Adarsh Lake front

Bengaluru Urban · · PRM/KA/RERA/1251/310/PR/170915/000155
⚠️ Complaints
81%
Construction complete
171
Units sold / ? total
159
Units available
3 BHK: 123
4 BHK: 36
8
Complaints on project
19 on builder

Construction progress

% complete per quarter

Sales velocity

Units sold per quarter (bar) · Cumulative booked (line)

Inventory drain

Available units over time

Show financial data (advance collected vs withdrawn)

Quarterly financials

₹ Crore — advance collected vs amount withdrawn this quarter

Quarter-wise Tower Data

Filed: 2026-04-15 · Project 81% complete
A 93%% complete
Unit type Total Booked Available
3 BHK 46 6 40
Parking 46 6 40
B 93%% complete
Unit type Total Booked Available
3 BHK 92 40 52
Parking 92 40 52
C 93%% complete
Unit type Total Booked Available
3 BHK 96 65 31
Parking 96 65 31
D 82%% complete
Unit type Total Booked Available
4 BHK 96 60 36
Parking 96 60 36

Project details

Registration no.
PRM/KA/RERA/1251/310/PR/170915/000155
District
Bengaluru Urban
Total cost