Projects / Assetz 22 & Crest
+ Compare with another project

Assetz 22 & Crest

Bengaluru Urban · BHAIRAV HOLDINGS INC TOR/PRM/KA/RERA/1251/309/PR/220802/000219
4 complaints · 0% built
Filed — · Q2 2026-27
Fund safety: no flags
Construction
0%
complete
Sold
118
of ? total units
Available
79
units
2 BHK: 2
3 BHK: 77
Complaints
4
on project · 4 on builder
Construction progress
% complete per quarter
Sales velocity
Units sold per quarter · cumulative booked (line)
Inventory drain
Available units over time
Show financial data (advance collected vs withdrawn)
Quarterly financials
₹ Crore — advance collected vs amount withdrawn this quarter

Quarter-wise Tower Data

Filed: 2026-10-14 · Project 0% complete
TOWER A 100% complete
Unit type Total Booked Available
2 BHK 1 — 1
3 BHK 86 69 17
Parking 102 69 33
Floor completion
Floor 0
100.0%
Floor 1
100.0%
Floor 2
100.0%
Floor 3
100.0%
Floor 4
100.0%
Floor 5
100.0%
Floor 6
100.0%
Floor 7
100.0%
Floor 8
100.0%
Floor 9
100.0%
Floor 10
100.0%
Floor 11
100.0%
Floor 12
100.0%
Floor 13
100.0%
Floor 14
100.0%
Floor 15
100.0%
Floor 16
100.0%
Floor 17
100.0%
Floor 18
100.0%
Floor 19
100.0%
Floor 20
100.0%
Floor 21
100.0%
Floor 22
100.0%
TOWER B 100% complete
Unit type Total Booked Available
2 BHK 1 — 1
3 BHK 109 49 60
Parking 130 49 81
Floor completion
Floor 0
100.0%
Floor 1
100.0%
Floor 2
100.0%
Floor 3
100.0%
Floor 4
100.0%
Floor 5
100.0%
Floor 6
100.0%
Floor 7
100.0%
Floor 8
100.0%
Floor 9
100.0%
Floor 10
100.0%
Floor 11
100.0%
Floor 12
100.0%
Floor 13
100.0%
Floor 14
100.0%
Floor 15
100.0%
Floor 16
100.0%
Floor 17
100.0%
Floor 18
100.0%
Floor 19
100.0%
Floor 20
100.0%
Floor 21
100.0%
Floor 22
100.0%

Unit Specifications

Unit type Carpet area (sqft) Units
2 BHK 925 1 Estimate ROI →
2 BHK 965 1 Estimate ROI →
3 BHK 1,035–1,262 86 Estimate ROI →
3 BHK 952–1,193 109 Estimate ROI →
Show escrow account details
Escrow Accounts
Bank
HDFC
Branch
JAIN HEIGHTS AND STRUCTURES PRIVATE LIMITED
IFSC
HDFC0000009
70% Collection A/C
57500000056606

Registration Extension Extension granted

Promoters can apply for a Section 6 extensionA formal application under RERA Section 6 for more time to complete the project, requiring a stated reason — distinct from the automatic, government-wide Covid extension every project received. when they can't meet the originally registered completion date.

Promoter's stated reason for delay: Applied for modification

Event Start date Proposed completion
At the time of Registration 2016-10-30 2022-03-30 Certificate →
Section 6 Extension 2022-03-30 2023-03-30 Certificate →
Further Extension 2023-03-30 2026-12-31 Certificate →
Extension applied on
2024-11-18
Extension approved on
2024-12-18
Extension registration no.
EX/PRM/KA/RERA/1251/309/PR/241218/000219

Project details

Registration no.
TOR/PRM/KA/RERA/1251/309/PR/220802/000219
District
Bengaluru Urban
Taluk
Bengaluru North
Promoter
BHAIRAV HOLDINGS INC
Firm type
Partnership Firm
PAN
AAKFB6935F
Project start
2016-10-30
FAR sanctioned
3.96
Land area
78,308 sqft
Proposed completion
2023-03-30 overdue
Project address
PID No.10-1-71, Yeshwanthapura, Industrial Sub Urb, , Ward No.10, Mahalakshmipuram, Bangalore

Buyer Risk Report 4 complaints

4 complaints on file from this project's K-RERA quarterly filings.

Sign in free — no password — to see exactly which quarters and complaints triggered these flags.

Sign in to see full details →
Show documents on file with K-RERA (128)
Documents on file
Government NOCs
BESCOM (electricity) on file
BWSSB (water & sewerage) on file
Fire NOC on file
KSPCB (pollution control) on file
SEIAA (environmental clearance) not found
Airport / Air Force NOC not found
Telecom (BSNL) NOC on file
Lift license not found
RERA statutory forms
Form-1 (project registration) not found
Form-2/3 (CA certificate) not found
Form-B / Sec 3(1) affidavit on file
Company KYC
Certificate of incorporation not found
GST certificate not found
PAN card on file
Partnership deed / firm registration on file
Promoter financials
3 on file
Legal / land documents
9 on file
Other documents
34 on file · 31 marked not available
Plan approvals
9 on file · 1 marked not available
Sale/allotment documents
4 on file
Site photographs
2 on file
Technical certificates
2 on file
Inventory of documents the promoter has uploaded to their K-RERA project page — not a review of their contents. "Not found" means no filed document matched that item by name; it doesn't necessarily apply to every project (e.g. an airport-proximity NOC).

Frequently Asked Questions

Based on K-RERA registered data for Assetz 22 & Crest
Is Assetz 22 & Crest RERA registered in Karnataka?

Yes. Assetz 22 & Crest is registered with the Karnataka Real Estate Regulatory Authority (K-RERA) under registration number TOR/PRM/KA/RERA/1251/309/PR/220802/000219.

What is the RERA registration number of Assetz 22 & Crest?

The K-RERA registration number of Assetz 22 & Crest is TOR/PRM/KA/RERA/1251/309/PR/220802/000219.

What is the current construction status of Assetz 22 & Crest?

As of Q2 2026-27, Assetz 22 & Crest is 0% complete according to its latest K-RERA quarterly filing.

Are flats still available in Assetz 22 & Crest?

Yes. As per the latest K-RERA quarterly filing (Q2 2026-27), Assetz 22 & Crest has 79 unit(s) available for purchase.

Are 2 BHK flats available in Assetz 22 & Crest?

Yes. According to the latest K-RERA quarterly filing, there are 2 2 BHK unit(s) available in Assetz 22 & Crest, Bengaluru Urban.

Are 3 BHK flats available in Assetz 22 & Crest?

Yes. According to the latest K-RERA quarterly filing, there are 77 3 BHK unit(s) available in Assetz 22 & Crest, Bengaluru Urban.

Are there any RERA complaints against Assetz 22 & Crest?

Yes. Assetz 22 & Crest has 4 complaint(s) filed against it on the K-RERA portal. Review these on the official K-RERA website before making a purchase decision.

How many RERA complaints does BHAIRAV HOLDINGS INC have?

BHAIRAV HOLDINGS INC, the builder/promoter of Assetz 22 & Crest, has 4 complaint(s) filed against them across all their K-RERA registered projects in Karnataka.

Who is the builder or developer of Assetz 22 & Crest?

Assetz 22 & Crest is developed by BHAIRAV HOLDINGS INC, a partnership firm registered with K-RERA in Bengaluru Urban, Karnataka.

When did Assetz 22 & Crest last file a quarterly update with K-RERA?

Assetz 22 & Crest last filed a quarterly update for Q2 2026-27 on 2026-10-14. The project has submitted 4 quarterly report(s) on K-RERA to date.