Skanda Enclave 3
Show financial data (advance collected vs withdrawn)
Quarter-wise Tower Data
No tower breakdown recorded for this quarter.
Show escrow account details
Registration Extension
Promoters can apply for a Section 6 extensionA formal application under RERA Section 6 for more time to complete the project, requiring a stated reason — distinct from the automatic, government-wide Covid extension every project received. when they can't meet the originally registered completion date.
| Event | Start date | Proposed completion | |
|---|---|---|---|
| At the time of Registration | 2019-04-10 | 2026-04-10 | Certificate → |
| Covid Extension | 2026-04-10 | 2027-01-10 | Certificate → |
Project details
Show documents on file with K-RERA (54)
| BESCOM (electricity) | not found |
| BWSSB (water & sewerage) | not found |
| Fire NOC | not found |
| KSPCB (pollution control) | on file |
| SEIAA (environmental clearance) | not found |
| Airport / Air Force NOC | not found |
| Telecom (BSNL) NOC | not found |
| Lift license | not found |
| Form-1 (project registration) | not found |
| Form-2/3 (CA certificate) | not found |
| Form-B / Sec 3(1) affidavit | on file |
| Certificate of incorporation | not found |
| GST certificate | not found |
| PAN card | on file |
| Partnership deed / firm registration | not found |
Frequently Asked Questions
Is Skanda Enclave 3 RERA registered in Karnataka?
Yes. Skanda Enclave 3 is registered with the Karnataka Real Estate Regulatory Authority (K-RERA) under registration number PRM/KA/RERA/1268/378/PR/190809/002799.
What is the RERA registration number of Skanda Enclave 3?
The K-RERA registration number of Skanda Enclave 3 is PRM/KA/RERA/1268/378/PR/190809/002799.
What is the current construction status of Skanda Enclave 3?
As of Q1 2026-27, Skanda Enclave 3 is 99% complete according to its latest K-RERA quarterly filing.
Are flats still available in Skanda Enclave 3?
As per the latest K-RERA filing (Q1 2026-27), Skanda Enclave 3 is sold out — no units are currently listed as available.
Are there any RERA complaints against Skanda Enclave 3?
As per K-RERA data tracked by rera.watch, there are no complaints currently recorded against Skanda Enclave 3.
When did Skanda Enclave 3 last file a quarterly update with K-RERA?
Skanda Enclave 3 last filed a quarterly update for Q1 2026-27 on 2026-07-15. The project has submitted 3 quarterly report(s) on K-RERA to date.