021-07-18 |
Shriram Summit Project Delayed |
Disposed
|
| CMP/210717/0008137 |
2021-07-17 |
delayed, compensation or Bank Interest payout until Possession. |
Disposed
|
| CMP/210714/0008129 |
2021-07-14 |
Delayed Compensation |
Disposed
|
| CMP/210706/0008101 |
2021-07-06 |
Need the delay compensation as project is getting delay for more that 2 yrs as per Sales Agreement. |
Disposed
|
| CMP/210705/0008098 |
2021-07-05 |
Delay in possession(31st dec 2019) and no compensation payed by builder |
Disposed
|
| CMP/210623/0008043 |
2021-06-23 |
Delay in Flat Handover |
Disposed
|
| CMP/210623/0008027 |
2021-06-23 |
Multiple extension in Delivery date of Project Completion and compensation for delay |
Disposed
|
| CMP/210615/0007999 |
2021-06-15 |
Compensation on Account of Delay in Possession |
Disposed
|
| CMP/210615/0007997 |
2021-06-15 |
Builder is not delivering the project and denying for delay compensation |
Disposed
|
| CMP/210613/0007995 |
2021-06-13 |
Delay in handover of flat(Agreement completion date:31st Dec 2019) and no compensation from builder |
Disposed
|
| CMP/210613/0007994 |
2021-06-13 |
Project Delay |
Disposed
|
| CMP/210613/0007993 |
2021-06-13 |
Delay in possession(31st dec 2019) and no compensation payed by builder |
Disposed
|
| CMP/210607/0007982 |
2021-06-07 |
Delivery of Project and Compensation for non Delivery on time |
Disposed
|
| CMP/210530/0007968 |
2021-05-30 |
Refund or Delay Compensation. |
Disposed
|
| CMP/210527/0007965 |
2021-05-27 |
Delay Compensation |
Disposed
|
| CMP/210526/0007963 |
2021-05-26 |
Delayed Delivery and No clarity on Compensation( Flat No 210402) |
Disposed
|
| CMP/210526/0007962 |
2021-05-26 |
Compensation Needed for the Delay and Trauma Caused by Builder by NOT Meeting the Project Timeline |
Disposed
|
| CMP/210526/0007961 |
2021-05-26 |
Compensation and delivery of the Apartment |
Disposed
|
| CMP/210525/0007960 |
2021-05-25 |
Delivery Date Expired |
Disposed
|
| CMP/210525/0007959 |
2021-05-25 |
REFUND OR COMPENSATION |
Disposed
|
| CMP/210524/0007958 |
2021-05-24 |
Delay in handover of 2 units and lack of commitment on compensation |
Disposed
|
| CMP/210518/0007953 |
2021-05-18 |
delayed handover by 24 months |
Disposed
|
| CMP/210516/0007950 |
2021-05-16 |
Requesting Refund for delayed project |
Disposed
|
| CMP/210505/0007941 |
2021-05-05 |
Complaint against Shriram Properties Pvt Ltd regards to project Shriram Sameeksha deviation to the original plan for 1. Placing of Organic Waste Converter (OWC) is not in accordance with the sanction |
Disposed
|
| CMP/210211/0007620 |
2021-02-11 |
Cancellation Of Agreement - Shriram Summit 21.14.03 |
Disposed
|
| CMP/201214/0007247 |
2020-12-14 |
Complaint under Section 31 of the Real Estate Regulation and Development Act, 2016 |
Disposed
|
| CMP/201115/0007038 |
2020-11-15 |
Delay in Possession (31-Dec-2019) & No Compensation provisioned by builder. |
Disposed
|
| CMP/201108/0007036 |
2020-11-08 |
Delay in Possession starting 31-Dec-2019 & no compensation provided by builder. |
Disposed
|
| CMP/200929/0006708 |
2020-09-29 |
Delay in Possession starting 31-Dec-2019 & absolutely no compensation provided by builder |
Disposed
|
| CMP/200926/0006622 |
2020-09-26 |
Delay in Possession starting 31-Dec-2019 & absolutely no compensation provided by builder. |
Disposed
|
| CMP/200915/0006595 |
2020-09-15 |
Project is Delayed and also no updates on RERA extension and latest delivery date |
Disposed
|
| CMP/200319/0005761 |
2020-03-19 |
Promoter should pay the interest till they handover the flat to me. |
Disposed
|
