Projects / SANKALP CENTRAL PHASE 3A
+ Compare with another project

SANKALP CENTRAL PHASE 3A

Mysore · SANKALP CONSTRUCTIONS PRIVATE LIMITED PRM/KA/RERA/1268/378/PR/180424/006798
On track · 35% built
Filed — · Q1 2026-27
Fund safety: no flags
Construction
35%
complete
Sold
62
of 142 total units
Available
80
units
2 BHK: 80
3 BHK: 80
Complaints
0
on project
Construction progress
% complete per quarter
Sales velocity
Units sold per quarter · cumulative booked (line)
Inventory drain
Available units over time
Show financial data (advance collected vs withdrawn)
Quarterly financials
₹ Crore — advance collected vs amount withdrawn this quarter

Quarter-wise Tower Data

Filed: 2026-07-14 · Project 35% complete
WING - J 25% complete
Unit type Total Booked Available
2 BHK 31 14 17
2 BHK 31 14 17
3 BHK 16 7 9
3 BHK 16 7 9
Parking 47 21 26
Floor completion
Floor 0
15.0%
Floor 0
15.0%
Floor 1
0.0%
Floor 1
0.0%
Floor 2
0.0%
Floor 2
0.0%
Floor 3
0.0%
Floor 3
0.0%
Floor 4
0.0%
Floor 4
0.0%
Floor 5
0.0%
Floor 5
0.0%
Floor 6
0.0%
Floor 6
0.0%
Floor 7
0.0%
Floor 7
0.0%
WING - K 40% complete
Unit type Total Booked Available
3 BHK 32 16 16
3 BHK 32 16 16
Parking 32 16 16
Floor completion
Floor 0
40.0%
Floor 0
40.0%
Floor 1
30.0%
Floor 1
30.0%
Floor 2
30.0%
Floor 2
30.0%
Floor 3
30.0%
Floor 3
30.0%
Floor 4
30.0%
Floor 4
30.0%
Floor 5
30.0%
Floor 5
30.0%
Floor 6
30.0%
Floor 6
30.0%
Floor 7
20.0%
Floor 7
20.0%
WING - L 27% complete
Unit type Total Booked Available
2 BHK 31 8 23
2 BHK 31 8 23
3 BHK 16 8 8
3 BHK 16 8 8
Parking 47 16 31
Floor completion
Floor 0
40.0%
Floor 0
40.0%
Floor 1
0.0%
Floor 1
0.0%
Floor 2
0.0%
Floor 2
0.0%
Floor 3
0.0%
Floor 3
0.0%
Floor 4
0.0%
Floor 4
0.0%
Floor 5
0.0%
Floor 5
0.0%
Floor 6
0.0%
Floor 6
0.0%
Floor 7
0.0%
Floor 7
0.0%
WING - M 25% complete
Unit type Total Booked Available
3 BHK 16 9 7
3 BHK 16 9 7
Parking 16 9 7
Floor completion
Floor 0
25.0%
Floor 0
25.0%
Floor 1
0.0%
Floor 1
0.0%
Floor 2
0.0%
Floor 2
0.0%
Floor 3
0.0%
Floor 3
0.0%
Floor 4
0.0%
Floor 4
0.0%
Floor 5
0.0%
Floor 5
0.0%
Floor 6
0.0%
Floor 6
0.0%
Floor 7
0.0%
Floor 7
0.0%

Unit Specifications

Unit type Carpet area (sqft) Units
2 BHK 889 124 Estimate ROI →
3 BHK 1,151–1,314 160 Estimate ROI →
Show escrow account details
Escrow Accounts
Bank
STATE BANK OF INDIA
Branch
V M Double Road, Kuvempunagar, Mysore
IFSC
SBIN0040441
70% Collection A/C
42286407846
100% A/C
42785433686
30% A/C
64018506748

