Compare / Sobha Sentosa Phase 4 Wing 1 and 2 vs SANKALP CENTRAL PHASE 3A

Sobha Sentosa Phase 4 Wing 1 and 2 vs SANKALP CENTRAL PHASE 3A

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
7 complaints · 100% built
SOBHA LIMITED PRM/KA/RERA/1251/446/PR/310322/004799
On track · 42% built
SANKALP CONSTRUCTIONS PRIVATE LIMITED PRM/KA/RERA/1268/378/PR/180424/006798
Sobha Sentosa Phase 4 Wing 1 and 2
Construction
100%
as of Q2 2026-27
Sold
142
of 142 · +1 last qtr
Available
0
SANKALP CENTRAL PHASE 3A
Construction
42%
as of Q2 2026-27
Sold
65
of 142 · +3 last qtr
Available
77
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
Sobha Sentosa Phase 4 Wing 1 and 2
Complaints
7
on this project · 225 on SOBHA LIMITED overall
SANKALP CENTRAL PHASE 3A
Complaints
0
on this project
Builder track record
Across each promoter's other K-RERA registered projects
Sobha Sentosa Phase 4 Wing 1 and 2
SOBHA LIMITED
37 other projects on K-RERA · 8 delivered (100% complete) · avg 55.2% complete · 52 complaints across those projects
SANKALP CENTRAL PHASE 3A
SANKALP CONSTRUCTIONS PRIVATE LIMITED
6 other projects on K-RERA · 0 delivered (100% complete) · avg 39.2% complete
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
Sobha Sentosa Phase 4 Wing 1 and 2
Promoter pattern 1 of 36 other projects show the same delay-risk pattern
SANKALP CENTRAL PHASE 3A
No risk signals from filed quarters.
Sobha Sentosa Phase 4 Wing 1 and 2 — escrow account details
Bank
RATNAKAR BANK
Branch
PRESTIGE TOWERS, ( 0156 ) GROUND FLOOR, G-13, G-14, G-15 AND G-17, PRESTIGE TOWERS, 99, 100 RESIDENCY ROAD, BANGALORE
IFSC
RATN0000156
70% Collection A/C
409002400472
100% A/C
409002400465
30% A/C
409002400489
SANKALP CENTRAL PHASE 3A — escrow account details
Bank
STATE BANK OF INDIA
Branch
V M Double Road, Kuvempunagar, Mysore
IFSC
SBIN0040441
70% Collection A/C
42286407846
100% A/C
42785433686
30% A/C
64018506748
Sobha Sentosa Phase 4 Wing 1 and 2 — details
Total units
142
Total cost
₹162.50 Cr
Project start
2023-01-01
Proposed completion
2027-12-31
Address
Balagere, Bangalore
SANKALP CENTRAL PHASE 3A — details
Total units
142
Total cost
₹116.07 Cr
Project start
2024-07-01
Proposed completion
2030-06-30
Address
No 677 N3 Vasanth Mahal Road, Nazarbad Mohalla, Mysore