Projects / Aratt-Escapes Phase 2
+ Compare with another project

Aratt-Escapes Phase 2

Bengaluru Urban · ARATT CITY TOWERS LLP PRM/KA/RERA/1251/309/PR/290626/008767
On track · 55% built
Filed — · Q1 2026-27
Fund safety: no flags
Construction
55%
complete
Sold
—
of ? total units
Available
0
units
Complaints
0
on project · 1 on builder
Construction progress
% complete per quarter
Sales velocity
Units sold per quarter · cumulative booked (line)
Inventory drain
Available units over time
Show financial data (advance collected vs withdrawn)
Quarterly financials
₹ Crore — advance collected vs amount withdrawn this quarter

Quarter-wise Tower Data

Filed: 2026-07-15 · Project 55% complete

No tower breakdown recorded for this quarter.

Show escrow account details
Escrow Accounts
Bank
ICICI Bank
Branch
Ulsoor Road Branch
IFSC
ICIC0003049
70% Collection A/C
777705131902
100% A/C
777705131901
30% A/C
777705131903

Project details

Registration no.
PRM/KA/RERA/1251/309/PR/290626/008767
District
Bengaluru Urban
Taluk
Bengaluru North
Promoter
ARATT CITY TOWERS LLP
Firm type
Partnership Firm
PAN
ABFFA7901C
GSTIN
29ABFFA7901C1ZP
Project start
2026-04-20
Total cost
₹6.84 Cr
Land/property litigation
No
Proposed completion
2028-04-20
Project address
SY NO 67/3 AND 67/4, MARGONDANAHALLI VILLAGE JIGANI HOBLI ANEKALTALUK
Show documents on file with K-RERA (71)
Documents on file
Government NOCs
BESCOM (electricity) on file
BWSSB (water & sewerage) not found
Fire NOC not found
KSPCB (pollution control) not found
SEIAA (environmental clearance) not found
Airport / Air Force NOC not found
Telecom (BSNL) NOC not found
Lift license not found
RERA statutory forms
Form-1 (project registration) on file
Form-2/3 (CA certificate) on file
Form-B / Sec 3(1) affidavit on file
Company KYC
Certificate of incorporation not found
GST certificate on file
PAN card on file
Partnership deed / firm registration not found
Promoter financials
6 on file
Legal / land documents
3 on file
Other documents
21 on file · 13 marked not available
Plan approvals
4 on file
Sale/allotment documents
7 on file
Site photographs
2 on file
Technical certificates
3 on file
Inventory of documents the promoter has uploaded to their K-RERA project page — not a review of their contents. "Not found" means no filed document matched that item by name; it doesn't necessarily apply to every project (e.g. an airport-proximity NOC).

Frequently Asked Questions

Based on K-RERA registered data for Aratt-Escapes Phase 2
Is Aratt-Escapes Phase 2 RERA registered in Karnataka?

Yes. Aratt-Escapes Phase 2 is registered with the Karnataka Real Estate Regulatory Authority (K-RERA) under registration number PRM/KA/RERA/1251/309/PR/290626/008767.

What is the RERA registration number of Aratt-Escapes Phase 2?

The K-RERA registration number of Aratt-Escapes Phase 2 is PRM/KA/RERA/1251/309/PR/290626/008767.

What is the current construction status of Aratt-Escapes Phase 2?

As of Q1 2026-27, Aratt-Escapes Phase 2 is 55% complete according to its latest K-RERA quarterly filing.

Are flats still available in Aratt-Escapes Phase 2?

As per the latest K-RERA filing (Q1 2026-27), Aratt-Escapes Phase 2 is sold out — no units are currently listed as available.

Are there any RERA complaints against Aratt-Escapes Phase 2?

As per K-RERA data tracked by rera.watch, there are no complaints currently recorded against Aratt-Escapes Phase 2.

How many RERA complaints does ARATT CITY TOWERS LLP have?

ARATT CITY TOWERS LLP, the builder/promoter of Aratt-Escapes Phase 2, has 1 complaint(s) filed against them across all their K-RERA registered projects in Karnataka.

Who is the builder or developer of Aratt-Escapes Phase 2?

Aratt-Escapes Phase 2 is developed by ARATT CITY TOWERS LLP, a partnership firm registered with K-RERA in Bengaluru Urban, Karnataka.

When did Aratt-Escapes Phase 2 last file a quarterly update with K-RERA?

Aratt-Escapes Phase 2 last filed a quarterly update for Q1 2026-27 on 2026-07-15. The project has submitted 1 quarterly report(s) on K-RERA to date.