Compare / Sattva Lumina vs Sobha Hamptons -Townpark Phase 2 W1 to 3

Sattva Lumina vs Sobha Hamptons -Townpark Phase 2 W1 to 3

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
1 complaint · 30% built
Sattva Resi Private Limited PRM/KA/RERA/1251/472/PR/060924/007009
0 complaints · 11% built
SOBHA LIMITED PRM/KA/RERA/1251/308/PR/230125/007418
Sattva Lumina
Construction
30%
as of Q2 2026-27
Sold
903
of 1553 · +107 last qtr
Available
650
Sobha Hamptons -Townpark Phase 2 W1 to 3
Construction
11%
as of Q2 2026-27
Sold
250
of 492 · +2 last qtr
Available
244
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
Sattva Lumina
Complaints
1
on this project · 2 on Sattva Resi Private Limited overall
Sobha Hamptons -Townpark Phase 2 W1 to 3
Complaints
0
on this project · 225 on SOBHA LIMITED overall
Builder track record
Across each promoter's other K-RERA registered projects
Sattva Lumina
Sattva Resi Private Limited
8 other projects on K-RERA · 1 delivered (100% complete) · avg 35.7% complete · 1 complaint across those projects
Sobha Hamptons -Townpark Phase 2 W1 to 3
SOBHA LIMITED
37 other projects on K-RERA · 9 delivered (100% complete) · avg 57.7% complete · 59 complaints across those projects
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
Sattva Lumina
Delay risk trending ~12 month(s) past declared completion
Promoter pattern 4 of 6 other projects show the same delay-risk pattern
Sobha Hamptons -Townpark Phase 2 W1 to 3
Promoter pattern 1 of 36 other projects show the same delay-risk pattern
Sattva Lumina — escrow account details
Bank
YES BANK
Branch
Kasturba Road
IFSC
YESB0000022
70% Collection A/C
002272400000111
100% A/C
002272500000181
30% A/C
002281400007429
Sobha Hamptons -Townpark Phase 2 W1 to 3 — escrow account details
Bank
KOTAK MAHINDRA BANK
Branch
MG Road, Bangalore
IFSC
KKBK0008066
70% Collection A/C
0249886274
100% A/C
0249886298
30% A/C
0249886304
Sattva Lumina — details
Total units
1553
Total cost
₹1066.75 Cr
Project start
2024-11-01
Proposed completion
2029-11-01
Address
Sy. No.20/2, 20/3, 20/4, 20/5, 28/2, 28/4, 28/5, 29/1, 30/1, 30/2, 30/3, 30/4 and 30/5 of Rajanukunte Village , Hesaraghatta Hobli, Yelahanka Taluk , Yelahanka , Bengaluru Urban, Karnataka - 560064
Sobha Hamptons -Townpark Phase 2 W1 to 3 — details
Total units
492
Total cost
₹1005.29 Cr
Project start
2027-07-01
Proposed completion
2033-06-30
Address
Sy No. 107(P), 115/2, 115/3, 115/4, 115/5, 116/3 situated at Nagondanahalli village and Sy No. 30/1, 30/6, Situated at Hagadur Village, K.R.Puram Hobli