Compare / PALLADIUM LIVE SPACES vs The Valley By Essem18 Phase 1

PALLADIUM LIVE SPACES vs The Valley By Essem18 Phase 1

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
On track · 35% built
PALLADIUM PROJECTS PRM/KA/RERA/1251/310/PR/100925/008078
On track · 45% built
Essem18 Developers Private Limited PRM/KA/RERA/1251/310/PR/281125/008284
PALLADIUM LIVE SPACES
Construction
35%
as of Q3 2025-26
Sold
—
of 24 · +0 last qtr
Available
24
The Valley By Essem18 Phase 1
Construction
45%
as of Q1 2026-27
Sold
—
of ? · +0 last qtr
Available
0
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
PALLADIUM LIVE SPACES
Complaints
0
on this project
The Valley By Essem18 Phase 1
Complaints
0
on this project
Builder track record
Across each promoter's other K-RERA registered projects
PALLADIUM LIVE SPACES
PALLADIUM PROJECTS
No other K-RERA registered projects on file for this promoter.
The Valley By Essem18 Phase 1
Essem18 Developers Private Limited
1 other project on K-RERA · 0 delivered (100% complete) · avg 11.0% complete
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
PALLADIUM LIVE SPACES
No risk signals from filed quarters.
The Valley By Essem18 Phase 1
Delay risk trending ~6 month(s) past declared completion
PALLADIUM LIVE SPACES — escrow account details
Bank
IDFC FIRST BANK
Branch
LANGLORD TOWN
IFSC
IDFB0080195
70% Collection A/C
10226866752
100% A/C
10226866796
30% A/C
10226866809
The Valley By Essem18 Phase 1 — escrow account details
Bank
KOTAK MAHINDRA BANK
Branch
GANDHI BAZAR, BASAVANAGUDI
IFSC
KKBK0000423
70% Collection A/C
2950449533
100% A/C
2950449526
30% A/C
43575857733
PALLADIUM LIVE SPACES — details
Total units
24
Total cost
₹11.46 Cr
Project start
2024-01-02
Proposed completion
2029-12-31
Address
SITE NO 4223/2196/901/219. (218,218,219,220,220,220) KOTHANUR GRAMATHANA, , WARD NO 195, UTTARAHALLI HOBLI , Bengaluru South , Bengaluru Urban, Karnataka - 560078
The Valley By Essem18 Phase 1 — details
Total cost
₹11.56 Cr
Project start
2025-10-01
Proposed completion
2026-12-31
Address
Survey No 9/1, Khata No 386/9/1, Patanagere Village, Kengeri Hobli, Ward no 198 Bengaluru