| CMP/200317/0005724 |
2020-03-17 |
Delay Compensation Not Paid by Shriram Properties (Shriram Summitt Project) |
Disposed
|
| CMP/200316/0005708 |
2020-03-16 |
Refund of Project Delay Compensation |
Disposed
|
| CMP/200307/0005657 |
2020-03-07 |
Physical Possession , OC & Delay Compensation |
Disposed
|
| CMP/200116/0005234 |
2020-01-16 |
Delayed project completion compensation |
Disposed
|
| CMP/191230/0005092 |
2019-12-30 |
Complaint against Shriram Properties Pvt Ltd regards to project ShriramSameeksha mainly delay compensation, C/P allotment which is located away from our tower approximately at a distance of 300 meters |
Disposed
|
| CMP/191121/0004779 |
2019-11-21 |
Return of delay compensation |
Disposed
|
| CMP/191112/0004676 |
2019-11-12 |
seeking for delay compensation from the date of default till the date of Handover of possession |
Disposed
|
| CMP/191101/0004540 |
2019-11-01 |
Relief Sought from RERA: Delay Compensation as per Agreement and RERA Rules |
Disposed
|
| CMP/191006/0004432 |
2019-10-06 |
Claim for delay compensation,GST INPUT & Interest |
Disposed
|
| CMP/190928/0004334 |
2019-09-28 |
Payment of Delay Compensation as per RERA |
Disposed
|
| CMP/190924/0004282 |
2019-09-24 |
Project delay compensation as per RERA |
Disposed
|
| CMP/190921/0004253 |
2019-09-21 |
Claim of Delay Compensation For Project Delay as per RERA |
Disposed
|
| CMP/190919/0004200 |
2019-09-19 |
DELAY COMPENSATION |
Disposed
|
| CMP/190820/0003892 |
2019-08-20 |
Seeking Delay Compensation in lieu of delay in hand over of unit 11 11 02 as per RERA guidelines |
Disposed
|
| CMP/190814/0003881 |
2019-08-14 |
REQUEST FOR DELAY COMPENSATION AS PER RERA KARNATAKA GUIDELINES DUE TO INORDINATE DELAY IN HANDING OVER OF MY FLAT 11.09.04 BY PROMOTER |
Disposed
|
| CMP/190728/0003739 |
2019-07-28 |
Seeking delay compensation with respect to the flat no 15 09 01 purchased by me in Shriram Summitt as per RERA rules |
Disposed
|
| CMP/190617/0003321 |
2019-06-17 |
Delay Compensation |
Disposed
|
| CMP/190616/0003319 |
2019-06-16 |
Seeking delay compensation with respect to the flat unit 050904 purchased by me in Shriram Summitt as per RERA rules/norms. |
Disposed
|
| CMP/190614/0003241 |
2019-06-14 |
Compensation for delayed project |
Disposed
|
| CMP/190528/0003189 |
2019-05-28 |
Shriram Summitt delayed compensation |
Disposed
|
| CMP/190428/0002803 |
2019-04-28 |
Request for compensation on account of delayed possession by builder. Property: Flat no. 12-04-02, Shriram Summitt, Electronic City, Bangalore. |
Disposed
|
| CMP/190426/0002783 |
2019-04-26 |
Request for compensation on account of delayed possession by builder |
Disposed
|
| CMP/190414/0002594 |
2019-04-14 |
Delay Compensation post delivery date expiry till I get the OC for flat 05-06-02 |
Disposed
|
| CMP/190314/0002393 |
2019-03-14 |
Shriram Summitt - Seeking Compensation for Delay in Handing over the Flat (16-07-03) |
Disposed
|
| CMP/190311/0002339 |
2019-03-11 |
Request for delay compensation as per RERA guidelines because of inordinate delay by the builder in handing over the flat # 05.08.04 in shriram summitt. |
Disposed
|
| CMP/190303/0002293 |
2019-03-03 |
Project Delay compensation |
Disposed
|
| CMP/190223/0002264 |
2019-02-23 |
Project delay compensation |
Disposed
|
| CMP/190217/0002173 |
2019-02-17 |
DELAY COMPENSATION |
Disposed
|
| CMP/190214/0002107 |
2019-02-14 |
Project delayed by 2 years and we end up paying huge amounts towards GST and additional interest, now builder is silent on compensation under RERA act even after promising over mail. |
Disposed
|