SANKALP CENTRAL PHASE 3A
Show financial data (advance collected vs withdrawn)
Quarter-wise Tower Data
WING - J 25% complete
| Unit type | Total | Booked | Available |
|---|---|---|---|
| 2 BHK | 31 | 14 | 17 |
| 2 BHK | 31 | 14 | 17 |
| 3 BHK | 16 | 7 | 9 |
| 3 BHK | 16 | 7 | 9 |
| Parking | 47 | 21 | 26 |
WING - K 40% complete
| Unit type | Total | Booked | Available |
|---|---|---|---|
| 3 BHK | 32 | 16 | 16 |
| 3 BHK | 32 | 16 | 16 |
| Parking | 32 | 16 | 16 |
WING - L 27% complete
| Unit type | Total | Booked | Available |
|---|---|---|---|
| 2 BHK | 31 | 8 | 23 |
| 2 BHK | 31 | 8 | 23 |
| 3 BHK | 16 | 8 | 8 |
| 3 BHK | 16 | 8 | 8 |
| Parking | 47 | 16 | 31 |
WING - M 25% complete
| Unit type | Total | Booked | Available |
|---|---|---|---|
| 3 BHK | 16 | 9 | 7 |
| 3 BHK | 16 | 9 | 7 |
| Parking | 16 | 9 | 7 |
Unit Specifications
| Unit type | Carpet area (sqft) | Units | |
|---|---|---|---|
| 2 BHK | 889 | 124 | Estimate ROI → |
| 3 BHK | 1,151–1,314 | 160 | Estimate ROI → |
Show escrow account details
Project details
Show documents on file with K-RERA (136)
| BESCOM (electricity) | not found |
| BWSSB (water & sewerage) | not found |
| Fire NOC | on file |
| KSPCB (pollution control) | on file |
| SEIAA (environmental clearance) | not found |
| Airport / Air Force NOC | on file |
| Telecom (BSNL) NOC | not found |
| Lift license | not found |
| Form-1 (project registration) | not found |
| Form-2/3 (CA certificate) | not found |
| Form-B / Sec 3(1) affidavit | on file |
| Certificate of incorporation | not found |
| GST certificate | not found |
| PAN card | not found |
| Partnership deed / firm registration | not found |
Frequently Asked Questions
Is SANKALP CENTRAL PHASE 3A RERA registered in Karnataka?
Yes. SANKALP CENTRAL PHASE 3A is registered with the Karnataka Real Estate Regulatory Authority (K-RERA) under registration number PRM/KA/RERA/1268/378/PR/180424/006798.
What is the RERA registration number of SANKALP CENTRAL PHASE 3A?
The K-RERA registration number of SANKALP CENTRAL PHASE 3A is PRM/KA/RERA/1268/378/PR/180424/006798.
What is the current construction status of SANKALP CENTRAL PHASE 3A?
As of Q1 2026-27, SANKALP CENTRAL PHASE 3A is 35% complete according to its latest K-RERA quarterly filing.
Are flats still available in SANKALP CENTRAL PHASE 3A?
Yes. As per the latest K-RERA quarterly filing (Q1 2026-27), SANKALP CENTRAL PHASE 3A has 80 unit(s) available for purchase.
How many flats have been sold in SANKALP CENTRAL PHASE 3A?
As per the latest K-RERA filing (Q1 2026-27), 62 out of 142 units in SANKALP CENTRAL PHASE 3A have been sold or booked.
Are 2 BHK flats available in SANKALP CENTRAL PHASE 3A?
Yes. According to the latest K-RERA quarterly filing, there are 80 2 BHK unit(s) available in SANKALP CENTRAL PHASE 3A, Mysore.
Are 3 BHK flats available in SANKALP CENTRAL PHASE 3A?
Yes. According to the latest K-RERA quarterly filing, there are 80 3 BHK unit(s) available in SANKALP CENTRAL PHASE 3A, Mysore.
Are there any RERA complaints against SANKALP CENTRAL PHASE 3A?
As per K-RERA data tracked by rera.watch, there are no complaints currently recorded against SANKALP CENTRAL PHASE 3A.
How many RERA complaints does SANKALP CONSTRUCTIONS PRIVATE LIMITED have?
SANKALP CONSTRUCTIONS PRIVATE LIMITED, the builder/promoter of SANKALP CENTRAL PHASE 3A, has 0 complaint(s) filed against them across all their K-RERA registered projects in Karnataka.
Who is the builder or developer of SANKALP CENTRAL PHASE 3A?
SANKALP CENTRAL PHASE 3A is developed by SANKALP CONSTRUCTIONS PRIVATE LIMITED, a company registered with K-RERA in Mysore, Karnataka.
When did SANKALP CENTRAL PHASE 3A last file a quarterly update with K-RERA?
SANKALP CENTRAL PHASE 3A last filed a quarterly update for Q1 2026-27 on 2026-07-14. The project has submitted 3 quarterly report(s) on K-RERA to date.