Compare / Sobha Neopolis Phase 4 - 3, 4, 8 & 9 vs Eaton Park @ The Prestige City

Sobha Neopolis Phase 4 - 3, 4, 8 & 9 vs Eaton Park @ The Prestige City

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
4 complaints · 39% built
SOBHA LIMITED PRM/KA/RERA/1251/446/PR/220923/006283
On track · 8% built
PRESTIGE PROJECTS PRIVATE LIMITED PRM/KA/RERA/1251/308/PR/180326/008537
Sobha Neopolis Phase 4 - 3, 4, 8 & 9
Construction
39%
as of Q2 2026-27
Sold
319
of 376 · +13 last qtr
Available
55
Eaton Park @ The Prestige City
Construction
8%
as of Q2 2026-27
Sold
247
of 366 · +80 last qtr
Available
65
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
Sobha Neopolis Phase 4 - 3, 4, 8 & 9
Complaints
4
on this project · 225 on SOBHA LIMITED overall
Eaton Park @ The Prestige City
Complaints
0
on this project · 16 on PRESTIGE PROJECTS PRIVATE LIMITED overall
Builder track record
Across each promoter's other K-RERA registered projects
Sobha Neopolis Phase 4 - 3, 4, 8 & 9
SOBHA LIMITED
37 other projects on K-RERA · 9 delivered (100% complete) · avg 56.9% complete · 55 complaints across those projects
Eaton Park @ The Prestige City
PRESTIGE PROJECTS PRIVATE LIMITED
7 other projects on K-RERA · 3 delivered (100% complete) · avg 79.2% complete · 7 complaints across those projects
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
Sobha Neopolis Phase 4 - 3, 4, 8 & 9
Promoter pattern 1 of 36 other projects show the same delay-risk pattern
Eaton Park @ The Prestige City
Escrow 1 quarter(s) withdrawn with no matching progress
Promoter pattern 1 of 6 other projects show the same delay-risk pattern
Sobha Neopolis Phase 4 - 3, 4, 8 & 9 — escrow account details
Bank
KOTAK MAHINDRA BANK
Branch
MG road
IFSC
KKBK0008066
70% Collection A/C
2349105606
Eaton Park @ The Prestige City — escrow account details
Bank
ICICI Bank
Branch
M G Road Bengaluru
IFSC
ICIC0000002
70% Collection A/C
777705283829
100% A/C
777705293930
30% A/C
777705191222
Sobha Neopolis Phase 4 - 3, 4, 8 & 9 — details
Total units
376
Total cost
₹589.50 Cr
Project start
2024-04-01
Proposed completion
2031-12-31
Address
Balagere, Bangalore
Eaton Park @ The Prestige City — details
Total units
366
Total cost
₹718.11 Cr
Project start
2026-04-01
Proposed completion
2030-06-30
Address
SY NOS 13/2, 30/1 (P), 30/2, 32, 33/1, 33/2, 33/3, 34/1, 36(P), 38/2, 39/2, 40/1, 40/2, 40/3, 41/1, 41/2, 41/2, 41/3, 42, 43/1, 43/2, 43/3, 44/1A, 44/1B, 44/2, 44/3, 45/1, 45/2, 46/1A, 46/1B, 46/1C, 46/1D, 46/2, 47/1, 47/2, 47/3, 47/4, 48/1, 48/2, 48/3, 49,50/1 TO 5, 51, 52/1 TO 4 , 53/1, 53/1B, 53/2, 54, 59/1,70/2&3, 70/4, 70/5, 71/1, 71/2, , BENGALURU