Projects / VACATION VILLAGE CHIKKAMAGALURU
+ Compare with another project

VACATION VILLAGE CHIKKAMAGALURU

Chikkamagaluru · ALPL 3 LLP PRM/KA/RERA/1255/477/PR/280126/008430
On track · 5% built
Filed — · Q1 2026-27
Construction
5%
complete
Sold
of ? total units
Available
0
units
Complaints
0
on project
Construction progress
% complete per quarter
Sales velocity
Units sold per quarter · cumulative booked (line)
Inventory drain
Available units over time
Show financial data (advance collected vs withdrawn)
Quarterly financials
₹ Crore — advance collected vs amount withdrawn this quarter

Quarter-wise Tower Data

Filed: 2026-07-15 · Project 5% complete

No tower breakdown recorded for this quarter.

Show escrow account details
Escrow Accounts
Bank
KOTAK MAHINDRA BANK
Branch
Jakkur
IFSC
KKBK0008146
70% Collection A/C
3333111147
100% A/C
3333111145
30% A/C
3333111133

Project details

Registration no.
PRM/KA/RERA/1255/477/PR/280126/008430
District
Chikkamagaluru
Taluk
Bengaluru North
Promoter
ALPL 3 LLP
Firm type
Partnership Firm
PAN
ACFFA5173M
GSTIN
29ACFFA5173M1ZY
Total cost
₹49.03 Cr
Project start
2025-08-01
Proposed completion
2030-12-31
Project address
Sy. Nos. 29/5, 29/6, 29/7, 29/11, 29/17, 31, 32/2, 45 & 46, situated at Hebbali Village, Kasaba Hobali , Chikkamagaluru taluk , Chikkamagaluru , Chikkamagaluru, Karnataka - 577131

Frequently Asked Questions

Based on K-RERA registered data for VACATION VILLAGE CHIKKAMAGALURU
Is VACATION VILLAGE CHIKKAMAGALURU RERA registered in Karnataka?

Yes. VACATION VILLAGE CHIKKAMAGALURU is registered with the Karnataka Real Estate Regulatory Authority (K-RERA) under registration number PRM/KA/RERA/1255/477/PR/280126/008430.

What is the RERA registration number of VACATION VILLAGE CHIKKAMAGALURU?

The K-RERA registration number of VACATION VILLAGE CHIKKAMAGALURU is PRM/KA/RERA/1255/477/PR/280126/008430.

What is the current construction status of VACATION VILLAGE CHIKKAMAGALURU?

As of Q1 2026-27, VACATION VILLAGE CHIKKAMAGALURU is 5% complete according to its latest K-RERA quarterly filing.

Are flats still available in VACATION VILLAGE CHIKKAMAGALURU?

As per the latest K-RERA filing (Q1 2026-27), VACATION VILLAGE CHIKKAMAGALURU is sold out — no units are currently listed as available.

Are there any RERA complaints against VACATION VILLAGE CHIKKAMAGALURU?

As per K-RERA data tracked by rera.watch, there are no complaints currently recorded against VACATION VILLAGE CHIKKAMAGALURU.

How many RERA complaints does ALPL 3 LLP have?

ALPL 3 LLP, the builder/promoter of VACATION VILLAGE CHIKKAMAGALURU, has 0 complaint(s) filed against them across all their K-RERA registered projects in Karnataka.

Who is the builder or developer of VACATION VILLAGE CHIKKAMAGALURU?

VACATION VILLAGE CHIKKAMAGALURU is developed by ALPL 3 LLP, a partnership firm registered with K-RERA in Chikkamagaluru, Karnataka.

When did VACATION VILLAGE CHIKKAMAGALURU last file a quarterly update with K-RERA?

VACATION VILLAGE CHIKKAMAGALURU last filed a quarterly update for Q1 2026-27 on 2026-07-15. The project has submitted 2 quarterly report(s) on K-RERA to date.