Sobha Dream Acres - Tropical Greens Phase 22 Wing 23 and 24
Show financial data (advance collected vs withdrawn)
Quarter-wise Tower Data
Wing 23 100% complete
| Unit type | Total | Booked | Available |
|---|---|---|---|
| 1 BHK | 3 | 3 | 0 |
| 1 BHK | 3 | 3 | 0 |
| 2 BHK | 114 | 114 | 0 |
| 2 BHK | 114 | 114 | 0 |
| Parking | 117 | 117 | — |
Wing 24 100% complete
| Unit type | Total | Booked | Available |
|---|---|---|---|
| 1 BHK | 3 | 3 | 0 |
| 1 BHK | 3 | 3 | 0 |
| 2 BHK | 117 | 117 | 0 |
| 2 BHK | 117 | 117 | 0 |
| Parking | 120 | 120 | — |
Unit Specifications
| Unit type | Carpet area (sqft) | Units | |
|---|---|---|---|
| 1 BHK | 5,464 | 6 | Estimate ROI → |
| 2 BHK | 7,551–7,565 | 231 | Estimate ROI → |
Show escrow account details
Registration Extension
Promoters can apply for a Section 6 extensionA formal application under RERA Section 6 for more time to complete the project, requiring a stated reason — distinct from the automatic, government-wide Covid extension every project received. when they can't meet the originally registered completion date.
| Event | Start date | Proposed completion | |
|---|---|---|---|
| At the time of Registration | 2018-07-01 | 2025-06-30 | Certificate → |
| Covid Extension | 2025-06-30 | 2026-03-30 | Certificate → |
Registry Details
Want the latest sale-deed / registration status for this project? Our team will look it up for you.
A few details and our team will look this up for you.
✓ We're on it — our team will reach out to you shortly.
Project details
Show documents on file with K-RERA (104)
| BESCOM (electricity) | on file |
| BWSSB (water & sewerage) | on file |
| Fire NOC | on file |
| KSPCB (pollution control) | on file |
| SEIAA (environmental clearance) | on file |
| Airport / Air Force NOC | not found |
| Telecom (BSNL) NOC | not found |
| Lift license | not found |
| Form-1 (project registration) | not found |
| Form-2/3 (CA certificate) | not found |
| Form-B / Sec 3(1) affidavit | not found |
| Certificate of incorporation | not found |
| GST certificate | not found |
| PAN card | on file |
| Partnership deed / firm registration | not found |
Frequently Asked Questions
Is Sobha Dream Acres - Tropical Greens Phase 22 Wing 23 and 24 RERA registered in Karnataka?
Yes. Sobha Dream Acres - Tropical Greens Phase 22 Wing 23 and 24 is registered with the Karnataka Real Estate Regulatory Authority (K-RERA) under registration number PRM/KA/RERA/1251/446/PR/181010/002037.
What is the RERA registration number of Sobha Dream Acres - Tropical Greens Phase 22 Wing 23 and 24?
The K-RERA registration number of Sobha Dream Acres - Tropical Greens Phase 22 Wing 23 and 24 is PRM/KA/RERA/1251/446/PR/181010/002037.
What is the current construction status of Sobha Dream Acres - Tropical Greens Phase 22 Wing 23 and 24?
As of Q4 2025-26, Sobha Dream Acres - Tropical Greens Phase 22 Wing 23 and 24 is 100% complete — construction has finished according to its latest K-RERA quarterly filing.
Are flats still available in Sobha Dream Acres - Tropical Greens Phase 22 Wing 23 and 24?
As per the latest K-RERA filing (Q4 2025-26), Sobha Dream Acres - Tropical Greens Phase 22 Wing 23 and 24 is sold out — no units are currently listed as available.
Are there any RERA complaints against Sobha Dream Acres - Tropical Greens Phase 22 Wing 23 and 24?
As per K-RERA data tracked by rera.watch, there are no complaints currently recorded against Sobha Dream Acres - Tropical Greens Phase 22 Wing 23 and 24.
When did Sobha Dream Acres - Tropical Greens Phase 22 Wing 23 and 24 last file a quarterly update with K-RERA?
Sobha Dream Acres - Tropical Greens Phase 22 Wing 23 and 24 last filed a quarterly update for Q4 2025-26 on 2026-04-09. The project has submitted 2 quarterly report(s) on K-RERA to date.