Compare / Assetz Sora & Saki Phase 2 vs Winds of Change by CKPC

Assetz Sora & Saki Phase 2 vs Winds of Change by CKPC

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
On track · 26% built
NETRA SOFTWARE TECHNOLOGIES PRIVATE LIMITED PRM/KA/RERA/1251/309/PR/210524/006929
On track · 30% built
CKPC RESIDENCES PRIVATE LIMITED PRM/KA/RERA/1251/472/PR/210525/007765
Assetz Sora & Saki Phase 2
Construction
26%
as of Q1 2026-27
Sold
224
of 634 · +16 last qtr
Available
410
Winds of Change by CKPC
Construction
30%
as of Q1 2026-27
Sold
284
of 438 · +53 last qtr
Available
154
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
Assetz Sora & Saki Phase 2
Complaints
0
on this project
Winds of Change by CKPC
Complaints
0
on this project
Builder track record
Across each promoter's other K-RERA registered projects
Assetz Sora & Saki Phase 2
NETRA SOFTWARE TECHNOLOGIES PRIVATE LIMITED
1 other project on K-RERA · 0 delivered (100% complete) · avg 72.0% complete
Winds of Change by CKPC
CKPC RESIDENCES PRIVATE LIMITED
1 other project on K-RERA · 0 delivered (100% complete) · avg 5.0% complete
Assetz Sora & Saki Phase 2 — escrow account details
Bank
FEDERAL BANK OF INDIA
Branch
Koramangala
IFSC
FDRL0001437
70% Collection A/C
14370200018050
100% A/C
14370200018068
30% A/C
14370200018076
Winds of Change by CKPC — escrow account details
Bank
HDFC
Branch
RICHMOND ROAD
IFSC
HDFC0000523
70% Collection A/C
57500001716189
100% A/C
57500001716752
30% A/C
57500001715071
Assetz Sora & Saki Phase 2 — details
Total units
634
Total cost
₹307.95 Cr
Project start
2024-05-01
Proposed completion
2029-07-31
Address
PLOT Nos. R-9-D1, R-9-D2, R-9-D1-P & R-9-D2-P OF HITECH, DEFENCE & AEROSPACE PARK, (HARDWARE SECTOR) COMPRISED IN SURVEY Nos. 176, 177, 470, 471 , OF BAGALUR VILLAGE AND SURVEY NO. 176 & 82 OF HOOVINAYAKANAHALLI VILLAGE, JALA HOBLI,BENGALURU NORTH YELAHANKA TALUK, BENGALURU URBAN DIST. , Bengaluru North , Bengaluru Urban, Karnataka - 562110
Winds of Change by CKPC — details
Total units
438
Total cost
₹350.00 Cr
Project start
2025-07-01
Proposed completion
2029-03-30
Address
Sy Nos. 96/1, 96/2A1, 96/13, 98/2D, 98/5, 98/6, 98/7, 98/8, 98/9, 98/10, 98/11 & 99/2A1, 99/3 AT SINGANAYAKANAHALLI VILLAGE , YELAHANKA HOBLI , Yelahanka , Bengaluru Urban, Karnataka - 560064