ADARSH CREST PHASE 1
Show financial data (advance collected vs withdrawn)
Quarter-wise Tower Data
BLock 2 97% complete
| Unit type | Total | Booked | Available |
|---|---|---|---|
| 2 BHK | 14 | 14 | 0 |
| 2 BHK | 14 | 14 | 0 |
| 3 BHK | 34 | 34 | 0 |
| 3 BHK | 26 | 26 | 0 |
| 3 BHK | 34 | 34 | 0 |
| 3 BHK | 26 | 26 | 0 |
| Parking | 74 | 74 | — |
Block 1 78% complete
| Unit type | Total | Booked | Available |
|---|---|---|---|
| 3 BHK | 48 | 48 | 0 |
| 3 BHK | 48 | 48 | 0 |
| Parking | 48 | 48 | — |
Unit Specifications
| Unit type | Carpet area (sqft) | Units | |
|---|---|---|---|
| 2 BHK | 854–931 | 14 | Estimate ROI → |
| 3 BHK | 1,222–1,354 | 82 | Estimate ROI → |
| 3 BHK | 1,299–1,417 | 26 | Estimate ROI → |
Show escrow account details
Project details
Buyer Risk Report
1 risk signal detected from this project's K-RERA quarterly filings.
Sign in free — no password — to see exactly which quarters and complaints triggered these flags.
Sign in to see full details →A few details and our team will reach out — no referral fee, just a connection.
✓ We're on it — our team will reach out to you shortly.
Show documents on file with K-RERA (111)
| BESCOM (electricity) | on file |
| BWSSB (water & sewerage) | on file |
| Fire NOC | on file |
| KSPCB (pollution control) | on file |
| SEIAA (environmental clearance) | on file |
| Airport / Air Force NOC | not found |
| Telecom (BSNL) NOC | on file |
| Lift license | not found |
| Form-1 (project registration) | not found |
| Form-2/3 (CA certificate) | not found |
| Form-B / Sec 3(1) affidavit | on file |
| Certificate of incorporation | not found |
| GST certificate | not found |
| PAN card | not found |
| Partnership deed / firm registration | on file |
Frequently Asked Questions
Is ADARSH CREST PHASE 1 RERA registered in Karnataka?
Yes. ADARSH CREST PHASE 1 is registered with the Karnataka Real Estate Regulatory Authority (K-RERA) under registration number PRM/KA/RERA/1251/446/PR/211022/004369.
What is the RERA registration number of ADARSH CREST PHASE 1?
The K-RERA registration number of ADARSH CREST PHASE 1 is PRM/KA/RERA/1251/446/PR/211022/004369.
What is the current construction status of ADARSH CREST PHASE 1?
As of Q1 2026-27, ADARSH CREST PHASE 1 is 74% complete according to its latest K-RERA quarterly filing.
Are flats still available in ADARSH CREST PHASE 1?
As per the latest K-RERA filing (Q1 2026-27), ADARSH CREST PHASE 1 is sold out — no units are currently listed as available.
Are there any RERA complaints against ADARSH CREST PHASE 1?
As per K-RERA data tracked by rera.watch, there are no complaints currently recorded against ADARSH CREST PHASE 1.
When did ADARSH CREST PHASE 1 last file a quarterly update with K-RERA?
ADARSH CREST PHASE 1 last filed a quarterly update for Q1 2026-27 on 2026-07-15. The project has submitted 3 quarterly report(s) on K-RERA to date.