Birla Ojasvi
Bengaluru Urban · Bengaluru North
On track · 26% built
Birla Estates Private Limited PRM/KA/RERA/1251/310/PR/040924/006989
Down by the Water
Bengaluru Urban · Bengaluru North
On track · 5% built
TOTAL ENVIRONMENT BUILDING SYSTEMS PVT LTD PRM/KA/RERA/1251/472/PR/090824/006967
Birla Ojasvi
Construction
26%
as of Q2 2026-27
Sold
583
of 615 · +23 last qtr
Available
32
Down by the Water
Construction
5%
as of Q2 2026-27
Sold
223
of 602 · +0 last qtr
Available
379
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
Birla Ojasvi
Complaints
0
on this project · 3 on Birla Estates Private Limited overall
Down by the Water
Complaints
0
on this project · 14 on TOTAL ENVIRONMENT BUILDING SYSTEMS PVT LTD overall
Builder track record
Across each promoter's other K-RERA registered projects
Birla Ojasvi
Birla Estates Private Limited
No other K-RERA registered projects on file for this promoter.
Down by the Water
TOTAL ENVIRONMENT BUILDING SYSTEMS PVT LTD
1 other project on K-RERA · 0 delivered (100% complete) · avg 3.0% complete
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
Birla Ojasvi
Delay risk trending ~4 month(s) past declared completion
Down by the Water
Escrow 3 quarter(s) withdrawn with no matching progress
Birla Ojasvi — escrow account details
Bank
ICICI Bank
Branch
MG Road
IFSC
ICIC0000002
70% Collection A/C
777705250035
100% A/C
777705250034
30% A/C
777705250036
Down by the Water — escrow account details
Bank
RATNAKAR BANK
Branch
Prestige Towers
IFSC
RATN0000156
70% Collection A/C
409886787268
100% A/C
409986315788
30% A/C
409986315783
Birla Ojasvi — details
Total units
615
Total cost
₹635.14 Cr
Project start
2025-01-12
Proposed completion
2031-01-11
Address
Birla Trimaya, B.K. Halli Road, Akkalenahalli-Mallenahalli Village, Devanahalli Taluk, Bangalore Rural District-562110
Down by the Water — details
Total units
602
Total cost
₹1096.77 Cr
Project start
2024-07-01
Proposed completion
2031-05-31
Address
Survey Nos. 226/2,227/1,227/2,228/1,228/2,239/2b,241,353,354/1 SIR MVIT COLLEGE ROAD , BETTAHALASURU VILLAGE, JALA HOBLI, , BANGALORE , Bengaluru North , Bengaluru Urban.