Compare / SANKALP CROWN PHASE 2 vs SANKALP CENTRAL PHASE 3A

SANKALP CROWN PHASE 2 vs SANKALP CENTRAL PHASE 3A

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
On track · 74% built
SANKALP CONSTRUCTIONS PRIVATE LIMITED PRM/KA/RERA/1268/378/PR/180823/006182
On track · 35% built
SANKALP CONSTRUCTIONS PRIVATE LIMITED PRM/KA/RERA/1268/378/PR/180424/006798
SANKALP CROWN PHASE 2
Construction
74%
as of Q1 2026-27
Sold
132
of 208 · +4 last qtr
Available
76
SANKALP CENTRAL PHASE 3A
Construction
35%
as of Q1 2026-27
Sold
62
of 142 · +9 last qtr
Available
80
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
SANKALP CROWN PHASE 2
Complaints
0
on this project
SANKALP CENTRAL PHASE 3A
Complaints
0
on this project
Builder track record
Across each promoter's other K-RERA registered projects
SANKALP CROWN PHASE 2
SANKALP CONSTRUCTIONS PRIVATE LIMITED
6 other projects on K-RERA · 0 delivered (100% complete) · avg 29.0% complete
SANKALP CENTRAL PHASE 3A
SANKALP CONSTRUCTIONS PRIVATE LIMITED
6 other projects on K-RERA · 0 delivered (100% complete) · avg 36.8% complete
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
SANKALP CROWN PHASE 2
No risk signals from filed quarters.
SANKALP CENTRAL PHASE 3A
No risk signals from filed quarters.
SANKALP CROWN PHASE 2 — escrow account details
Bank
STATE BANK OF INDIA
Branch
V M Double Road, Kuvempunagar, Mysore
IFSC
SBIN0040441
70% Collection A/C
42824173066
SANKALP CENTRAL PHASE 3A — escrow account details
Bank
STATE BANK OF INDIA
Branch
V M Double Road, Kuvempunagar, Mysore
IFSC
SBIN0040441
70% Collection A/C
42286407846
100% A/C
42785433686
30% A/C
64018506748
SANKALP CROWN PHASE 2 — details
Total units
208
Total cost
₹108.54 Cr
Project start
2023-09-15
Proposed completion
2029-03-31
Address
No 677 N3 Vasanth Mahal Road, Nazarbad Mohalla, Mysore
SANKALP CENTRAL PHASE 3A — details
Total units
142
Total cost
₹116.07 Cr
Project start
2024-07-01
Proposed completion
2030-06-30
Address
418, Contoor Road, Gokulam 3rd Stage, Mysore