Projects / Nitesh Napa Valley
+ Compare with another project

Nitesh Napa Valley

On track · 99% built
Filed — · Q3 2025-26
Construction
99%
complete
Sold
130
of ? total units
Available
4
units
3 BHK: 0
4 BHK: 15
Other: 5
Complaints
0
on project
Construction progress
% complete per quarter
Sales velocity
Units sold per quarter · cumulative booked (line)
Inventory drain
Available units over time
Show financial data (advance collected vs withdrawn)
Quarterly financials
₹ Crore — advance collected vs amount withdrawn this quarter

Quarter-wise Tower Data

Filed: 2026-01-16 · Project 99% complete
Block A ( G+2 Floor ) A Type Villas 100% complete
Unit type Total Booked Available
4 BHK 25 23 2
4 BHK 25 23 2
4 BHK 25 23 2
4 BHK 25 23 2
4 BHK 25 23 2
Parking 50 46 4
Floor completion
Floor 0
100.0%
Floor 0
100.0%
Floor 0
100.0%
Floor 0
100.0%
Block B ( G+2 Floor ) B Type Villas 100% complete
Unit type Total Booked Available
4 BHK 86 85 1
4 BHK 86 85 1
4 BHK 86 85 1
4 BHK 86 85 1
4 BHK 86 85 1
Parking 172 170 2
Floor completion
Floor 0
100.0%
Floor 0
100.0%
Floor 0
100.0%
Floor 0
100.0%
Block C ( G+2 Floor ) C Type Villas 100% complete
Unit type Total Booked Available
3 BHK 22 22 0
3 BHK 22 22 0
3 BHK 22 22 0
3 BHK 22 22 0
3 BHK 22 22 0
Parking 44 44
Floor completion
Floor 0
100.0%
Floor 0
100.0%
Floor 0
100.0%
Floor 0
100.0%
Club House 100% complete
Unit type Total Booked Available
Other 1 1
Other 1 1
Other 1 1
Other 1 1
Other 1 1
Parking 131 131
Floor completion
Floor 0
100.0%
Floor 0
100.0%
Floor 0
100.0%
Floor 0
100.0%

Unit Specifications

Unit type Carpet area (sqft) Units
3 BHK 2,203 22 Estimate ROI →
4 BHK 3,311 86 Estimate ROI →
4 BHK 4,365 25 Estimate ROI →
Other 27,756 1 Estimate ROI →
Show escrow account details
Escrow Accounts
Bank
Axis Bank
Branch
Hegde Nagar, Bangalore
IFSC
UTIB0002980
70% Collection A/C
920020069371500

Registration Extension Extension granted

Promoter's stated reason for delay: others

Event Start date Proposed completion
At the time of Registration 2013-03-07 2021-03-31 Certificate →
Covid Extension 2021-03-31 2021-09-30 Certificate →
Section 6 Extension 2021-12-30 2022-12-29 Certificate →
Further Extension 2022-12-29 2025-12-31 Certificate →
Extension applied on
2021-11-30
Extension approved on
2022-02-25
Extension registration no.
EX/PRM/KA/RERA/1251/309/PR/220225/002104

Project details

District
Bengaluru Urban
Taluk
Yelahanka
Total cost
Project start
2013-03-07
FAR sanctioned
0.672
Land area
876,642 sqft
Proposed completion
2022-12-29 overdue
Project address
NITTE Meenakshi College Road Off Bellary Road near Ryan International School, Vadeyarapura Village Yelahanka
Show documents on file with K-RERA (119)
Documents on file
Government NOCs
BESCOM (electricity) on file
BWSSB (water & sewerage) on file
Fire NOC not found
KSPCB (pollution control) on file
SEIAA (environmental clearance) on file
Airport / Air Force NOC not found
Telecom (BSNL) NOC on file
Lift license not found
RERA statutory forms
Form-1 (project registration) not found
Form-2/3 (CA certificate) not found
Form-B / Sec 3(1) affidavit on file
Company KYC
Certificate of incorporation not found
GST certificate not found
PAN card on file
Partnership deed / firm registration not found
Legal / land documents
37 on file
Other documents
29 on file · 28 marked not available
Plan approvals
4 on file
Sale/allotment documents
2 on file
Site photographs
2 on file
Technical certificates
5 on file
Inventory of documents the promoter has uploaded to their K-RERA project page — not a review of their contents. "Not found" means no filed document matched that item by name; it doesn't necessarily apply to every project (e.g. an airport-proximity NOC).

Frequently Asked Questions

Based on K-RERA registered data for Nitesh Napa Valley
Is Nitesh Napa Valley RERA registered in Karnataka?

Yes. Nitesh Napa Valley is registered with the Karnataka Real Estate Regulatory Authority (K-RERA) under registration number .

What is the RERA registration number of Nitesh Napa Valley?

The K-RERA registration number of Nitesh Napa Valley is .

What is the current construction status of Nitesh Napa Valley?

As of Q3 2025-26, Nitesh Napa Valley is 99% complete according to its latest K-RERA quarterly filing.

Are flats still available in Nitesh Napa Valley?

Yes. As per the latest K-RERA quarterly filing (Q3 2025-26), Nitesh Napa Valley has 4 unit(s) available for purchase.

Are 4 BHK flats available in Nitesh Napa Valley?

Yes. According to the latest K-RERA quarterly filing, there are 15 4 BHK unit(s) available in Nitesh Napa Valley, Bengaluru Urban.

Are there any RERA complaints against Nitesh Napa Valley?

As per K-RERA data tracked by rera.watch, there are no complaints currently recorded against Nitesh Napa Valley.

When did Nitesh Napa Valley last file a quarterly update with K-RERA?

Nitesh Napa Valley last filed a quarterly update for Q3 2025-26 on 2026-01-16. The project has submitted 1 quarterly report(s) on K-RERA to date.