Compare / SURYANAGAR PHASE - 4 vs Nambiar District 25 Phase 3

SURYANAGAR PHASE - 4 vs Nambiar District 25 Phase 3

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
Active
EXECUTIVE ENGINEER KHB PRM/KA/RERA/1251/308/PR/230425/007686
On track · 0% built
Nambiar EnsembleResidential Projects LLP PRM/KA/RERA/1251/308/PR/260526/008686
SURYANAGAR PHASE - 4
No quarterly filings found for SURYANAGAR PHASE - 4 yet — construction progress and sales data aren't available on K-RERA.
Nambiar District 25 Phase 3
Construction
0%
as of Q1 2026-27
Sold
97
of 1202 · +97 last qtr
Available
1105
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
SURYANAGAR PHASE - 4
Complaints
0
on this project · 2 on EXECUTIVE ENGINEER KHB overall
Nambiar District 25 Phase 3
Complaints
0
on this project · 2 on Nambiar EnsembleResidential Projects LLP overall
Builder track record
Across each promoter's other K-RERA registered projects
SURYANAGAR PHASE - 4
EXECUTIVE ENGINEER KHB
No other K-RERA registered projects on file for this promoter.
Nambiar District 25 Phase 3
Nambiar EnsembleResidential Projects LLP
2 other projects on K-RERA · 0 delivered (100% complete) · avg 15.5% complete · 2 complaints across those projects
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
SURYANAGAR PHASE - 4
No risk signals from filed quarters.
Nambiar District 25 Phase 3
Promoter pattern 1 of 2 other projects show the same delay-risk pattern
SURYANAGAR PHASE - 4 — escrow account details
Bank
Union Bank of India
Branch
JIGANI
IFSC
UBIN0912883
70% Collection A/C
520101255104888
100% A/C
520101255104888
30% A/C
520101255104888
Nambiar District 25 Phase 3 — escrow account details
Bank
RATNAKAR BANK
Branch
Residency Road
IFSC
RATN0000156
70% Collection A/C
409160649371
100% A/C
409160649370
30% A/C
409160649372
SURYANAGAR PHASE - 4 — details
Total cost
₹3054.55 Cr
Project start
2021-06-21
Proposed completion
2030-12-31
Address
Bagganadoddi, Indlavadi & Kadujakkanahallli Village , Jigani hobli, Anekal Taluk, Bengaluru , Anekal , Bengaluru Urban, Karnataka - 562106
Nambiar District 25 Phase 3 — details
Total units
1202
Total cost
₹1885.75 Cr
Project start
2026-07-15
Proposed completion
2032-02-29
Address