Nambiar District 25 Phase 1 vs Elanza
Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
On track · 30% built
Nambiar EnsembleResidential Projects LLP
PRM/KA/RERA/1251/308/PR/100125/007377
Elanza
Bengaluru Urban · Anekal
On track · 2% built
Lodha Developers Limited
PRM/KA/RERA/1251/308/PR/191225/008353
Nambiar District 25 Phase 1
Construction
30%
as of Q2 2026-27
Sold
764
of 796
· +1 last qtr
Available
32
Elanza
Construction
2%
as of Q2 2026-27
Sold
331
of 698
· +34 last qtr
Available
367
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
Nambiar District 25 Phase 1
Complaints
0
on this project · 2 on Nambiar EnsembleResidential Projects LLP overall
Elanza
Complaints
0
on this project · 1 on Lodha Developers Limited overall
Builder track record
Across each promoter's other K-RERA registered projects
Nambiar District 25 Phase 1
Nambiar EnsembleResidential Projects LLP
2 other projects on K-RERA
· 0 delivered (100% complete)
· avg 4.0% complete
· 2 complaints across those projects
Elanza
Lodha Developers Limited
6 other projects on K-RERA
· 0 delivered (100% complete)
· avg 19.0% complete
· 1 complaint across those projects
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
Nambiar District 25 Phase 1
Delay risk
trending ~23 month(s) past declared completion
Escrow
1 quarter(s) withdrawn with no matching progress
Elanza
Escrow
2 quarter(s) withdrawn with no matching progress
Nambiar District 25 Phase 1 — escrow account details
Elanza — escrow account details
Nambiar District 25 Phase 1 — details
Elanza — details