The Magic Faraway Tree Phase 2
Show financial data (advance collected vs withdrawn)
Quarter-wise Tower Data
Tower 03 (B2-as per sanction) 75% complete
| Unit type | Total | Booked | Available |
|---|---|---|---|
| 3 BHK | 120 | 109 | 11 |
| Parking | 240 | 218 | 22 |
Tower 04 (B3-as per sanction) 90% complete
| Unit type | Total | Booked | Available |
|---|---|---|---|
| 3 BHK | 120 | 114 | 6 |
| Parking | 240 | 228 | 12 |
Tower 03 (B2-as per sanction) 60% complete
| Unit type | Total | Booked | Available |
|---|---|---|---|
| 3 BHK | 120 | 109 | 11 |
| 3 BHK | 120 | 109 | 11 |
| 3 BHK | 120 | 109 | 11 |
| 3 BHK | 120 | 109 | 11 |
| Parking | 240 | 218 | 22 |
Tower 04 (B3-as per sanction) 83% complete
| Unit type | Total | Booked | Available |
|---|---|---|---|
| 3 BHK | 120 | 114 | 6 |
| 3 BHK | 120 | 114 | 6 |
| 3 BHK | 120 | 114 | 6 |
| 3 BHK | 120 | 114 | 6 |
| Parking | 240 | 228 | 12 |
Tower 03 (B2-as per sanction) 51% complete
| Unit type | Total | Booked | Available |
|---|---|---|---|
| 3 BHK | 120 | 109 | 11 |
| 3 BHK | 120 | 109 | 11 |
| 3 BHK | 120 | 109 | 11 |
| 3 BHK | 120 | 109 | 11 |
| 3 BHK | 120 | 109 | 11 |
| 3 BHK | 120 | 109 | 11 |
| 3 BHK | 120 | 109 | 11 |
| 3 BHK | 120 | 109 | 11 |
| 3 BHK | 120 | 109 | 11 |
| 3 BHK | 120 | 109 | 11 |
| Parking | 240 | 218 | 22 |
Tower 04 (B3-as per sanction) 91% complete
| Unit type | Total | Booked | Available |
|---|---|---|---|
| 3 BHK | 120 | 114 | 6 |
| 3 BHK | 120 | 114 | 6 |
| 3 BHK | 120 | 114 | 6 |
| 3 BHK | 120 | 114 | 6 |
| 3 BHK | 120 | 114 | 6 |
| 3 BHK | 120 | 114 | 6 |
| 3 BHK | 120 | 114 | 6 |
| 3 BHK | 120 | 114 | 6 |
| 3 BHK | 120 | 114 | 6 |
| 3 BHK | 120 | 114 | 6 |
| Parking | 240 | 228 | 12 |
Tower 03 (B2-as per sanction) 50% complete
| Unit type | Total | Booked | Available |
|---|---|---|---|
| 3 BHK | 120 | 109 | 11 |
| 3 BHK | 120 | 109 | 11 |
| 3 BHK | 120 | 109 | 11 |
| 3 BHK | 120 | 109 | 11 |
| 3 BHK | 120 | 109 | 11 |
| 3 BHK | 120 | 109 | 11 |
| 3 BHK | 120 | 109 | 11 |
| 3 BHK | 120 | 109 | 11 |
| 3 BHK | 120 | 109 | 11 |
| 3 BHK | 120 | 109 | 11 |
| Parking | 240 | 218 | 22 |
Tower 04 (B3-as per sanction) 90% complete
| Unit type | Total | Booked | Available |
|---|---|---|---|
| 3 BHK | 120 | 114 | 6 |
| 3 BHK | 120 | 114 | 6 |
| 3 BHK | 120 | 114 | 6 |
| 3 BHK | 120 | 114 | 6 |
| 3 BHK | 120 | 114 | 6 |
| 3 BHK | 120 | 114 | 6 |
| 3 BHK | 120 | 114 | 6 |
| 3 BHK | 120 | 114 | 6 |
| 3 BHK | 120 | 114 | 6 |
| 3 BHK | 120 | 114 | 6 |
| Parking | 240 | 228 | 12 |
Unit Specifications
| Unit type | Carpet area (sqft) | Units | |
|---|---|---|---|
| 3 BHK | 1,647–2,648 | 240 | Estimate ROI → |
Show escrow account details
- Bank
- RATNAKAR BANK
- Branch
- Residency Road
- IFSC
- RATN0000156
- 70% Collection A/C
- 409000519475
Registration Extension Extension granted
Promoters can apply for a Section 6 extensionA formal application under RERA Section 6 for more time to complete the project, requiring a stated reason — distinct from the automatic, government-wide Covid extension every project received. when they can't meet the originally registered completion date.
