Sobha Royal Pavilion Phase 5 - Wing 8 and 9
⚠️ Complaints
✅ Delivered
100%
Construction complete
151
Units sold / ? total
0
Units available
2 BHK: 0
3 BHK: 0
0
Complaints on project
221 on builder
Construction progress
% complete per quarter
Sales velocity
Units sold per quarter (bar) · Cumulative booked (line)
Inventory drain
Available units over time
Show financial data (advance collected vs withdrawn)
Quarterly financials
₹ Crore — advance collected vs amount withdrawn this quarter
Quarter-wise Tower Data
Filed: 2026-04-09 · Project 100% complete
wing 8 100%% complete
| Unit type | Total | Booked | Available |
|---|---|---|---|
| 2 BHK | 4 | 4 | 0 |
| 3 BHK | 72 | 72 | 0 |
| Parking | 76 | 76 | — |
wing 9 100%% complete
| Unit type | Total | Booked | Available |
|---|---|---|---|
| 2 BHK | 4 | 4 | 0 |
| 3 BHK | 71 | 71 | 0 |
| Parking | 75 | 75 | — |
Project details
- Registration no.
- PRM/KA/RERA/1251/446/PR/190204/002341
- District
- Bengaluru Urban
- Total cost
- —