Project details

Registration no.
PRM/KA/RERA/1268/378/PR/180424/006798
District
Mysore
Taluk
Yelahanka
Promoter
SANKALP CONSTRUCTIONS PRIVATE LIMITED
Firm type
Company
PAN
AACCS5166N
GSTIN
29AACCS5166N1ZQ
Total units
142
Project start
2024-07-01
FAR sanctioned
2.17
Total cost
₹116.07 Cr
Land/property litigation
No
Proposed completion
2030-06-30
Project address
418, Contoor Road, Gokulam 3rd Stage, Mysore
Show documents on file with K-RERA (136)
Documents on file
Government NOCs
BESCOM (electricity) not found
BWSSB (water & sewerage) not found
Fire NOC on file
KSPCB (pollution control) on file
SEIAA (environmental clearance) not found
Airport / Air Force NOC on file
Telecom (BSNL) NOC not found
Lift license not found
RERA statutory forms
Form-1 (project registration) not found
Form-2/3 (CA certificate) not found
Form-B / Sec 3(1) affidavit on file
Company KYC
Certificate of incorporation not found
GST certificate not found
PAN card not found
Partnership deed / firm registration not found
Promoter financials
20 on file
Legal / land documents
11 on file
Other documents
46 on file · 19 marked not available
Plan approvals
20 on file
Sale/allotment documents
4 on file
Site photographs
4 on file
Technical certificates
2 on file
Inventory of documents the promoter has uploaded to their K-RERA project page — not a review of their contents. "Not found" means no filed document matched that item by name; it doesn't necessarily apply to every project (e.g. an airport-proximity NOC).

Frequently Asked Questions

Based on K-RERA registered data for SANKALP CENTRAL PHASE 3A
Is SANKALP CENTRAL PHASE 3A RERA registered in Karnataka?

Yes. SANKALP CENTRAL PHASE 3A is registered with the Karnataka Real Estate Regulatory Authority (K-RERA) under registration number PRM/KA/RERA/1268/378/PR/180424/006798.

What is the RERA registration number of SANKALP CENTRAL PHASE 3A?

The K-RERA registration number of SANKALP CENTRAL PHASE 3A is PRM/KA/RERA/1268/378/PR/180424/006798.

What is the current construction status of SANKALP CENTRAL PHASE 3A?

As of Q1 2026-27, SANKALP CENTRAL PHASE 3A is 35% complete according to its latest K-RERA quarterly filing.

Are flats still available in SANKALP CENTRAL PHASE 3A?

Yes. As per the latest K-RERA quarterly filing (Q1 2026-27), SANKALP CENTRAL PHASE 3A has 80 unit(s) available for purchase.

How many flats have been sold in SANKALP CENTRAL PHASE 3A?

As per the latest K-RERA filing (Q1 2026-27), 62 out of 142 units in SANKALP CENTRAL PHASE 3A have been sold or booked.

Are 2 BHK flats available in SANKALP CENTRAL PHASE 3A?

Yes. According to the latest K-RERA quarterly filing, there are 80 2 BHK unit(s) available in SANKALP CENTRAL PHASE 3A, Mysore.

Are 3 BHK flats available in SANKALP CENTRAL PHASE 3A?

Yes. According to the latest K-RERA quarterly filing, there are 80 3 BHK unit(s) available in SANKALP CENTRAL PHASE 3A, Mysore.

Are there any RERA complaints against SANKALP CENTRAL PHASE 3A?

As per K-RERA data tracked by rera.watch, there are no complaints currently recorded against SANKALP CENTRAL PHASE 3A.

How many RERA complaints does SANKALP CONSTRUCTIONS PRIVATE LIMITED have?

SANKALP CONSTRUCTIONS PRIVATE LIMITED, the builder/promoter of SANKALP CENTRAL PHASE 3A, has 0 complaint(s) filed against them across all their K-RERA registered projects in Karnataka.

Who is the builder or developer of SANKALP CENTRAL PHASE 3A?

SANKALP CENTRAL PHASE 3A is developed by SANKALP CONSTRUCTIONS PRIVATE LIMITED, a company registered with K-RERA in Mysore, Karnataka.

When did SANKALP CENTRAL PHASE 3A last file a quarterly update with K-RERA?

SANKALP CENTRAL PHASE 3A last filed a quarterly update for Q1 2026-27 on 2026-07-14. The project has submitted 3 quarterly report(s) on K-RERA to date.