Compare / Sobha Neopolis Phase 4 - 3, 4, 8 & 9 vs Fernvale @ The Prestige City

Sobha Neopolis Phase 4 - 3, 4, 8 & 9 vs Fernvale @ The Prestige City

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
4 complaints · 37% built
SOBHA LIMITED PRM/KA/RERA/1251/446/PR/220923/006283
On track · 9% built
PRESTIGE PROJECTS PRIVATE LIMITED PRM/KA/RERA/1251/308/PR/110326/008519
Sobha Neopolis Phase 4 - 3, 4, 8 & 9
Construction
37%
as of Q1 2026-27
Sold
306
of 376 · +9 last qtr
Available
68
Fernvale @ The Prestige City
Construction
9%
as of Q1 2026-27
Sold
295
of 387 · +24 last qtr
Available
92
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
Sobha Neopolis Phase 4 - 3, 4, 8 & 9
Complaints
4
on this project · 224 on SOBHA LIMITED overall
Fernvale @ The Prestige City
Complaints
0
on this project · 11 on PRESTIGE PROJECTS PRIVATE LIMITED overall
Builder track record
Across each promoter's other K-RERA registered projects
Sobha Neopolis Phase 4 - 3, 4, 8 & 9
SOBHA LIMITED
36 other projects on K-RERA · 9 delivered (100% complete) · avg 53.0% complete · 51 complaints across those projects
Fernvale @ The Prestige City
PRESTIGE PROJECTS PRIVATE LIMITED
7 other projects on K-RERA · 1 delivered (100% complete) · avg 71.2% complete · 5 complaints across those projects
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
Sobha Neopolis Phase 4 - 3, 4, 8 & 9
Promoter pattern 2 of 35 other projects show the same delay-risk pattern
Fernvale @ The Prestige City
Promoter pattern 4 of 6 other projects show the same delay-risk pattern
Sobha Neopolis Phase 4 - 3, 4, 8 & 9 — escrow account details
Bank
KOTAK MAHINDRA BANK
Branch
MG road
IFSC
KKBK0008066
70% Collection A/C
2349105606
Fernvale @ The Prestige City — escrow account details
Bank
ICICI Bank
Branch
MG Road Bangalore
IFSC
ICIC0000002
70% Collection A/C
777705304031
100% A/C
777705314132
30% A/C
777705191222
Sobha Neopolis Phase 4 - 3, 4, 8 & 9 — details
Total units
376
Total cost
₹589.50 Cr
Project start
2024-04-01
Proposed completion
2031-12-31
Address
Sy No. 107(P), 115/2, 115/3, 115/4, 115/5, 116/3 situated at Nagondanahalli village and Sy No. 30/1, 30/6, Situated at Hagadur Village, K.R.Puram Hobli
Fernvale @ The Prestige City — details
Total units
387
Total cost
₹476.65 Cr
Project start
2026-04-01
Proposed completion
2030-03-31
Address
SY NOS 13/2, 30/1 (P), 30/2, 32, 33/1, 33/2, 33/3, 34/1, 36(P), 38/2, 39/2, 40/1, 40/2, 40/3, 41/1, 41/2, 41/2, 41/3, 42, 43/1, 43/2, 43/3, 44/1A, 44/1B, 44/2, 44/3, 45/1, 45/2, 46/1A, 46/1B, 46/1C, 46/1D, 46/2, 47/1, 47/2, 47/3, 47/4, 48/1, 48/2, 48/3, 49,50/1 TO 5, 51, 52/1 TO 4 , 53/1, 53/1B, 53/2, 54, 59/1,70/2&3, 70/4, 70/5, 71/1, 71/2, , BENGALURU