Promoter's stated reason for delay: Force Majeure
| Event | Start date | Proposed completion | |
|---|---|---|---|
| At the time of Registration | 2016-03-02 | 2023-12-31 | Certificate → |
| Covid Extension | 2023-12-31 | 2024-09-30 | Certificate → |
| Section 6 Extension | 2024-09-30 | 2025-09-30 | Certificate → |
| Further Extension | 2025-09-30 | 2027-09-30 | Certificate → |
- Extension applied on
- 2024-09-24
- Extension approved on
- 2024-11-28
- Extension registration no.
- EX/PRM/KA/RERA/1251/310/PR/241128/000424
Project details
- Registration no.
- PRM/KA/RERA/1251/310/PR/171015/000424
- District
- Bengaluru Urban
- Taluk
- Bengaluru South
- Promoter
- Total Environment Building Systems Pvt Ltd
- Firm type
- Company
- PAN
- AABCT9452F
- Project start
- 2016-03-02
- FAR sanctioned
- 2.5
- Land area
- 87,716 sqft
- Proposed completion
- 2025-09-30 overdue
- Project address
- Survey no 32 part1 and 33 part 1 and 33 part 2 Kanakapura Road, Tallaghattapura
Buyer Risk Report 3 complaints
3 risk signals detected · 3 complaints on file from this project's K-RERA quarterly filings.
Sign in free — no password — to see exactly which quarters and complaints triggered these flags.
Sign in to see full details →A few details and our team will reach out — no referral fee, just a connection.
✓ We're on it — our team will reach out to you shortly.
Show documents on file with K-RERA (71)
| BESCOM (electricity) | on file |
| BWSSB (water & sewerage) | on file |
| Fire NOC | on file |
| KSPCB (pollution control) | on file |
| SEIAA (environmental clearance) | not found |
| Airport / Air Force NOC | not found |
| Telecom (BSNL) NOC | on file |
| Lift license | not found |
| Form-1 (project registration) | not found |
| Form-2/3 (CA certificate) | not found |
| Form-B / Sec 3(1) affidavit | not found |
| Certificate of incorporation | not found |
| GST certificate | not found |
| PAN card | not found |
| Partnership deed / firm registration | not found |
- Promoter financials
- 10 on file
- Legal / land documents
- 5 on file
- Other documents
- 28 on file · 1 marked not available
- Plan approvals
- 3 on file
- Sale/allotment documents
- 4 on file
- Site photographs
- 1 on file
- Technical certificates
- 2 on file
Certificate cross-check AI-generated
Promoter self-reported 72% complete for Q1 2026-27. An AI reading of 3 filed certificates is available.
Sign in free — no password — to see what each certificate independently states.
Sign in to see full details →Frequently Asked Questions
Is The Magic Faraway Tree Phase 2 RERA registered in Karnataka?
Yes. The Magic Faraway Tree Phase 2 is registered with the Karnataka Real Estate Regulatory Authority (K-RERA) under registration number PRM/KA/RERA/1251/310/PR/171015/000424.
What is the RERA registration number of The Magic Faraway Tree Phase 2?
The K-RERA registration number of The Magic Faraway Tree Phase 2 is PRM/KA/RERA/1251/310/PR/171015/000424.
What is the current construction status of The Magic Faraway Tree Phase 2?
As of Q2 2026-27, The Magic Faraway Tree Phase 2 is 82% complete according to its latest K-RERA quarterly filing.
Are flats still available in The Magic Faraway Tree Phase 2?
Yes. As per the latest K-RERA quarterly filing (Q2 2026-27), The Magic Faraway Tree Phase 2 has 17 unit(s) available for purchase.
Are 3 BHK flats available in The Magic Faraway Tree Phase 2?
Yes. According to the latest K-RERA quarterly filing, there are 17 3 BHK unit(s) available in The Magic Faraway Tree Phase 2, Bengaluru Urban.
Are there any RERA complaints against The Magic Faraway Tree Phase 2?
Yes. The Magic Faraway Tree Phase 2 has 3 complaint(s) filed against it on the K-RERA portal. Review these on the official K-RERA website before making a purchase decision.
How many RERA complaints does Total Environment Building Systems Pvt Ltd have?
Total Environment Building Systems Pvt Ltd, the builder/promoter of The Magic Faraway Tree Phase 2, has 14 complaint(s) filed against them across all their K-RERA registered projects in Karnataka.
Who is the builder or developer of The Magic Faraway Tree Phase 2?
The Magic Faraway Tree Phase 2 is developed by Total Environment Building Systems Pvt Ltd, a company registered with K-RERA in Bengaluru Urban, Karnataka.
When did The Magic Faraway Tree Phase 2 last file a quarterly update with K-RERA?
The Magic Faraway Tree Phase 2 last filed a quarterly update for Q2 2026-27 on 2026-10-15. The project has submitted 4 quarterly report(s) on K-RERA to date.