SAIRAM'S SUBRAMANYA NAGAR
Mysore · Bengaluru North
Active
SAIRAM DWELLINGS PRIVATE LIMITED PRM/KA/RERA/1268/378/PR/060924/007007
On track · 55% built
ARATT CITY TOWERS LLP PRM/KA/RERA/1251/309/PR/290626/008767
SAIRAM'S SUBRAMANYA NAGAR
No quarterly filings found for SAIRAM'S SUBRAMANYA NAGAR yet — construction progress and sales data aren't available on K-RERA.
Aratt-Escapes Phase 2
Construction
55%
as of Q1 2026-27
Sold
—
of ? · +0 last qtr
Available
0
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
SAIRAM'S SUBRAMANYA NAGAR
Complaints
0
on this project · 1 on SAIRAM DWELLINGS PRIVATE LIMITED overall
Aratt-Escapes Phase 2
Complaints
0
on this project · 1 on ARATT CITY TOWERS LLP overall
Builder track record
Across each promoter's other K-RERA registered projects
SAIRAM'S SUBRAMANYA NAGAR
SAIRAM DWELLINGS PRIVATE LIMITED
No other K-RERA registered projects on file for this promoter.
Aratt-Escapes Phase 2
ARATT CITY TOWERS LLP
2 other projects on K-RERA · 0 delivered (100% complete) · avg 84.5% complete · 1 complaint across those projects
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
SAIRAM'S SUBRAMANYA NAGAR
No risk signals from filed quarters.
Aratt-Escapes Phase 2
No risk signals from filed quarters.
SAIRAM'S SUBRAMANYA NAGAR — escrow account details
Bank
ICICI Bank
Branch
Kengeri
IFSC
ICIC0002335
70% Collection A/C
777705585962
100% A/C
777705585961
30% A/C
777705585963
Aratt-Escapes Phase 2 — escrow account details
Bank
ICICI Bank
Branch
Ulsoor Road Branch
IFSC
ICIC0003049
70% Collection A/C
777705131902
100% A/C
777705131901
30% A/C
777705131903
SAIRAM'S SUBRAMANYA NAGAR — details
Total cost
₹6.19 Cr
Project start
2024-07-01
Proposed completion
2025-12-01 overdue
Address
SY NO 233/2A1 & 232/4, KERGALLI VILLAGE , JAYAPURA HOBLI , MYSORE , Mysore, Karnataka - 570026
Aratt-Escapes Phase 2 — details
Total cost
₹6.84 Cr
Project start
2026-04-20
Proposed completion
2028-04-20
Address
SY NO 67/3 AND 67/4, MARGONDANAHALLI VILLAGE JIGANI HOBLI ANEKALTALUK