Projects / AMBIENCE DOWNTOWN
+ Compare with another project

AMBIENCE DOWNTOWN

Bengaluru Urban PRM/KA/RERA/1251/446/PR/191107/002995
On track · 47% built
Filed — · Q1 2026-27
Fund safety: no flags
Construction
47%
complete
Sold
45
of ? total units
Available
47
units
3 BHK: 72
4 BHK: 20
5 BHK: 2
Complaints
0
on project
Construction progress
% complete per quarter
Sales velocity
Units sold per quarter · cumulative booked (line)
Inventory drain
Available units over time
Show financial data (advance collected vs withdrawn)
Quarterly financials
₹ Crore — advance collected vs amount withdrawn this quarter

Quarter-wise Tower Data

Filed: 2026-07-15 · Project 47% complete
TOWER A 47% complete
Unit type Total Booked Available
3 BHK 64 28 36
3 BHK 64 28 36
4 BHK 26 16 10
4 BHK 26 16 10
5 BHK 2 1 1
5 BHK 2 1 1
Parking 336 43 293
Floor completion
Floor 0
80.0%
Floor 0
80.0%
Floor 1
80.0%
Floor 1
80.0%
Floor 2
80.0%
Floor 2
80.0%
Floor 3
80.0%
Floor 3
80.0%
Floor 4
80.0%
Floor 4
80.0%
Floor 5
80.0%
Floor 5
80.0%
Floor 6
80.0%
Floor 6
80.0%
Floor 7
80.0%
Floor 7
80.0%
Floor 8
80.0%
Floor 8
80.0%
Floor 9
80.0%
Floor 9
80.0%
Floor 10
80.0%
Floor 10
80.0%
Floor 11
80.0%
Floor 11
80.0%
Floor 12
80.0%
Floor 12
80.0%
Floor 13
70.0%
Floor 13
70.0%

Unit Specifications

Unit type Carpet area (sqft) Units
3 BHK 1,485–1,701 64 Estimate ROI →
4 BHK 1,873–2,971 26 Estimate ROI →
5 BHK 3,208–3,251 2 Estimate ROI →
Show escrow account details
Escrow Accounts
Bank
HDFC
Branch
Old Airport Road
IFSC
HDFC0000075
70% Collection A/C
57500000843237

Registration Extension Extension granted

Promoters can apply for a Section 6 extensionA formal application under RERA Section 6 for more time to complete the project, requiring a stated reason — distinct from the automatic, government-wide Covid extension every project received. when they can't meet the originally registered completion date.

Promoter's stated reason for delay: Applied for modification

Event Start date Proposed completion
At the time of Registration 2019-10-19 2023-03-31 Certificate →
Covid Extension 2023-03-31 2023-12-31 Certificate →
Section 6 Extension 2023-12-30 2024-12-30 Certificate →
Further Extension 2024-12-30 2026-12-31 Certificate →
Extension applied on
2023-09-30
Extension approved on
2023-10-10
Extension registration no.
EX/PRM/KA/RERA/1251/446/PR/231010/002995

Project details

Registration no.
PRM/KA/RERA/1251/446/PR/191107/002995
District
Bengaluru Urban
Taluk
Bengaluru East
Project start
2019-10-19
FAR sanctioned
2.5
Land area
92,861 sqft
Proposed completion
2024-12-30 overdue
Project address
Survey No 59/2 of Lingarajapuram ,Village, Kasaba Hobli,, BBMP Ward No 28, Banaswadi Layout,

Buyer Risk Report

1 risk signal detected from this project's K-RERA quarterly filings.

Sign in free — no password — to see exactly which quarters and complaints triggered these flags.

Sign in to see full details →
Show documents on file with K-RERA (122)
Documents on file
Government NOCs
BESCOM (electricity) on file
BWSSB (water & sewerage) on file
Fire NOC on file
KSPCB (pollution control) on file
SEIAA (environmental clearance) not found
Airport / Air Force NOC not found
Telecom (BSNL) NOC on file
Lift license not found
RERA statutory forms
Form-1 (project registration) not found
Form-2/3 (CA certificate) not found
Form-B / Sec 3(1) affidavit on file
Company KYC
Certificate of incorporation not found
GST certificate not found
PAN card on file
Partnership deed / firm registration not found
Promoter financials
5 on file · 5 marked not available
Legal / land documents
14 on file
Other documents
40 on file · 4 marked not available
Plan approvals
12 on file
Sale/allotment documents
9 on file
Site photographs
2 on file
Technical certificates
5 on file
Inventory of documents the promoter has uploaded to their K-RERA project page — not a review of their contents. "Not found" means no filed document matched that item by name; it doesn't necessarily apply to every project (e.g. an airport-proximity NOC).

Frequently Asked Questions

Based on K-RERA registered data for AMBIENCE DOWNTOWN
Is AMBIENCE DOWNTOWN RERA registered in Karnataka?

Yes. AMBIENCE DOWNTOWN is registered with the Karnataka Real Estate Regulatory Authority (K-RERA) under registration number PRM/KA/RERA/1251/446/PR/191107/002995.

What is the RERA registration number of AMBIENCE DOWNTOWN?

The K-RERA registration number of AMBIENCE DOWNTOWN is PRM/KA/RERA/1251/446/PR/191107/002995.

What is the current construction status of AMBIENCE DOWNTOWN?

As of Q1 2026-27, AMBIENCE DOWNTOWN is 47% complete according to its latest K-RERA quarterly filing.

Are flats still available in AMBIENCE DOWNTOWN?

Yes. As per the latest K-RERA quarterly filing (Q1 2026-27), AMBIENCE DOWNTOWN has 47 unit(s) available for purchase.

Are 3 BHK flats available in AMBIENCE DOWNTOWN?

Yes. According to the latest K-RERA quarterly filing, there are 72 3 BHK unit(s) available in AMBIENCE DOWNTOWN, Bengaluru Urban.

Are 4 BHK flats available in AMBIENCE DOWNTOWN?

Yes. According to the latest K-RERA quarterly filing, there are 20 4 BHK unit(s) available in AMBIENCE DOWNTOWN, Bengaluru Urban.

Are 5 BHK flats available in AMBIENCE DOWNTOWN?

Yes. According to the latest K-RERA quarterly filing, there are 2 5 BHK unit(s) available in AMBIENCE DOWNTOWN, Bengaluru Urban.

Are there any RERA complaints against AMBIENCE DOWNTOWN?

As per K-RERA data tracked by rera.watch, there are no complaints currently recorded against AMBIENCE DOWNTOWN.

When did AMBIENCE DOWNTOWN last file a quarterly update with K-RERA?

AMBIENCE DOWNTOWN last filed a quarterly update for Q1 2026-27 on 2026-07-15. The project has submitted 3 quarterly report(s) on K-RERA to date.