Compare / THE GROOVE vs ESD KANASU

THE GROOVE vs ESD KANASU

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
THE GROOVE
Kolar · Bengaluru South
On track · 68% built
SAGE VENTURES PRM/KA/RERA/1265/347/PR/110725/007913
ESD KANASU
Mysore · Bengaluru South
On track · 88% built
EVANTHA SRI DURGA BUILDERS LLP PRM/KA/RERA/1268/378/PR/051125/008224
THE GROOVE
Construction
68%
as of Q1 2026-27
Sold
of ? · +0 last qtr
Available
0
ESD KANASU
Construction
88%
as of Q1 2026-27
Sold
of ? · +0 last qtr
Available
0
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
THE GROOVE
Complaints
0
on this project
ESD KANASU
Complaints
0
on this project
Builder track record
Across each promoter's other K-RERA registered projects
THE GROOVE
SAGE VENTURES
No other K-RERA registered projects on file for this promoter.
ESD KANASU
EVANTHA SRI DURGA BUILDERS LLP
No other K-RERA registered projects on file for this promoter.
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
THE GROOVE
No risk signals from filed quarters.
ESD KANASU
Escrow 1 quarter(s) withdrawn with no matching progress
THE GROOVE — escrow account details
Bank
HDFC
Branch
C V RAMAN NAGAR
IFSC
HDFC0004716
70% Collection A/C
50200111954574
100% A/C
50200100466295
30% A/C
50200112122438
ESD KANASU — escrow account details
Bank
HDFC
Branch
Jayanagar 4th T Block
IFSC
HDFC0001226
70% Collection A/C
50200113933723
100% A/C
50200113908656
30% A/C
50200071226977
THE GROOVE — details
Total cost
₹21.94 Cr
Project start
2024-12-06
Proposed completion
2027-02-05
Address
ANCHEMUSKUR VILLAGE, LAKKUR HOBLI, MALUR TALUK , CHIKKA TIRUPATHI VILLAGE PANCHAYAT , Maluru , Kolar, Karnataka - 563160
ESD KANASU — details
Total cost
₹21.63 Cr
Project start
2025-09-01
Proposed completion
2027-12-31
Address
Sy no 52, K Hemmanahalli Village , Ilavala Hobli , MYSORE , Mysore, Karnataka - 571130