Phase 3 at Sy.Nos.115/3(p), 115/4(p), 115/5(p) and 116/3(p), in the composite project Sobha Windsor situated at, Sy.Nos. 107, 115/2, 115/3(p), 115/4(p), 115/5(p), 116/3(p) of Nagondanahalli Village and Sy.No.30/1 and 30/6 of Hagadur Village
Show documents on file with K-RERA (161)
Documents on file
Government NOCs
BESCOM (electricity)
on file
BWSSB (water & sewerage)
on file
Fire NOC
on file
KSPCB (pollution control)
on file
SEIAA (environmental clearance)
on file
Airport / Air Force NOC
not found
Telecom (BSNL) NOC
not found
Lift license
not found
RERA statutory forms
Form-1 (project registration)
not found
Form-2/3 (CA certificate)
not found
Form-B / Sec 3(1) affidavit
on file
Company KYC
Certificate of incorporation
not found
GST certificate
not found
PAN card
not found
Partnership deed / firm registration
not found
Promoter financials
18 on file
Legal / land documents
21 on file
· 4 marked not available
Other documents
72 on file
· 15 marked not available
Plan approvals
13 on file
· 2 marked not available
Sale/allotment documents
3 on file
Site photographs
2 on file
Technical certificates
1 on file
Inventory of documents the promoter has uploaded to their K-RERA project page — not a review of their contents.
"Not found" means no filed document matched that item by name; it doesn't necessarily apply to every project (e.g. an airport-proximity NOC).
Frequently Asked Questions
Based on K-RERA registered data for Sobha Arena - Pebble Court (Block 1)
Is Sobha Arena - Pebble Court (Block 1) RERA registered in Karnataka?
Yes. Sobha Arena - Pebble Court (Block 1) is registered with the Karnataka Real Estate Regulatory Authority (K-RERA) under registration number PRM/KA/RERA/1251/446/PR/210219/003937.
What is the RERA registration number of Sobha Arena - Pebble Court (Block 1)?
The K-RERA registration number of Sobha Arena - Pebble Court (Block 1) is PRM/KA/RERA/1251/446/PR/210219/003937.
What is the current construction status of Sobha Arena - Pebble Court (Block 1)?
As of Q4 2025-26, Sobha Arena - Pebble Court (Block 1) is 100% complete — construction has finished according to its latest K-RERA quarterly filing.
Are flats still available in Sobha Arena - Pebble Court (Block 1)?
As per the latest K-RERA filing (Q4 2025-26), Sobha Arena - Pebble Court (Block 1) is sold out — no units are currently listed as available.
Are there any RERA complaints against Sobha Arena - Pebble Court (Block 1)?
As per K-RERA data tracked by rera.watch, there are no complaints currently recorded against Sobha Arena - Pebble Court (Block 1).
When did Sobha Arena - Pebble Court (Block 1) last file a quarterly update with K-RERA?
Sobha Arena - Pebble Court (Block 1) last filed a quarterly update for Q4 2025-26 on 2026-04-10. The project has submitted 2 quarterly report(s) on K-RERA to date.