SRIKARA URBAN PARK

Bengaluru Urban PRM/KA/RERA/1251/308/PR/210331/004075
On track · 91% built
Filed — · Q1 2026-27
Construction
91%
complete
Sold
49
of ? total units
Available
77
units
2 BHK: 61
2.5 BHK: 9
3 BHK: 7
Complaints
0
on project
Construction progress
% complete per quarter
Sales velocity
Units sold per quarter · cumulative booked (line)
Inventory drain
Available units over time
Show financial data (advance collected vs withdrawn)
Quarterly financials
₹ Crore — advance collected vs amount withdrawn this quarter

Quarter-wise Tower Data

Filed: 2026-07-10 · Project 91% complete
A 91% complete
Unit type Total Booked Available
2 BHK 47 20 27
3 BHK 9 4 5
Parking 56 24 32
Floor completion
Floor 0
91.0%
Floor 1
92.0%
Floor 2
92.0%
Floor 3
92.0%
Floor 4
92.0%
B 91% complete
Unit type Total Booked Available
2 BHK 50 16 34
2.5 BHK 15 6 9
3 BHK 5 3 2
Parking 70 25 45
Floor completion
Floor 0
91.0%
Floor 1
91.0%
Floor 2
91.0%
Floor 3
91.0%
Floor 4
91.0%

Unit Specifications

Unit type Carpet area (sqft) Units
2 BHK 769–800 97 Estimate ROI →
2.5 BHK 925–932 15 Estimate ROI →
3 BHK 990–1,041 14 Estimate ROI →
Show escrow account details
Escrow Accounts
Bank
Indian Bank
Branch
Electronic City , Bengaluru
IFSC
IDIB000E024
70% Collection A/C
6978552399

Project details

Registration no.
PRM/KA/RERA/1251/308/PR/210331/004075
District
Bengaluru Urban
Taluk
Anekal
Total cost
Project start
2021-03-01
FAR sanctioned
2.25
Land area
60,160 sqft
Proposed completion
2027-03-31
Project address
Sy. No. 67/1, 67/2, 68/3 of Maragondanahalli Village, Jigani Hobli, Anekal Taluk, Bengaluru

Frequently Asked Questions

Based on K-RERA registered data for SRIKARA URBAN PARK
Is SRIKARA URBAN PARK RERA registered in Karnataka?

Yes. SRIKARA URBAN PARK is registered with the Karnataka Real Estate Regulatory Authority (K-RERA) under registration number PRM/KA/RERA/1251/308/PR/210331/004075.

What is the RERA registration number of SRIKARA URBAN PARK?

The K-RERA registration number of SRIKARA URBAN PARK is PRM/KA/RERA/1251/308/PR/210331/004075.

What is the current construction status of SRIKARA URBAN PARK?

As of Q1 2026-27, SRIKARA URBAN PARK is 91% complete according to its latest K-RERA quarterly filing.

Are flats still available in SRIKARA URBAN PARK?

Yes. As per the latest K-RERA quarterly filing (Q1 2026-27), SRIKARA URBAN PARK has 77 unit(s) available for purchase.

Are 2 BHK flats available in SRIKARA URBAN PARK?

Yes. According to the latest K-RERA quarterly filing, there are 61 2 BHK unit(s) available in SRIKARA URBAN PARK, Bengaluru Urban.

Are 2.5 BHK flats available in SRIKARA URBAN PARK?

Yes. According to the latest K-RERA quarterly filing, there are 9 2.5 BHK unit(s) available in SRIKARA URBAN PARK, Bengaluru Urban.

Are 3 BHK flats available in SRIKARA URBAN PARK?

Yes. According to the latest K-RERA quarterly filing, there are 7 3 BHK unit(s) available in SRIKARA URBAN PARK, Bengaluru Urban.

Are there any RERA complaints against SRIKARA URBAN PARK?

As per K-RERA data tracked by rera.watch, there are no complaints currently recorded against SRIKARA URBAN PARK.

When did SRIKARA URBAN PARK last file a quarterly update with K-RERA?

SRIKARA URBAN PARK last filed a quarterly update for Q1 2026-27 on 2026-07-10. The project has submitted 3 quarterly report(s) on K-RERA to date.